The consent was duly executed and adopted as an order of the court on 17.5.2021 without any intervening application to halt adoption; no plausible grounds for setting it aside were established
Applying Flora N. Wasike v Destino Wamboko, a consent adopted as a court order binds the parties and can only be discharged on grounds such as fraud or collusion. The consent simply marked the matters as fully settled; disputes about the underlying settlement agreements had birthed a new cause of action already before the Chief Magistrate's Court. Setting aside the consent would revive closed matters, create multiplicity of proceedings and potential contradictory verdicts, amounting to an abuse of court process.
Whether the client's application of 18.11.2021 for stay of proceedings should be granted
The court treated the 18.11.2021 application as a response to the advocate's application of 19.10.2021 and marked it as spent, having resolved the dispute by dismissing the advocate's application
Invoking Sections 1A and 1B of the Civil Procedure Act on active case management and the overriding objective, the court considered both applications together since both related to the negotiations culminating in the consent of 19.4.2021. Having dismissed the advocate's application, the stay sought became moot and the application was marked spent.
Legal principles established
#- A consent order made in the presence and with the consent of counsel is binding and cannot be varied or discharged unless obtained by fraud, collusion, agreement contrary to the policy of the court, or without sufficient material facts
- The sub judice rule prevents courts from simultaneously entertaining parallel litigation over the same cause of action, subject matter and relief, to avoid contradictory verdicts and multiplicity of proceedings
Court orders
#- 1.The application dated 19.10.2019 is dismissed with costs to the Client/Respondent
- 2.The application dated 18.11.2021 is marked as SPENT
- 3.All the three Misc. Appl. files Nos. 94, 95 and 96 of 2019 stand as closed
- 4.This ruling is to be placed on each of the three files
- Jurisdiction invoked
- Section 1A and 1B of the Civil Procedure Act (case management; original civil jurisdiction)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Andrew & Steve Advocates v Paragon Electronics Limited [2022] KEELC 1507 (KLR)", Case Analysis (2022). Miscellaneous Application Nos. 94, 95 and 96 of 2019. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/1507/eng@2022-02-09
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.