Kimani & 10 others v Athi Water Works Development Agency & another
The bottom line
#The Environment and Land Court refused to stop the Karimenu Dam project, ruling the residents waited too long and money can compensate their losses.
What this practically means
#Executive summary
#Key legal issues
#Prima facie case with probability of success
Not established; the claim for a permanent injunction was doubtful because the project ran from 2/5/2019 to 2/5/2022 and plaintiffs filed suit when 76% of works were complete
The court noted the contractual period had lapsed and there was no evidence the impugned works were ongoing. The plaintiffs' claims related to past, quantified damages. Coming to court too late, when most works were implemented, undermined the probability that a permanent injunction would issue at trial.
Adequacy of damages
Damages would be an adequate remedy since the plaintiffs pleaded and quantified special damages and also pleaded general damages
The plaintiffs had quantified their losses in a demand letter and pleadings, making liquidated and general damages claims. Where damages are quantifiable and compensable, the second Giella limb fails and an interlocutory injunction is not normally granted.
Balance of convenience
Balance of convenience did not favour an injunction, given delay, quantified monetary claims, and prejudice to 1,000,000 water beneficiaries, taxpayers and the implementing agencies
The court listed five factors: plaintiffs waited until the project neared completion; they sought monetary compensation; an injunction would prejudice the 1,000,000 Kenyans targeted to benefit; it would prejudice Kenyan taxpayers funding the project; and implementing agencies would incur idle labour and equipment costs.
Legal principles established
#- The Giella v Cassman Brown criteria govern interlocutory injunctions: prima facie case, irreparable harm not compensable by damages, and balance of convenience in doubt
- A court considering an interlocutory injunction does not make conclusive or definitive pronouncements on the contested issues in the suit
Court orders
#- 1.The plaintiffs' notice of motion dated November 15, 2021 seeking a temporary injunction is rejected
- 2.Costs shall be in the cause
- Jurisdiction invoked
- Original jurisdiction of the Environment and Land Court over the suit (interlocutory application within ELC Case 147 of 2021)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kimani & 10 others v Athi Water Works Development Agency & another", Case Analysis (2022). Environment & Land Case 147 of 2021. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/4906/eng@2022-09-21
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.