Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCDismissedNot stated in the judgment (ruling on Notice of Motion dated 9th December 2019)· [2022] KEELC 1330 (KLR)

Simba Corporation Limited v Kenya Railways Corporation & another [2022] KEELC 1330 (KLR)

Environment and Land Court of Kenya
23 February 2022
1,865 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~7 min to read original · ~4 min brief

The bottom line

#

The Mombasa Environment and Land Court refused to pause eviction and rent enforcement against a tenant because the planned appeal was not shown to have real merit.

What this practically means

#

Executive summary

#
This is a ruling of the Environment and Land Court at Mombasa (N.A. Matheka, J) on a Notice of Motion dated 9th December 2019 by the Plaintiff, brought under sections 1A and 3A of the Civil Procedure Act and Order 42 rule 6 and Order 51 rule 1 of the Civil Procedure Rules, seeking extension of interim orders issued on 7th November 2019 by Justice Yano and restraint of the Defendants from levying distress or evicting the Plaintiff from Title No. Mombasa/Block XLVIII/114 pending an intended appeal. The underlying suit, founded on a lease dated 24th April 1967 between the Plaintiff and the 1st Defendant (in a lessor-lessee relationship), had been dismissed by a judgment of Justice Komingoi read by Justice Yano, primarily because no notice had been issued under section 87 of the Kenya Railways Corporation Act before filing suit. The Plaintiff lodged a Notice of Appeal on 21st November 2019. The Defendants opposed, asserting the lawfulness of the rent increase from Kshs.27,000 to Kshs.2,815,720 annually, alleging arrears of Kshs.16,991,000, and maintaining that the right of re-entry on default was a contractual right the court should not interfere with. The court restated the Order 42 rule 6 conditions and the twin arguability and nugatory-ness principles from Reliance Bank v Norlake Investments, Chris Munga N. Bichange, Mohamed Salim and Carter & Sons. Finding that the applicant satisfied neither limb and had fulfilled none of the grounds for stay, the court dismissed the application with costs.

Key legal issues

#
01

Whether the conditions for grant of stay of execution pending appeal were met

Holding

The application was dismissed because the applicant satisfied none of the conditions for stay of execution

Reasoning

The court set out the Order 42 rule 6 conditions (substantial loss, no unreasonable delay, security) and the twin arguability/nugatory-ness principles from the authorities. It then examined the court record and grounds of appeal and found that the applicant failed on both the arguability limb and the nugatory-ness limb, concluding that none of the grounds for stay had been fulfilled.

p. 3
02

Whether the intended appeal was arguable and its success would be rendered nugatory without stay

Holding

The court was not persuaded that the appeal was arguable or that its success would be rendered nugatory

Reasoning

Applying the principles in Reliance Bank Ltd v Norlake Investments Ltd and Chris Munga N. Bichange v Richard Nyagaka Tongi, the court perused the record and grounds of appeal and found the arguability of the intended appeal not demonstrated, and equally found that refusal of stay would not render a successful appeal nugatory, noting that part of the judgment had already been executed with only the monetary part remaining.

p. 3

Legal principles established

#
  • An applicant for stay of execution pending appeal must satisfy the twin conditions of an arguable (not frivolous) appeal and that the appeal would be rendered nugatory if stay is not granted; both limbs must be demonstrated
  • The right of appeal must be balanced against the plaintiff's right to enjoy the fruits of the judgment, and there must be just cause to deprive the plaintiff of that right
  • Under Order 42 rule 6, the applicant must show substantial loss, absence of unreasonable delay, and furnish security for due performance of the decree

Court orders

#
  1. 1.The application dated 9th December 2019 is dismissed with costs

Authorities

#

Legislation

  • Civil Procedure Act, Cap 21, Laws of KenyaSection 1A
  • Civil Procedure Act, Cap 21, Laws of KenyaSection 3A
  • Civil Procedure Rules, 2010Order 42 Rule 6
  • Civil Procedure Rules, 2010Order 51 Rule 1
  • Kenya Railways Corporation ActSection 87

Cases cited (4)

  • Reliance Bank Ltd (In Liquidation) vs. Norlake Investments Ltd
    Civil Appl. No. Nai. 93/02 (UR)
  • Chris Munga N. Bichange vs Richard Nyagaka Tongi & 2 Others
    eKLR
  • Mohamed Salim T/A Choice Butchery vs Nasserpuria Memon Jamat
    (2013) eKLR
  • Carter & Sons Ltd vs Deposit Protection Fund Board & 2 Others
    Civil Appeal No. 291 of 1997, at Page 4
Jurisdiction invoked
Order 42 Rule 6 and Order 51 Rule 1 of the Civil Procedure Rules, 2010; sections 1A and 3A of the Civil Procedure Act, Cap 21

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Simba Corporation Limited v Kenya Railways Corporation & another [2022] KEELC 1330 (KLR)", Case Analysis (2022). Not stated in the judgment (ruling on Notice of Motion dated 9th December 2019). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/1330/eng@2022-02-23

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.