Kenya Electricity Transmission Company & another v Maryann Sheikh Abdikadir & & 121 others; Fruitful Farms Limited (Applicant) [2021] KEELC 3940 (KLR)
The bottom line
#A Kajiado court allowed Kenya Power's transmission line project to proceed, directing affected landowners to pursue compensation instead of blocking construction.
What this practically means
#Executive summary
#Key legal issues
#Injunction pending appeal
Refused - no prima facie case established
Applying Giella v Cassman Brown and related authorities, the court found the Applicants' land had already been gazetted for compulsory acquisition for a public utility, and the earlier Ruling directed parties to negotiate compensation. The Applicants had not updated the court on the progress of the appeal. Granting an injunction would therefore impede a public utility project without demonstrated merit.
Joinder of Fruitful Farms Limited as Defendant
Refused - Applicant is not a necessary or proper party
Under Order 1 Rule 10(2) and Joseph Njau Kingori, an intending defendant must be necessary/proper and its presence necessary for complete adjudication. The Applicant farms on land owned by the 94th and 95th Defendants, who are already parties; developments on the land are considered during assessment of compensation under Rule 3 of the Land (Assessment of Just Compensation) Rules 2017. The Applicant's concerns should be raised at the compensation inquiry.
Legal principles established
#- An injunction pending appeal will not issue where the appeal is frivolous or where the injunction would inflict greater injustice than it would avoid.
- Compulsory acquisition focusses on the land while developments thereon are considered during assessment of compensation/damages.
- Principles for joinder of an intending party: necessary party, proper party, relief flowing from the defendant, decree enforceable without him, and presence necessary for effective adjudication.
Court orders
#- 1.Dismissal of the 78th and 79th Defendants' Notice of Motion dated 24th October 2020 seeking an injunction pending appeal
- 2.Dismissal of Fruitful Farms Limited's Chamber Summons Application dated 13th January 2021 seeking joinder as a Defendant
- 3.Costs in the cause
- Jurisdiction invoked
- Articles 50 and 159 of the Constitution; Order 42 Rule 6 and Order 1 Rule 10(2) of the Civil Procedure Rules; Sections 1A, 1B and 3A of the Civil Procedure Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kenya Electricity Transmission Company & another v Maryann Sheikh Abdikadir & & 121 others; Fruitful Farms Limited (Applicant) [2021] KEELC 3940 (KLR)", Case Analysis (2021). Not stated in extract. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2021/3940/eng@2021-03-22
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.