ELCOtherEnvironment & Land Case 185 of 2018· [2022] KEELC 15639 (KLR)

G Cleph Limited v Jericho Development Company Limited

Environment and Land Court
20 December 2022
714 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~3 min to read original · ~4 min brief

The bottom line

#

A Kenyan court refused a buyer's claim for Ksh. 13.6 million in interest and costs because the property transfer delay was caused by the lands registry, not the vendor.

What this practically means

#

Executive summary

#
G Cleph Limited sued Jericho Development Company Limited by plaint dated April 16, 2018, claiming that by a sale agreement dated March 7, 2016 it had purchased commercial units at The Greenhouse Office Park (grid numbers 20, 21, 22, 24, 25 on the fourth floor, penthouses 20, 22 and 24, and four parking slots) for Ksh. 39,400,000/=, which it paid in full, but the defendant failed to complete the agreement by transferring the suit properties. The plaintiff sought an order of specific performance compelling completion of registration within 14 days, interest at the late payment rate under clause 3.2 of the agreement amounting to Ksh. 13,593,000/= as at April 7, 2018 and continuing to accrue, and costs. The defendant did not enter appearance or file a defence, though represented, and was absent at the hearing. During the pendency of the suit the suit premises were transferred to the plaintiff, leaving only interest and costs for determination. PW1, a director of the plaintiff, adopted his witness statement and produced exhibits. Applying the principle that a court cannot rewrite a contract, the court found that the plaintiff's own evidence showed the draft assignment of lease had been lodged at the lands registry and stamp duty paid, placing the transaction at the registration stage, which falls within the province of government officers. The plaintiff failed to identify any specific obligation the defendant had failed to perform at that stage. The court accordingly declined to award interest or costs and marked the suit as spent with no orders as to costs.

Key legal issues

#
01

Whether the vendor's conduct warranted an award of interest and costs after the suit properties were transferred during the pendency of the suit

Holding

The court declined to award interest or costs because the transaction had reached the registration stage, which is in the province of government officers, and the plaintiff did not identify any specific obligation the defendant failed to perform at that stage

Reasoning

The plaintiff's own witness statement admitted that the draft assignment of lease was lodged at the lands registry and stamp duty was paid to the Kenya Revenue Authority. The court concluded the transaction was at the registration process stage, attributable to government officers, not the vendor. Since the plaintiff failed to point out the specific role the defendant was obligated to play at that stage, no act of commission or omission by the vendor was established to justify interest or costs.

02

Whether a court can rewrite a contract between parties

Holding

A court cannot rewrite a contract; it can only enforce what the parties executed

Reasoning

Relying on Pius Kimaiyo Langat v Co-operative Bank of Kenya Ltd, the court restated the trite principle that courts lack jurisdiction to vary or rewrite contractual terms agreed by parties. The court's role is limited to enforcing the contract as executed, in line with William Kazungu Karisa v Cosmas Angore Chanzera, which holds that parties must perform their obligations in accordance with the terms of the contract they executed.

p. 2

Legal principles established

#
  • A court cannot rewrite a contract between the parties; it can only enforce what the parties executed in the contract
  • Parties must perform their respective obligations in accordance with the terms of the contract executed by them

Court orders

#
  1. 1.The suit is marked as spent with no orders as to costs

Authorities

#

Cases cited (2)

  • Pius Kimaiyo Langat v Co-operative Bank of Kenya Ltd
    (2017) eKLR

    That a court cannot rewrite a contract between parties; it can only enforce what the parties executed

  • William Kazungu Karisa v Cosmas Angore Chanzera
    [2006] e KLR

    That parties must perform their respective obligations in accordance with the terms of the contract executed by them

Jurisdiction invoked
Environment and Land Court jurisdiction under Article 162(2) of the Constitution (implied; not expressly cited in the judgment)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "G Cleph Limited v Jericho Development Company Limited", Case Analysis (2022). Environment & Land Case 185 of 2018. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/15639/eng@2022-12-20

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.