ELCPartially Allowed· [2021] KEELC 1698 (KLR)

Domitien Ndayizeye v Kencom Sacco Society Limited [2021] KEELC 1698 (KLR)

Environment and Land Court
7 October 2021
2,831 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~11 min to read original · ~4 min brief

The bottom line

#

What this practically means

#

Executive summary

#
The Defendant generated a Letter of Offer dated 21st August 2015 offering to sell Unit No. 13 on L.R. No. 12825/141, Runda Estate, Nairobi to the Plaintiff for KShs 33,000,000. The Plaintiff accepted and paid a deposit of KShs 7,000,000. On 16th February 2016 the Plaintiff withdrew from the transaction, invoking Clause 7 of the Letter of Offer, which permitted cancellation before execution of the sale agreement upon forfeiture of 10% of the deposit, with the balance refundable within 7 days. The Defendant acknowledged the termination and promised to refund but repeatedly failed to do so, refunding only KShs 2,000,000 in September 2016, prompting the suit filed on 4th April 2018. By the time of trial the outstanding balance had been refunded, leaving only interest and costs for determination. The court, Oguttu Mboya J, held that failure to refund within the 7 days stipulated in Clause 7 - a clause the Defendant herself generated - was a breach entitling the Plaintiff to interest. Relying on section 26 of the Civil Procedure Act and the Prem Lata and Mukisa Biscuits line of authority, the court found the Plaintiff deprived of the use of his money by the Defendant's wrongful conduct. Pre-suit interest was also permissible since the claim was liquidated and contractually due. Interest was awarded at court rates from 23rd February 2016 until payment of the principal sum. On costs, applying section 27, costs follow the event; the Defendant's breach attracted costs against her. The suit succeeded on both remaining issues, and the Plaintiff was awarded interest and costs of the suit.

Key legal issues

#
01

Entitlement to interest on a withheld deposit refund

Holding

The Plaintiff is entitled to interest at court rates from the 23rd of February 2016 (the 7th day after notice of termination) until payment of the principal sum.

Reasoning

Clause 7 of the Letter of Offer, generated by the Defendant herself, required refund of the deposit within 7 days of withdrawal. Failure to comply was ipso facto a breach. Having been aware of the obligation and having kept shifting goalposts, the Defendant's intransigence deprived the Plaintiff of the use of his money, attracting interest both under section 26 of the Civil Procedure Act and as damages for deprivation, consistent with Prem Lata and Mukisa Biscuits.

p. 2
02

Duration of computation of interest

Holding

Interest runs from 23rd February 2016 (before suit) to the date the principal sum was paid; no interest arises post-judgment since the principal was already refunded.

Reasoning

Section 26 of the Civil Procedure Act permits interest from date of suit to decree and further interest from decree to payment. Since the principal sum had been refunded before judgment, the court was concerned with pre-decree interest, including pre-suit interest which was justified because the claim was liquidated and contractually due, the Defendant having generated Clause 7 fixing the 7-day refund timeline.

p. 3
03

Costs of the suit

Holding

Costs awarded to the Plaintiff as costs follow the event.

Reasoning

Under section 27 of the Civil Procedure Act costs follow the event unless the court directs otherwise. The Defendant was aware of her obligation to refund within 7 days under a clause she herself coined; her failure to comply without need of reminder justified costs against her, per Margaret Ncekei Thuranira v Mary Mpinda & Another.

p. 4

Legal principles established

#
  • Where a party is deprived of the use of money by the wrongful act of another, interest should be awarded to compensate for the deprivation.
  • Interest for the period before filing of suit is a matter of substantive law and is claimable only where there is contractual stipulation, mercantile usage, statutory right or implied agreement.
  • Costs follow the event unless the court for good reason otherwise directs.

Court orders

#
  1. 1.The Plaintiff shall be and is hereby entitled to Interest at Court rates with effect from the 23rd of February 2016, until the date when the Principal sum was paid.
  2. 2.The Plaintiff be and is hereby awarded Costs of the Suit.

Authorities

#

Legislation

  • Civil Procedure Act, Chapter 21 Laws of KenyaSection 26
  • Civil Procedure Act, Chapter 21 Laws of KenyaSection 27

Cases cited (9)

  • Prem Lata vs Peter Musa Mbiyu
    (1965) EA 592
  • Mukisa Biscuits Manufacturing Company Limited v West End Distributors Limited
    (1970) EA 469
  • Jane Wanjiku Wambu v Anthony Kigamba Hato & 3 others
    [2017] eKLR
  • Gulamhussein v French Somaliland Shipping Company Limited
    [1959] EA 25
  • Highway Furniture Mart Limited v The Permanent Secretary & Another
    EALR (2006) 2 EA 94
  • Margaret Ncekei Thuranira vs Mary Mpinda & Another
    (2015) eKLR
  • Devran Dattan versus Dawda
    [1949] EACA 35
  • James Koskei Chirchir versus Chairman Board of Governors Eldoret Polytechnic
    [2011] eKLR (Civil Appeal No. 211 of 2005)
  • Super Marine Handling Services Limited versus Kenya Revenue Authority
    [2010] eKLR (Civil Appeal No. 85 of 2006)
Jurisdiction invoked
Original civil suit; Section 26 and Section 27 of the Civil Procedure Act, Chapter 21 Laws of Kenya

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Domitien Ndayizeye v Kencom Sacco Society Limited [2021] KEELC 1698 (KLR)", Case Analysis (2021). . Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2021/1698/eng@2021-10-07

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.