ELCDismissedEnvironment & Land Case 147 of 2021· [2022] KEELC 4906 (KLR)

Kimani & 10 others v Athi Water Works Development Agency & another

Environment and Land Court
21 September 2022
1,531 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~6 min to read original · ~4 min brief

The bottom line

#

The Environment and Land Court refused to stop the Karimenu Dam project, ruling the residents waited too long and money can compensate their losses.

What this practically means

#

Executive summary

#
Eleven plaintiffs sued Athi Water Works Development Agency and Avic International Africa Limited over construction of the Karimenu Water Dam, alleging the works cracked their houses and business premises, collapsed boreholes and killed livestock. They sought a declaration of violation of quiet enjoyment, a permanent injunction, Kshs 18,060,000 special damages, general damages and costs. Together with the plaint they moved the court by notice of motion dated November 15, 2021 seeking a temporary injunction restraining further construction. The defendants responded that they were implementing a Government flagship project financed by a China Exim Bank loan and the Exchequer at a contract sum of Kshs 23.6 billion to supply water to 1,000,000 people in Ruiru, Juja, Gatundu and parts of Nairobi; that works ran from 2/5/2019 to 2/5/2022 with about 76% complete by February 2022; that all approvals including a NEMA EIA licence were obtained; and that an injunction would cause contractual penalties, idle labour and equipment, and prejudice the public. Applying Giella v Cassman Brown, Eboso J held the plaintiffs had no prima facie case on the permanent injunction claim since they came to court too late when most works were done and the contractual period had lapsed; damages were adequate as their claims were pleaded and quantified; and the balance of convenience favoured completion of the project. The application was rejected with costs in the cause.

Key legal issues

#
01

Prima facie case with probability of success

Holding

Not established; the claim for a permanent injunction was doubtful because the project ran from 2/5/2019 to 2/5/2022 and plaintiffs filed suit when 76% of works were complete

Reasoning

The court noted the contractual period had lapsed and there was no evidence the impugned works were ongoing. The plaintiffs' claims related to past, quantified damages. Coming to court too late, when most works were implemented, undermined the probability that a permanent injunction would issue at trial.

p. 3
02

Adequacy of damages

Holding

Damages would be an adequate remedy since the plaintiffs pleaded and quantified special damages and also pleaded general damages

Reasoning

The plaintiffs had quantified their losses in a demand letter and pleadings, making liquidated and general damages claims. Where damages are quantifiable and compensable, the second Giella limb fails and an interlocutory injunction is not normally granted.

p. 3
03

Balance of convenience

Holding

Balance of convenience did not favour an injunction, given delay, quantified monetary claims, and prejudice to 1,000,000 water beneficiaries, taxpayers and the implementing agencies

Reasoning

The court listed five factors: plaintiffs waited until the project neared completion; they sought monetary compensation; an injunction would prejudice the 1,000,000 Kenyans targeted to benefit; it would prejudice Kenyan taxpayers funding the project; and implementing agencies would incur idle labour and equipment costs.

p. 4

Legal principles established

#
  • The Giella v Cassman Brown criteria govern interlocutory injunctions: prima facie case, irreparable harm not compensable by damages, and balance of convenience in doubt
  • A court considering an interlocutory injunction does not make conclusive or definitive pronouncements on the contested issues in the suit

Court orders

#
  1. 1.The plaintiffs' notice of motion dated November 15, 2021 seeking a temporary injunction is rejected
  2. 2.Costs shall be in the cause

Authorities

#

Cases cited (1)

  • Giella v Cassman Brown Co Ltd
    1973 EA 358

    Criteria for grant of an interlocutory injunction: prima facie case, irreparable harm, balance of convenience

Jurisdiction invoked
Original jurisdiction of the Environment and Land Court over the suit (interlocutory application within ELC Case 147 of 2021)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kimani & 10 others v Athi Water Works Development Agency & another", Case Analysis (2022). Environment & Land Case 147 of 2021. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/4906/eng@2022-09-21

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.