Simalice Construction Company Ltd v Arjan & another
The bottom line
#A Kenyan court refused to freeze land sales where the only dispute was a money balance that could be repaid later.
What this practically means
#Executive summary
#Key legal issues
#Whether the applicant established a prima facie case and irreparable injury to warrant a temporary injunction
The application failed; the applicant had sold the property and received almost the entire purchase price, the 1st respondent was the registered owner, and any outstanding balance was quantifiable and recoverable in damages.
The court applied the Giella/American Cyanamid and Nguruman sequential tests. It found the sale agreement undisputed, the 1st respondent registered as owner per searches of September 28, 2022, and the only dispute a small quantifiable balance (Kshs 5,500,000 claimed vs Kshs 500,000 admitted). Damages being adequate, no irreparable harm was shown and the sequential hurdles were not crossed.
Legal principles established
#- A temporary injunction under Order 40 rule 1 requires proof that property in dispute is in danger of being wasted, damaged or alienated
- Where damages are an adequate remedy, no interlocutory injunction should be granted
Court orders
#- 1.Notice of motion application dated October 5, 2022 dismissed
- 2.Each party to bear its own costs
- Jurisdiction invoked
- Order 40 rule 1 of the Civil Procedure Rules and section 3A of the Civil Procedure Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Simalice Construction Company Ltd v Arjan & another", Case Analysis (2022). Environment & Land Case E010 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/15416/eng@2022-12-21
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.