Karinga & 4 others v Ngure
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Validity of the agreement for sale of villas
A valid written agreement existed, satisfying section 3(3) of the Contract Act, evidenced by signed agreements, letters of offer, cheques, RTGS transfers and acknowledgments
The court applied section 3(3) of the Contract Act requiring contracts for disposition of an interest in land to be in writing, signed by all parties and attested by a witness. The Plaintiffs produced signed sale agreements executed on 16th August 2012, letters of offer, copies of cheques, RTGS transfers, cash deposit slips and signed acknowledgments by the Defendant, none of which was disputed, establishing a valid agreement.
Breach of the agreement by the Defendant
The Defendant breached the agreement by failing to complete construction of the villas despite receiving Kshs 53,235,000.00
The Plaintiffs particularized the breach as failure to complete construction of the villas and hotel, delay without reasonable excuse, misleading the Plaintiffs on progress, and failure to refund monies paid. PW1 testified the project remained incomplete since 2013 despite substantial payments. The court found the Defendant, having been paid Kshs 53,235,000.00, refused and/or neglected to complete construction, constituting breach.
Entitlement to compensation for breach
The Plaintiffs are entitled to a refund of Kshs 53,235,000.00 plus interest at 14% from the date of payment until payment in full, per the default clause
Relying on Hadley v Baxendale and Perpetua Atieno v Louis Onyango Otieno, the court held that a purchaser upon vendor's repudiation recovers the return of deposits with interest and expenses within the parties' contemplation. Clause 11 of the sale agreement was a default clause for failure to complete. Having found a valid agreement and breach, the court awarded the refund with 14% interest and costs.
Legal principles established
#- Uncontroverted evidence must still be interrogated; a plaintiff must prove its case on a balance of probability whether the evidence is unchallenged or not
- Where a vendor wrongfully refuses to complete, damages include return of any deposit paid with interest and other expenses within the contemplation of the parties
Court orders
#- 1.Declaration that the Defendant is in breach of the contract in relation to the construction of Coco Bahari Villas on LR Number MN/III/1848
- 2.Refund of Kshs 53,235,000.00 paid to the Defendant by the Plaintiffs
- 3.Interest at 14% per annum on the refund from the date of payment until payment in full
- 4.Costs of the suit to the Plaintiffs
- Jurisdiction invoked
- Original civil jurisdiction of the Environment and Land Court over contracts for disposition of interests in land
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Karinga & 4 others v Ngure", Case Analysis (2023). Environment & Land Case 71 of 2021. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/16210/eng@2023-03-14
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.