Marino Hardware Limited v Frabhudas Chunilal & 3 others [2021] KEELC 946 (KLR)
The bottom line
#A Mombasa court refused to revive a tenant's two-year-delayed appeal after eviction, but ordered the landlord to release the tenant's locked-up goods within seven days.
What this practically means
#Executive summary
#Key legal issues
#Whether incoming advocates could be granted leave to come on record after judgment under Order 9 Rule 9
Leave was granted notwithstanding that the current advocates had no audience, in the interest of justice, because notice had been issued to the previous advocates
Order 9 Rule 9 requires a court order or consent for a change of advocates after judgment; its mischief is non-payment of advocates. The incoming advocates sought consent but received no response and thus lacked audience. The court held they should have filed a standalone application but, in the interest of justice, equity and conscience, and noting notice to the outgoing firm, exercised its discretion to regularise their appearance.
Whether the Applicant satisfied the conditions for stay of execution pending appeal
The conditions were not satisfied: no substantial loss demonstrated, inordinate delay, and no security offered
The court weighed the four conditions: substantial loss, no unreasonable delay, security and sufficient cause. Evidence showed the premises had been executed by eviction on 22nd November 2019 and Respondents had taken possession; goods worth approximately Kshs 14 million were locked up. The application was filed with inordinate delay blamed on COVID-19, and the Applicant in rental arrears made no offer of security. The court was thus not satisfied substantial loss would ensue.
Whether extension of time to file the appeal out of time should be granted under Section 79G
Extension refused: the cumulative delay exceeded twenty-four months, the reasons were not cogent, and the substratum of the appeal was lost
The court set out the modern discretionary factors for extension of time: length of delay, reason for delay, chances of the appeal succeeding, and prejudice to the Respondent. The Applicant slept on its rights for nearly three months after judgment, subsequent applications were dismissed for non-compliance, and the delay exceeded two years. With eviction already executed, the orders sought would be of no value and would only prejudice the Respondents.
Legal principles established
#- The purpose of a stay of execution pending appeal is to preserve the subject matter in dispute so the appellant's right of appeal is not rendered nugatory
- An applicant for stay must show sufficient cause, substantial loss, no unreasonable delay, furnish security, and demonstrate that the appeal will be rendered nugatory
- A change of advocates after judgment requires an order of the court or consent of the outgoing advocate under Order 9 Rule 9
- Appeals from a subordinate court to the High Court must be filed within thirty days of the decree or order appealed against
Court orders
#- 1.The notice of motion application dated 3rd December, 2020 by the Intended Appellant/Applicant is bereft of any merit and the same is hereby dismissed
- 2.The Applicant is granted leave to change Advocates by appointing the law firm of Messrs. Asige, Keverenge & Anyanzwa Company Advocates in place of Messrs. Muthee Soni & Associates Advocates
- 3.The Respondents are directed to unconditionally release all the moveable properties belonging to the Applicant and in their possession in form of goods, documents and/or consignments to the Applicant within the next Seven (7) days
- 4.The costs of the application to be borne by the Applicant
- On appeal from
- Business Premises Rent Tribunal (BPRT)
- Jurisdiction invoked
- Sections 1, 1A, 3A, 63(e) and 79G of the Civil Procedure Act, Cap. 21; Order 9 Rules 9 & 10, Order 42 Rule 6(1) & (2) and Order 51 Rule 1 of the Civil Procedure Rules, 2010; Section 3 of the Environment and Land Court Act No. 19 of 2012
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Marino Hardware Limited v Frabhudas Chunilal & 3 others [2021] KEELC 946 (KLR)", Case Analysis (2021). Not stated in the judgment (Notice of Motion dated 3rd December, 2020). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2021/946/eng@2021-11-10
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.