ELCPartially AllowedEnvironment and Land Case Civil Suit E023 of 2022· [2023] KEELC 18438 (KLR)

Ndindiri v Irimu & 3 others

Environment and Land Court
29 June 2023
2,199 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~9 min to read original · ~4 min brief

The bottom line

#

A Nairobi court awarded a landowner Kshs 31 million after neighbours blocked her construction, but she still had to prove her case despite their absence.

What this practically means

#

Executive summary

#
The plaintiff, registered proprietor of L.R. No. Nairobi Block 110/425 at Garden Estate, sued four defendants for permanent injunction and compensation after her town-house construction project was suspended for 67 days (September 11 to November 17, 2021). She averred the defendants, officials of Eastern Thome Self Help Group, obtained exparte orders in CM ELC No. E327 of 2021 stopping construction; that suit was dismissed on November 17, 2021. Her contractor, Full Mark Building Kenya Limited, quantified losses at Kshs 31,172,537.59 through the project quantity surveyor, which the plaintiff settled. Three witnesses testified for the plaintiff; the defendants, though filing a statement of defence, neither participated in the trial nor filed submissions. The court framed two issues: whether the plaintiff proved her case to the required standard, and whether she was entitled to the orders sought. Relying on Bilsah Matiangi, Kirugi v Kabiya and Gichinga Kibutha, the court held that although uncontroverted evidence is not automatic proof, the plaintiff had discharged her burden on a balance of probabilities: ownership was undisputed, the suspension was unjustified, and the losses were quantified. Judgment was entered for the plaintiff: a permanent injunction restraining the defendants from interfering with access to the site, and payment of Kshs 31,172,537.59 as compensation. Notably, despite success, each party was directed to bear its own costs given the defendants' non-participation. The final orders contain a material typographical error describing the compensation period as ending September 17, 2021 rather than November 17, 2021.

Key legal issues

#
01

Whether the plaintiff proved her case despite the defendants' non-participation

Holding

Yes - the plaintiff proved ownership of the suit property and that the defendants caused the suspension of her project without justification, to the required standard.

Reasoning

The defendants filed a statement of defence but called no witnesses, leaving the plaintiff's testimony unrebutted. The court noted, however, that uncontroverted evidence is not automatic; the plaintiff still bore the burden of proof on a balance of probabilities. Evidence showed the plaintiff was the registered proprietor of L.R. No. Nairobi Block 110/425, that her project was suspended for 67 days, and that losses of Kshs 31,172,537.59 were quantified by the project quantity surveyor. No cogent explanation was offered by the defendants.

02

Whether the plaintiff was entitled to a permanent injunction and compensation

Holding

Yes - both the permanent injunction and compensation of Kshs 31,172,537.59 were granted as prayed.

Reasoning

The evidence showed the defendants, through their servants and agents, blocked the contractor from accessing the property, halting construction and causing losses. The quantity surveyor quantified the losses at Kshs 31,172,537.59 and, absent controverting evidence, the court was satisfied the claim was proved. Invoking equitable principles, the court found no basis to deny the reliefs sought and entered judgment for the plaintiff on both heads.

p. 5

Legal principles established

#
  • Uncontroverted evidence is not automatic proof; the plaintiff must still prove the case on a balance of probabilities even where the defendant does not participate.

Court orders

#
  1. 1.A permanent injunction issued against the Defendants, their agents, servants and/or employees from interfering with or denying the Plaintiff's contractors, employees and/or servants' access to the construction site on plot L.R. No. 110/425 located at Garden Estate.
  2. 2.Payment of Kshs 31,172,537.59 to the Plaintiff by the Defendants as compensation for losses incurred as a result of suspension of the project.
  3. 3.Each party to bear own costs of the suit.
Jurisdiction invoked
Environment and Land Court Act, section 13 (including 13(7)(c) and (d))

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Ndindiri v Irimu & 3 others", Case Analysis (2023). Environment and Land Case Civil Suit E023 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/18438/eng@2023-06-29

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.