Nizar Hasham Virani & another v Kenya Pipeline Company Ltd [2021] KEELC 2114 (KLR)

Environment and Land Court
3 September 2021
1,511 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~6 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court allowed landowners to amend their case late, ruling a one-month delay caused no real prejudice to the other side.

What this practically means

#

Executive summary

#
The Plaintiffs sued in 2015 by plaint dated 23 December 2015 seeking a permanent injunction restraining the Defendant from interfering with land parcel KISUMU/KOGONY/2642 and a declaration entitling them to compensation before any easementary right could arise from the laying of pipelines across the land. An amended plaint filed on 15 March 2019 added claims for removal of a second pipeline and compensation for damage and trespass. By a notice of motion dated 1 April 2021, the Plaintiffs sought enlargement of time to file a further amended plaint and an order deeming it properly filed upon payment of fees, after failing to comply with leave granted on 24 February 2021. The Defendant opposed, arguing inordinate unexplained delay, that the amendment introducing a substantial compensation claim was time-barred under section 4(2) of the Limitation of Actions Act, was too drastic and warranted a fresh suit, and was an afterthought to prolong the six-year-old suit. Antony Ombwayo J identified two issues: whether leave to amend could issue out of time, and whether the draft further amended plaint could be deemed filed. Relying on Order 8 rule 7 of the Civil Procedure Rules and section 95 of the Civil Procedure Act, and following Libya Oil Kenya Limited v Joel Kipkorir Siele, the court held the one-month delay, though unexplained, was not inordinate and caused no prejudice beyond costs. Applying the AAT Holdings principles and Order 2 rule 6(1), the court found the amendments concerned the same parties, land and infrastructure, were material and avoided multiplicity of suits. The application was allowed with the final orders enlarging time and deeming the further amended plaint properly filed upon payment of requisite fees. No costs order was made in the disposition.

Key legal issues

#
01

Whether leave could be granted to file an amended plaint out of time

Holding

Yes. Order 8 rule 7 allows the court to extend the period even after the order of leave has ceased to have effect, reinforced by section 95 of the Civil Procedure Act; the one-month delay attributed to counsel's inadvertence caused no compensable prejudice.

Reasoning

The plaintiffs had been granted 14 days from 24 February 2021 to amend but filed the application on 13 April 2021, attributing the delay to pressure of work. The court acknowledged the delay was unexplained but held it was short, that no miscarriage of justice would result, and that any inconvenience was compensable by costs, following Libya Oil Kenya Limited v Joel Kipkorir Siele & another.

p. 2
02

Whether the draft further amended plaint could be deemed properly filed rather than made the subject of a fresh suit

Holding

Yes. The amendment related to new developments on the same land between the same parties, did not introduce an inconsistent cause of action, and would avoid multiplicity of suits.

Reasoning

The respondent argued the proposed amendment introducing a large compensation claim was too drastic and warranted a fresh suit, and was time-barred under section 4(2) of the Limitation of Actions Act. The court, applying the principles in AAT Holdings Ltd v Diamond Shields International Ltd and Order 2 rule 6(1), found the previous pleadings consistently sought damages over the same parcel of land (KISUMU/KOGONY/2642) and the amendment concerned continued infrastructure works on it, so it was material and not a fundamentally different claim.

p. 3

Legal principles established

#
  • Where an order granting leave to amend has ceased to have effect, the court retains the power to extend the period, and a delay of about a month which occasions no prejudice capable of being compensated by costs justifies enlargement of time.
  • An amendment relating to the same parties, the same land and continued laying of infrastructure by the defendant does not introduce a fundamentally different claim warranting a fresh suit, and avoids multiplicity of suits.

Court orders

#
  1. 1.That time be and is hereby enlarged for the Plaintiffs/Applicants to file an application for further amendment
  2. 2.That the further amended plaint filed and served be and is hereby deemed as having been properly filed and served upon payment of requisite fees

Authorities

#

Legislation

  • Civil Procedure Rules, 2010Order 8 rule 7
  • Civil Procedure Actsection 95
  • Civil Procedure Rules, 2010Order 2 rule 6(1)
  • Limitation of Actions Actsection 4(2)

Cases cited (2)

  • Libya Oil Kenya Limited v Joel Kipkorir Siele & another
    [2021] eKLR
  • AAT Holdings Ltd v Diamond Shields International Ltd
    [2014] eKLR
Jurisdiction invoked
Section 95 of the Civil Procedure Act and Order 8 rule 7 of the Civil Procedure Rules, 2010 (inherent discretion to enlarge time)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Nizar Hasham Virani & another v Kenya Pipeline Company Ltd [2021] KEELC 2114 (KLR)", Case Analysis (2021). Not stated in judgment extract. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2021/2114/eng@2021-09-03

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.