ELCDismissedEnvironment & Land Case E014 of 2021· [2023] KEELC 15784 (KLR)

Drum Major Properties Limited v Kenya National Highways Authority & another; Nyange (Interested Party)

Environment and Land Court
22 February 2023
5,162 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~21 min to read original · ~4 min brief

The bottom line

#

A Kenyan court allowed KeNHA to withhold Kshs 49 million in land compensation because an unresolved ownership dispute between a director and his ex-wife was pending.

What this practically means

#

Executive summary

#
Drum Major Properties Limited, registered owner of Mavoko Town Block 64/534 at Athi River, sued KeNHA and the National Land Commission by Originating Summons seeking payment of Kshs 49,116,836 awarded as compensation for a portion compulsorily acquired for the second carriageway of the Athi River-Machakos Turnoff (A109) Road, plus interest at 12% per annum from the date of the award, and a temporary injunction against interference with the property. KeNHA acknowledged the award, stating it had remitted the funds to the NLC, but explained that payment was withheld because of an ownership dispute between the Plaintiff's director, Mutuku Kilewe, and Tecla Mwake Nyange, his former wife, who claimed the property was matrimonial property irregularly transferred to the company and was the subject of pending proceedings (Nairobi HC OS No 37 of 2013). The NLC relied on Section 115(c) of the Land Act, which permits withholding compensation where there is a dispute as to the persons entitled or their shares. Nyange was joined as an Interested Party and sought a stay pending determination of the matrimonial cause. The court framed two issues: whether the Defendants should be compelled to pay the award plus interest, and whether they were justified in withholding payment. Applying Article 40 of the Constitution, the Land Act and the Supreme Court's decision in Attorney General v Zinj Limited, the court held that the pending ownership dispute engaged Section 115(c), justifying withholding of the funds. It further found the Plaintiff had concealed material facts - the Interested Party's objections since 2018 and an injunction against its director - and had filed suit in bad faith. The suit was dismissed with costs to the Defendants and the Interested Party, and the Defendants were ordered to take vacant possession of the suit property to allow the road project to proceed.

Key legal issues

#
01

Whether the NLC was justified in withholding the compensation award

Holding

Yes - Section 115(c) of the Land Act permits withholding where there is a dispute as to entitlement or shares, and the Interested Party's pending matrimonial property claim (Nairobi HC OS No 37 of 2013) constitutes such a dispute.

Reasoning

The court found no dispute that the owner was entitled to the assessed sum; the dispute was over ownership. The Interested Party claimed joint acquisition of the property in 2004 during her marriage to the Plaintiff's majority shareholder, a claim pending before the family court. The Defendants agreed payment could not be made until that dispute was resolved. Section 115(c) expressly excepts such disputes from the duty of prompt payment.

p. 6
02

Whether the Plaintiff was entitled to the injunction and to compel payment

Holding

No - the Plaintiff concealed material facts, including the pending matrimonial suit and an injunction restraining its director from dealing with the property, and filed suit in bad faith.

Reasoning

The court found that from as early as 2018 the Interested Party had objected in writing to payment to the Plaintiff, and had obtained an injunction restraining Mutuku Kilewe from dealing with the suit property in Civil Suit No XX of 2013 (OS). The Plaintiff disclosed neither fact and did not join the Interested Party initially. This non-disclosure disentitled the Plaintiff to equitable relief and justified dismissal.

03

Whether the Defendants should take possession of the suit property

Holding

Yes - having valued the property and sought to proceed with the project, the Defendants were allowed to take vacant possession given the public interest in timely completion of the road.

Reasoning

The 1st Defendant demonstrated the need to complete the project in time to avoid detrimental contractual consequences prejudicial to the taxpayer. Having sought to be allowed to proceed with construction, and the compensation having been assessed and preserved, the court ordered the Defendants to take vacant possession of the suit property.

p. 9

Legal principles established

#
  • Where there is a dispute as to the right of persons entitled to compensation or as to the shares in which compensation is to be paid, the National Land Commission is not obligated to pay until the dispute is determined (Section 115(c) of the Land Act).
  • Deprivation of property through compulsory acquisition must be accompanied by prompt, full and just compensation under Article 40 of the Constitution and the Land Act.

Court orders

#
  1. 1.The Plaintiff's suit is dismissed with costs to the Defendants and the Interested Party
  2. 2.The Defendants are to take vacant possession of the suit property to allow completion of the road project
Jurisdiction invoked
Article 40 of the Constitution and the Land Act (compulsory acquisition and compensation); Environment and Land Court jurisdiction

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#