Joseph Kamau Mbiriri v Robert Kiwuwa Kigo & 2 others [2022] KEELC 1260 (KLR)
The bottom line
#Kenya's Environment and Land Court ruled the plaintiff could keep mining pending trial, confirming that mining on private land needs the owner's consent under the Mining Act.
What this practically means
#Executive summary
#Key legal issues
#Interpretation of the status quo order made on 21st January 2020
The status quo encompasses the Plaintiff's right to continue mining on the suit location pursuant to Section 37 of the Mining Act, and the court invoked its inherent powers to extend the earlier temporary injunction orders until final determination
The court defined status quo by reference to Black Law Dictionary as the situation currently existing. Noting that the interim injunction orders of 2017 were compromised by consent on 19th September 2019 without clarity as to whether they had been extended, the court concluded that the status quo order replaced those interim orders. Exercising inherent powers and the oxygen rule, it extended the injunction and activated Section 37(1) and (3) of the Mining Act to allow the Plaintiff to continue mining.
Statutory right to mine pending determination of the dispute
Section 37(1) and (3) of the Mining Act allows the Plaintiff to continue mining until the matter is heard and determined
Mr. Gaita for the Plaintiff relied on Section 37 of the Mining Act, which grants a person consent rights over mining activities on private land. The court accepted that the provision should take effect, permitting the Plaintiff to continue mining pending the full hearing and determination of the suit.
Legal principles established
#- Minerals and mineral oils constitute public land under Article 62 of the Constitution
- On private land, mineral rights may only be granted with the consent of the registered proprietor under Section 37 of the Mining Act
Court orders
#- 1.Extension of the temporary injunction orders granted on 17th November 2017 until the matter is heard and finally determined
- 2.That the provisions of Section 37(1) and (3) of the Mining Act No. 12 of 2016 take effect allowing the Plaintiff to continue mining until the matter is heard and determined
- 3.That the matter be granted first priority and fast-tracked to be finalized in the next ninety (90) days
- 4.Each party to bear its own costs
- Jurisdiction invoked
- Inherent powers under Section 3(1) of the Environment and Land Court Act, Section 101 of the Land Registration Act, Section 150 of the Land Act and Article 159(1) and (2) of the Constitution of Kenya
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Joseph Kamau Mbiriri v Robert Kiwuwa Kigo & 2 others [2022] KEELC 1260 (KLR)", Case Analysis (2022). ELC No. 423 of 2017. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2022/1260/eng@2022-02-09
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.