Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCDismissedNotice of Motion dated 13th May 2021 (interlocutory application in the main suit)· [2022] KEELC 2925 (KLR)

Maria & 5 others v Kuria & 5 others (Environment & Land Case 46 of 2021) [2022] KEELC 2925 (KLR)

Environment and Land Court
23 June 2022
3,343 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~13 min to read original · ~4 min brief

The bottom line

#

Malindi's Environment and Land Court refused to stop a completed Safaricom phone mast because the applicants had no expert evidence the mast would harm them.

What this practically means

#

Executive summary

#
This is a ruling of the Environment and Land Court at Malindi (M.A. Odeny, J) on a Notice of Motion dated 13th May 2021 by the Plaintiffs, owners of Plots 2916 and 2911 Malindi adjacent to Plot 2917, seeking a permanent injunction restraining the 1st-3rd Defendants from constructing a Base Transceiver Station (BTS) tower and an order compelling the 3rd Defendant to suspend its operations pending the hearing of the main suit. The Plaintiffs argued the construction was illegal for lack of a properly issued EIA licence and prior public participation, threatening their Article 42 right to a clean and healthy environment. The 3rd Defendant contended approvals and an EIA licence were obtained after public consultation and the construction was complete; the 4th Defendant (NEMA) confirmed the project had commenced without a licence, was halted, and that the licence was subsequently issued; the 5th Defendant denied any complaint against it. The court framed two issues: the injunction threshold and costs. Applying the Giella v Cassman Brown principles, it found the construction already finalized, so orders would be issued in vain; the Plaintiffs produced no survey report or expert evidence supporting their health-risk allegations; and they failed to show irreparable injury not compensable in damages. The balance of convenience tilted against granting the injunction. The application was dismissed with costs, with directions on the hearing of the main suit.

Key legal issues

#
01

Whether the Plaintiffs met the threshold for a temporary injunction

Holding

They did not: the BTS construction was already finalized leaving nothing to restrain, and no prima facie case supported by evidence of irreparable injury was established

Reasoning

The court found the construction complete, so injunctive orders would be futile. The Plaintiffs' allegations of health risk from the mast's proximity lacked any survey report or expert evidence, the map produced not even showing the suit properties. They also failed to show injury not compensable by damages, and the balance of convenience tilted against the injunction.

p. 7
02

Whether the alleged lack of public participation and EIA licensing prior to construction vitiated the process

Holding

The court did not decide the point finally; the 3rd Defendant confirmed a license was issued in accordance with the regulations and the Plaintiffs did not establish irreparable injury

Reasoning

The 3rd Defendant deponed that public consultation forms were completed by immediate neighbours before the EIA license issued, and approvals were obtained from the 4th and 6th Defendants. The 4th Defendant confirmed the project began without a license but was halted pending licensing. The court, without going into merits at the interlocutory stage, found no demonstrated injury uncompensable by damages.

p. 7
03

Whether a permanent injunction can be granted at an interlocutory stage

Holding

The court treated the application as one for temporary injunction and declined to grant the permanent injunction sought, dismissing the application

Reasoning

The 3rd Defendant had argued that a permanent injunction cannot issue before the hearing of the main suit. The court framed the issues around temporary injunction principles and, finding no prima facie case nor irreparable injury, dismissed the application with costs and directed parties to take directions on the hearing of the main suit.

p. 6

Legal principles established

#
  • Courts do not issue orders in vain; an injunction restrains threatened or ongoing breaches and is never meant to prevent what has already occurred
  • A party seeking a temporary injunction must establish a prima facie case with a probability of success, irreparable loss/injury, and, if in doubt, balance of convenience
  • No injunction should normally be granted where damages would be an adequate remedy
  • A party alleging scientific or health-based injury must table evidence of the threat, violation or injury; he who alleges must prove

Court orders

#
  1. 1.The application for injunction dated 13th May 2021 is dismissed with costs
  2. 2.Parties to take directions on the hearing of the main suit
Jurisdiction invoked
Environment and Land Court jurisdiction over environmental claims under Articles 42 and 70 of the Constitution; interlocutory relief sought under order 40 rule 1 of the Civil Procedure Rules

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Maria & 5 others v Kuria & 5 others (Environment & Land Case 46 of 2021) [2022] KEELC 2925 (KLR)", Case Analysis (2022). Notice of Motion dated 13th May 2021 (interlocutory application in the main suit). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/2925/eng@2022-06-23

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.