The plaintiff's title anchored on Deed Plan No. 180529 is genuine; the 1st defendant's title was procured fraudulently or issued by mistake and was cancelled.
Both titles trace to the 1994 subdivision of mother Plot No. 34, which identified the suit land by Deed Plan No. 180529. The Director of Surveys' evidence showed Deed Plan No. 242710 in the 1st defendant's title relates to LR No. 26312 in Nairobi, not the suit land in Mtwapa. No authenticated survey plan of any 2005 amendment survey was produced, and there was no record of surrender of Deed Plan No. 180529. The plaintiff's title was also first in time (2001).
Violation of the doctrine of lis pendens
The 1st defendant processed and obtained title while the suit was pending and after an injunction had issued, breaching Section 52 of the ITPA; the title cannot stand on that basis alone.
An injunction had issued on 5 March 2010 while the registered proprietor was Oscar Muli Kithuka. The 1st defendant nonetheless had the land transferred to herself on 17 June 2010 without joining Oscar Muli or issuing a third party notice. Section 52 of the ITPA, supported by Rose Wakanyi Karanja and Mawji v US International University, prohibits dealing with disputed property during contentious litigation.
Authenticity of the Land Control Board consent
The LCB consent was of dubious authenticity because it purportedly issued on 3 September 2009, a day before the application dated 4 September 2009.
The 1st defendant produced an application for LCB consent dated 4 September 2009 alongside a consent dated 3 September 2009. She could not explain how consent issued before the application. The court found this fatal to the legitimacy of the transfer process to her.
Liability and quantum for trespass
The 1st defendant trespassed on the plaintiff's land, was not an innocent purchaser for value, and was liable for general damages of Kshs. 1,000,000/=.
The 1st defendant entered the land before she had title, erected a wall and structures without producing building plans, failed to produce the sale agreement or proof of payment, and did not call Oscar Muli. The court exercised its discretion on quantum considering her conduct, the length of the plaintiff's exclusion, and the size and location of the land.
Legal principles established
#- Once litigation is pending over immovable property, parties are barred from transferring or otherwise dealing with it under the lis pendens doctrine, and a title obtained in breach cannot stand.
- Where two titles exist over the same land, the court must determine which is genuine by going to the root of both titles.
- Under Section 32 of the Survey Act, land is not deemed surveyed or resurveyed until the plan has been authenticated by the Director or an authorised Government Surveyor.
- A party alleging a resurvey bears the burden of producing the duly authenticated survey plan for it.
- A second title for the same land cannot lawfully be issued where one already exists.
- General damages for trespass are quantified at the discretion of the court.
Court orders
#- 1.Declaration that the 1st defendant's title is null and void ab initio
- 2.Cancellation of the 1st defendant's title CR No. 45719
- 3.Order that the Registrar of Titles not undertake any further registration of dispositions based on the 1st defendant's title
- 4.Order that the 1st defendant's title be retained by the Court and never released to any person
- 5.General damages of Kshs. 1,000,000/= in favour of the plaintiff against the 1st defendant, with interest at court rates from the date of judgment
- 6.1st defendant to bear the costs of the suit and the counterclaim
- Jurisdiction invoked
- Original jurisdiction of the Environment and Land Court under the 2010 Constitution (matter transferred from the High Court upon the court's creation)
Key timeline
#Practical implications
#Frequently asked questions
#Later judgments citing this (4)
#Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.
- Registered Trustees of Sheik Bayed Bin Sultan Al Nahyan v Pelican Engineering & Construction Company Limited & 4 others (Environment and Land Case 639 of 2015) [2024] KEELC 6534 (KLR)[2024] KEELC 6534 (KLR)3 Oct 2024applied
- Omu & another v Kiso Enterpises Limited & 3 others (Environment & Land Case 3 & 134 of 2016 (Consolidated)) [2024] KEELC 5843 (KLR)[2024] KEELC 5843 (KLR)22 Aug 2024
- Joseph Ndegwa Wanjiri & Another v [1st Defendant] & Mwana Mukia Housing Co-operative Society Ltd[2024] KEELC 4757 (KLR)13 Jun 2024
- Kahiga (Suing in her capacity as a personal representative of the Estate of Alexander Kagiri Meri Njatha Alias Alexander Kagiri Meri) v Kimani & 16 others (Environment & Land Case 38 of 2019) [2023] KEELC 230 (KLR)[2023] KEELC 230 (KLR)26 Jan 2023
Cite this brief
#Cite this brief
Caselaw, "Davis Mwashao Jome v Damaris Karanja & another [2021] KEELC 1461 (KLR)", Case Analysis (2021). Not stated in the judgment (instituted by plaint dated 17 September 2009). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2021/1461/eng@2021-10-13
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.