ELCPartially AllowedApplication dated 19th July 2021 (arising from 1st and 2nd Interested Parties' Application dated 27th January 2021)· [2022] KEELC 2104 (KLR)

Dopp Investments Limited V Kenya Railways Corporation & National Land Commission; Kahia Transporters Ltd, Trade Lead Ltd, Kachungo Edward Bekwekwe, Charles Mulole Shanga, Hamisi Tsuma Mwero & Redalu Mbovo Mgaidi (Interested Parties) (Environment & Land Case 39 of 2019) [2022] KEELC 2104 (KLR)

Environment and Land Court
18 January 2022
2,773 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~11 min to read original · ~4 min brief

The bottom line

#

A Mombasa court refused to fast-track payment of Kshs 667 million in SGR land compensation because competing ownership claims must be resolved at a full trial.

What this practically means

#

Executive summary

#
This was a ruling on an application dated 19th July 2021 by the Plaintiff in a Mombasa Environment and Land Court suit concerning Title MN/VI/1040/2, part of which was compulsorily acquired for the Standard Gauge Railway. The Plaintiff sought certification of the 1st and 2nd Interested Parties' application dated 27th January 2021, expungement of Titles 5153/VI/MN, 5141/VI/MN and 5154/VI/MN from the record, immediate payment of a compensation award of Kshs. 667,903,887 for the undisputed 71.5% portion, a full trial on Title LR 31537, and variation of orders made on 8th November 2018 in HCCC 405 of 2017. The Interested Parties consented to the expungement but opposed immediate compensation, maintaining that the Plaintiff's title was fake because the mother plot became extinct in 1975 upon compulsory acquisition, making a 610-acre grant impossible. The 2nd Defendant confirmed its 2016 determination upholding the Plaintiff's title, the 2017 award, and survey findings that 3.81 hectares (28.5%) of the acquired corridor was encroached by LR 31537. Relying on Gupta vs Continental Builders and Job Kiloch, Justice N.A. Matheka held the counterclaim raised bona fide triable issues requiring a full trial. Only Prayer 2 was granted by consent; the prayers for immediate compensation, trial of LR 31537 within the application, and variation of the 2018 orders were refused. Costs were to be in the cause.

Key legal issues

#
01

Whether immediate payment of the compensation award could issue despite a pending counterclaim

Holding

Refused; the counterclaim raises serious allegations and triable issues, including that the Plaintiff's title is fake and that Plot 1040/VI/MN became extinct in 1975

Reasoning

The Interested Parties allege the Plaintiff's title does not exist and that the plot ceased to exist upon Government acquisition in 1975, making a 610-acre allotment implausible given the original 3.01-acre mother title. Such competing factual claims require a full trial before compensation can be ordered.

p. 3
02

Whether the orders of 8th November 2018 in HCCC 405 of 2017 could be varied in this suit

Holding

No; variation must be sought in the same active file

Reasoning

The court held that a substantive suit in ELC No. 405 of 2017 exists and any application to vary its orders must be made in that file, not in the present suit.

p. 3
03

Whether the survey findings established a dispute over LR 31537's encroachment

Holding

The 2nd Defendant's survey found 13.348 hectares compulsorily acquired, with 3.81 hectares (28.5%) encroached by LR 31537 and 71.5% unencroached

Reasoning

The Deputy Director of Survey at NLC confirmed that LR 1040/2 was registered in 1991 while LR 31537 was surveyed and registered in 2017, and that part of the compulsorily acquired corridor is encroached by LR 31537. These contested findings support a full trial.

p. 2

Legal principles established

#
  • A bona fide triable issue is any matter raised by the defendant that would require further interrogation by the court during a full trial; it need not be an issue that would succeed
  • Where triable issues are raised, summary payment or final orders cannot be made and the matter must go to full trial

Court orders

#
  1. 1.Prayer 2 of the application granted by consent (allowing the 1st and 2nd Interested Parties' Application dated 27th January 2021 and expunging Titles 5153/VI/MN, 5141/VI/MN and 5154/VI/MN from the Court record)
  2. 2.Prayers 3, 4 and 5 refused; the matter to proceed to full trial on the triable issues
  3. 3.Costs to be in the cause

Authorities

#

Legislation

  • Civil Procedure ActSections 1A, 1B and 3A
  • Constitution of Kenya, 2010Article 40

Cases cited (2)

  • Gupta vs Continental Builders Ltd
    (1978) KLR 83
  • Job Kiloch vs Nation Media Group Ltd, Salaba Agencies Ltd & Michael Riorio
    (2015) eKLR
Jurisdiction invoked
Sections 1A, 1B and 3A of the Civil Procedure Act and the inherent jurisdiction of the Court

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Dopp Investments Limited V Kenya Railways Corporation & National Land Commission; Kahia Transporters Ltd, Trade Lead Ltd, Kachungo Edward Bekwekwe, Charles Mulole Shanga, Hamisi Tsuma Mwero & Redalu Mbovo Mgaidi (Interested Parties) (Environment & Land Case 39 of 2019) [2022] KEELC 2104 (KLR)", Case Analysis (2022). Application dated 19th July 2021 (arising from 1st and 2nd Interested Parties' Application dated 27th January 2021). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/2104/eng@2022-01-18

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.