Kiragu v Kenya Power & Lighting Company
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Whether the Energy Act, 2019 ousts the ELC's jurisdiction over the plaintiff's trespass claim via the exhaustion doctrine
No. The cause of action arose in 2012, before the Energy Act, 2019, and statutes are prima facie prospective; the dispute is one of trespass to land within the ELC's jurisdiction under Article 162 and section 13 of the ELC Act.
The court applied the presumption against retrospectivity per Samuel Kamau Macharia: the Energy Act, 2019 cannot govern a 2012 cause of action absent express words or necessary implication. It further held the dispute is not between a licensee and a third party but a land-use/trespass dispute, outside the mandate of the Energy Regulatory Commission and Energy Tribunal, and squarely within the ELC's jurisdiction under section 13(2)(e).
Nature of the dispute - trespass versus an energy-sector dispute
The dispute is one of use and occupation of land, namely trespass, not a dispute between a licensee and a third party under the Energy Act.
The plaintiff's claim is that the defendant illegally set up a way leave and laid high voltage power lines through her land without consent, causing damage and loss of user. The court characterized this as a continuing trespass actionable from day to day, falling within the ELC's jurisdiction rather than the energy-sector dispute-resolution mechanisms.
Legal principles established
#- Where a cause of action arose before the enactment of the Energy Act, 2019, that Act's exhaustion mechanisms do not apply to it.
- Continuing trespass is actionable from day to day for as long as the trespass continues.
Court orders
#- 1.The defendant's preliminary objection dated March 14, 2022 is dismissed with costs to the plaintiff
- Jurisdiction invoked
- Article 162(2)(b) of the Constitution and section 13 of the Environment and Land Court Act, 2011
Key timeline
#Practical implications
#Frequently asked questions
#Later judgments citing this (1)
#Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.
- Kenya Electricity Transmission Co Ltd (KETRACO) v Obonyo & another (Environment and Land Appeal E100 of 2025) [2026] KEELC 5353 (KLR)[2026] KEELC 5353 (KLR)31 Aug 2026followed
Cite this brief
#Cite this brief
Caselaw, "Kiragu v Kenya Power & Lighting Company", Case Analysis (2022). Environment and Land Case Civil Suit E047 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/13533/eng@2022-09-27
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.