The bottom line

#

Kenyan developers cannot delay giving unit owners their management company shares until every unit is sold — the law kicks in much sooner.

What this practically means

#

Executive summary

#
This ruling by the Environment and Land Court at Nairobi (O. A. Angote, J) determines the Plaintiffs' application dated 11th February 2022 in a suit by four purchasers of units in Nextgen Commercial Center on L.R. No. 209/18648, Nairobi. The Plaintiffs sought leave to incorporate a management company of unit owners and an order of inhibition against dealings with the property, contending that the developer, Nextgen Office Suites Limited, had frustrated conversion of long-term sub-leases into sectional titles and failed to establish a management corporation with unit owners as members, as required by the Sectional Properties Act, 2020 and the Sectional Properties Regulations, 2021. The 1st Defendant opposed on three grounds: the prayers were not anchored in the main suit; the suit was a defective representative suit brought without authority of over 400 unit owners; and the suit was not ripe because not all units had been transferred, with the property allegedly exempt as a large mixed-use development under Regulation 22. The court held the suit was not representative; that the 1st Defendant's admission of an intention to transfer reversionary interest to Nextgen Management Limited brought the premises within Regulation 18(c); that the commercial center was a distinct development so Regulation 22 did not apply; and that a developer cannot contract out of the Act by deferring share allotment until all leases are registered. Finding prima facie non-compliance, the court granted leave to incorporate a Corporation of unit owners, inhibited the 1st Defendant from dealing with the property except for establishing the corporation and converting leases, and ordered the 1st Defendant to pay the costs of the application.

Key legal issues

#
01

Whether the suit is a representative suit requiring compliance with Order 1 Rule 8

Holding

The suit is not a representative suit; the Plaintiffs filed it as individual purchasers of units, and the mere fact that orders may affect other purchasers does not convert it into a representative suit.

Reasoning

The court read the Plaint and found the Plaintiffs sued in their own capacity as purchasers of units in Nextgen Commercial Center. Although their interests may be similar to other purchasers, the suit does not meet the requirements of a representative suit under Order 1 of the Civil Procedure Rules, and the potential effect of orders on other purchasers cannot change its character.

p. 5
02

Whether the Plaintiffs' rights under Regulation 18 of the Sectional Properties Regulations 2021 had crystallised

Holding

The rights had crystallised because the 1st Defendant admitted an intention to transfer the reversionary interest to Nextgen Management Limited, bringing the premises within Regulation 18(c).

Reasoning

Regulation 18(c) applies where part of the units have been transferred and the reversionary interest is by written agreement intended to be transferred to the management company to hold in trust for owners. The 1st Defendant's own affidavit admitted that all management companies would be given one share in Nextgen Management Limited to which reversionary interest would be transferred, satisfying Regulation 18(c) once a unit is sold.

p. 7
03

Whether the suit property is exempt as a large mixed-use development under Regulation 22

Holding

Regulation 22 does not apply because the commercial center is a distinct, well-delineated development with its own management company, albeit sharing one mother title with the residential apartments.

Reasoning

The 1st Defendant's own affidavit disclosed separate management companies for the different developments: Ruby Tower and Sapphire Tower for residential blocks and Nextgen Mall Management Company for the commercial centre. The Plaintiffs' interest is confined to the commercial center, which is distinct from the apartments, so the mixed-use exemption under Regulation 22 is inapplicable.

p. 8
04

Whether the developer can defer issuing share certificates until all leases are registered

Holding

No; the Act obliges the developer to comply once units are sold, and contractual terms deferring compliance are contrary to the spirit and letter of the Act.

Reasoning

Section 27 requires the developer to convene a corporation meeting within ninety days of 50% of units being sold or 180 days of the first sale, whichever is sooner. The court held that it is not for the developer to decide how many units to sell before complying with the Act, and that the standard contract term conditioning share allotment on registration of all leases was unlawful.

p. 8
05

Whether conservatory orders (leave to incorporate a corporation and inhibition) should issue

Holding

Yes; the 1st Defendant has prima facie failed to comply with the Sectional Properties Act and should be inhibited from dealing with the premises other than to establish the Corporation and convert leases.

Reasoning

The court found that until a Corporation is registered with all unit owners as shareholders, conversion of the property into sectional units cannot commence. The 1st Defendant's prima facie non-compliance threatened the substratum of the suit, justifying leave to incorporate a corporation and an inhibition preserving the property pending full determination.

p. 10

Legal principles established

#
  • Membership of a sectional management corporation is not dependent on the developer selling all units; owners become shareholders the moment their leases are registered.
  • A developer cannot, by contract, defer compliance with the Sectional Properties Act by conditioning share allotment on registration of all leases.
  • Where details of unit purchasers are within the developer's knowledge and it fails to disclose them, the court presumes all units have been sold.

Court orders

#
  1. 1.Pending the hearing and determination of the suit, the Plaintiffs granted leave to incorporate a Corporation of Nextgen Commercial Center on L.R. No. 209/18648, Nairobi, with membership drawn from all owners/purchasers of units, to manage common areas and common interests in compliance with the Sectional Properties Act, 2020
  2. 2.Other than establishing the Management Company/Corporation and conversion of all leases into sectional units, the 1st Defendant inhibited from dealing with Nextgen Commercial Center on L.R. No. 209/18648 pending hearing and determination of the suit
  3. 3.The 1st Defendant to pay the costs of the application

Authorities

#

Legislation

  • Constitution of Kenya, 2010Article 40
  • Sectional Properties Act, 2020Sections 4(1), 4(3), 13(1), 13(2), 17(1)-(6), 20, 27, 28
  • Sectional Properties Regulations, 2021Regulations 18, 22
  • Land Registration Act, 2012Section 54(5), Section 68
  • Civil Procedure RulesOrder 1 Rule 8, Order 40
  • Insolvency Act
  • Companies Act, 2015

Cases cited (10)

  • Vincent A. Chokaa & Another vs Changdu Guangling Kenya Co. Ltd & 3 Others
    [2016] eKLR

    Plaintiffs' submissions on management company control and service charge

  • Nyamira F.C.S vs The Chief Land Registrar & Another
    [2005] eKLR

    1st Defendant's submissions on inhibition orders

  • Yang Guang Property Design & Manufacturing Limited vs China Wu Yi Company (K) Ltd
    [2021] eKLR

    1st Defendant's submissions on inhibition orders

  • Margaret Rachel Mbogo & Another vs Robert Njoki Muthara & Another
    [2021] eKLR

    1st Defendant's submissions on inhibition orders

  • Yiapas Ole Seese & 4 Others vs Sakita Ole Narok & 2 Others
    [2008] eKLR

    Requirements for representative suits

  • Kahindi Katana Mwango & Another vs Cannon Assurance (K) Ltd
    [2013] eKLR

    Requirements for representative suits

  • Republic vs National Employment Authority & 3 Others ex-parte Middle East Consultancy Services Ltd
    [2018] eKLR

    Doctrine of ripeness - readiness of a case for litigation

  • Republic vs Kenya School of Law & Another Ex-parte Kithinji Maseka Semo & Another
    [2019] eKLR

    Interpretation of statutes

  • Jan Bolden Nielsen vs Herman Philipus Steya also known as Hermannus Philipus Steyn & 2 Others
    [2012] eKLR

    Threshold for injunctive/inhibition orders

  • Abbott Laboratories vs Gardner

    Two-part test for assessing ripeness challenges

Jurisdiction invoked
Original jurisdiction of the Environment and Land Court over land and developments on land (interlocutory application in a pending suit)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kanyi & 3 others v Nextgen Office Suites Limited & 4 others", Case Analysis (2023). Environment & Land Case E063 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/16434/eng@2023-03-16

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.