ELCPartially AllowedELC No. 82 of 2019· [2023] KEELC 825 (KLR)

Clairmont Investment Limited v China Communication Construction – Company Limited (Environment & Land Case 82 of 2019) [2023] KEELC 825 (KLR)

Environment and Land Court
16 February 2023
834 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~3 min to read original · ~4 min brief

The bottom line

#

A Kajiado court awarded a landowner Kshs 4.7 million for trespass, but far less than claimed, because he could not prove his higher valuation or projected rental income.

What this practically means

#

Executive summary

#
The plaintiff, owner of land reference No. Kajiado/Kitengela 16766 (0.3400 hectares), sued the defendant for trespass, alleging that in 2016 the defendant entered the land without authority and constructed a septic tank and open sewage treatment pits. The plaintiff claimed Kshs 19,027,775, comprising current market value of Kshs 12,500,000, disturbance at 15%, loss of rental/profit at Kshs 150,000 per month from July 2016 to December 2018, and valuation charges, plus general and exemplary damages. The defendant denied the averments and filed a valuation by its valuer, Bernard M. Nzau, placing the land value at Kshs 6,000,000, the affected portion at Kshs 3,000,000 and rental value at Kshs 40,000 per month. At trial the plaintiff called two witnesses, including valuer Dominic Mutua Muoka, while the defendant called Mr Nzau, who disputed the plaintiff's valuation. The court found the trespass not disputed but was confronted with two conflicting valuation reports. It preferred the report with the lower figures, criticising the plaintiff for not filing a third report after being served with the defendant's report. The court also found the plaintiff had not proved readiness, resources or approved plans to build apartments earning Kshs 150,000 per month, and noted that neither party proved the duration of the trespass. Judgment was entered for the plaintiff at Kshs 4,740,000: Kshs 3,000,000 for the value of the land occupied by the abandoned septic development, Kshs 1,440,000 as lost rent for three years at Kshs 40,000 per month, and Kshs 300,000 for trespass, plus costs of the suit.

Key legal issues

#
01

Trespass onto the suit land

Holding

Trespass was established as it was not disputed

Reasoning

The court found that the defendant built a septic tank and open sewage treatment pits on the plaintiff's land in 2016 without authority. The defendant did not dispute the trespass itself; the dispute was confined to valuation and quantum of damages.

p. 3
02

Conflicting valuation reports

Holding

The court adopted the lower (defendant's) figures

Reasoning

Both parties filed valuations that conflicted. The plaintiff did not respond to the defendant's valuation with a further report, and the court held that the failure preponderated against the plaintiff, so the defendant's lower valuation was preferred.

p. 2
03

Claim for loss of profit/rental at Kshs 150,000 per month

Holding

Not proved; instead Kshs 40,000 per month for 3 years awarded

Reasoning

The plaintiff did not prove capacity or approved plans for apartments generating Kshs 150,000 monthly, nor the duration of the trespass. The court instead adopted the defendant's valuer's rental figure of Kshs 40,000 per month over an assumed 3-year period.

p. 3
04

Duration of the trespass

Holding

Neither party proved the duration

Reasoning

The court noted the absence of evidence on how long the trespass lasted, an omission by both sides, which affected the assessment of lost rent; it nonetheless adopted a 3-year period at the defendant's rental rate.

p. 3

Legal principles established

#
  • Where two conflicting expert valuation reports are filed, the court may prefer the one with the lower figures, and a party whose report is disputed should file a further report to preponderate its case
  • Loss of projected rental income must be proved by showing readiness, ability, resources and approved plans for the intended development

Court orders

#
  1. 1.Judgment for the plaintiff in the sum of Kshs 3,000,000 being the value of the land occupied by the abandoned septic development
  2. 2.Kshs 1,440,000 being value of lost rent for 3 years at Kshs 40,000 per month
  3. 3.Kshs 300,000 for trespass; total award of Kshs 4,740,000
  4. 4.Plaintiff awarded costs of the suit
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over the suit land reference No. Kajiado/Kitengela 16766

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Clairmont Investment Limited v China Communication Construction – Company Limited (Environment & Land Case 82 of 2019) [2023] KEELC 825 (KLR)", Case Analysis (2023). ELC No. 82 of 2019. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/825/eng@2023-02-16

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.