Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedELC Case Number 155 of 2019 (OS)· [2020] KEELC 2460 (KLR)

Sung Rim Choi v Exotic Gates Limited [2020] KEELC 2460 (KLR)

Environment and Land Court
14 May 2020
2,215 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~9 min to read original · ~4 min brief

The bottom line

#

A Nairobi court ordered a developer to refund an off-plan apartment buyer's deposit with interest, holding that a developer who never started construction cannot blame the buyer.

What this practically means

#

Executive summary

#
The Applicant purchased off-plan Apartment No. EGL/01/011/2014 in Block A, Hatheru Road from the Respondent under an offer letter dated 8th November 2014 at a price of Kshs.20,300,000/=, with a 25% deposit of Kshs.5,075,000/= payable. The Applicant paid only Kshs.3,000,000/=, which the Respondent accepted and receipted on 12th November 2014 without demanding the balance. Construction was to be completed by June 2016 but, five years later, had never commenced; the Respondent attributed the delay to issues of title. The Applicant sued for a declaration of breach, refund of the deposit with interest, and general damages. The Respondent opposed, contending the deposit was non-refundable, that the Applicant frustrated the contract by underpaying, and counter-claimed for a 2.5% refund policy fee, cumulative default penalties of Kshs.1,064,900/=, and 10% of the sale price under the Law Society Conditions of Sale 1989. The court framed two issues: who was in breach, and whether the parties were entitled to their respective claims. It held the Respondent, not the Applicant, was in breach: by accepting the partial deposit without demanding the balance it waived the right to rely on the shortfall; by contracting without clean title it was guilty of material non-disclosure; and the stalled project justified the Applicant's withholding of further instalments. The court entered judgment for the Applicant: a declaration of breach, refund of Kshs.3,000,000/= with interest at court rates from 12th November 2014 until payment in full, and costs. General damages were refused as unavailable alongside special damages, and the counter-claim was dismissed with costs.

Key legal issues

#
01

Which party was in breach of the agreement of 8th November 2014

Holding

The Respondent was in breach; the Applicant's failure to pay the balance of deposit and subsequent instalments was excused by the Respondent's waiver and its failure to commence construction

Reasoning

The Applicant paid Kshs.3,000,000/= of the agreed Kshs.5,075,000/= deposit, which was accepted and receipted without demand for the balance, amounting to waiver/estoppel. The Respondent conceded the delay in construction was due to title issues, amounting to material non-disclosure. Five years after signing and three years past the June 2016 completion date, construction had not begun, so the Applicant was justified in withholding further payments.

p. 3
02

Whether the Applicant is entitled to refund of the deposit and interest

Holding

Yes - refund of Kshs.3,000,000/= with interest at court rates from 12th November 2014, not conditional on completion or resale of the unit

Reasoning

The contract could not be salvaged since the project never commenced. The Respondent had enjoyed the Applicant's money for five years and it would be unfair to delay the refund by pegging it to completion of the project or sale of the unit to another purchaser. Interest was awarded at court rates from the date the deposit was received.

p. 3
03

Whether the Respondent's counter-claim succeeds

Holding

The counter-claim fails and is dismissed with costs

Reasoning

The 2.5% refund policy fee did not apply because the Applicant was forced to back out, not willingly opting out. The late penalty fee of Kshs.1,064,900/= could not apply as the project never started. The 10% of sale price under the Law Society Conditions could only apply had a formal contract been executed and collapsed due to the Applicant's default; only an offer letter existed.

p. 3
04

Whether the Applicant is entitled to general damages

Holding

No - general damages cannot be awarded in addition to special damages

Reasoning

Although the Applicant sought general damages for distress, the court held these could not be awarded in addition to special damages, and judgment was entered only for the refund, interest and costs.

p. 3

Legal principles established

#
  • A party who accepts a part-payment without demanding the balance waives its right to insist on full payment and cannot later plead the shortfall as breach by the other party.
  • A developer who enters a sale agreement without clean title is guilty of material non-disclosure and cannot blame the purchaser for the failure of the project.
  • Where an off-plan project has not commenced years after the completion date, a purchaser is not bound to pay further instalments and is entitled to a refund of the deposit not pegged to completion or resale of the unit.

Court orders

#
  1. 1.A declaration that the Respondent is in breach of the contract for sale of Apartment No. EGL/01/100/2014 in Block A, Hatheru Road entered with the Applicant on 8th November 2014
  2. 2.The Respondent to refund the Applicant Kshs.3,000,000/= together with interest at court rates from 12th November 2014 until payment in full
  3. 3.The Respondent to pay the Applicant costs of the suit
  4. 4.The Respondent's counter-claim dismissed with costs to the Applicant

Authorities

#

Legislation

  • Constitution of KenyaArticles 40, 64, 159
  • Civil Procedure Act (Cap 21)Sections 1, 1A, 1B, 3, 3A
  • Civil Procedure Rules 2010Order 37 Rule 3
  • Limitation of Actions Act (Cap 22)Section 10
  • Law Society Conditions of Sale1989

Cases cited (4)

  • Serah Njeri Mwobi Vs John Kimani Njoroge
    (2013) eKLR
  • John Mburu Vs Consolidated Bank of Kenya
    (2018) eKLR
  • Steel Rolling Mills Limited Vs Jubilee Insurance Company Limited
    (2007) eKLR
  • Rehema W Njoroge Vs Presbyterian Foundation & Another
    (2018) eKLR
Jurisdiction invoked
Articles 40, 64 and 159 of the Constitution; Sections 1, 1A, 1B, 3 and 3A of the Civil Procedure Act (Cap 21); Order 37 Rule 3 of the Civil Procedure Rules 2010; Section 10 of the Limitation of Actions Act (Cap 22)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Sung Rim Choi v Exotic Gates Limited [2020] KEELC 2460 (KLR)", Case Analysis (2020). ELC Case Number 155 of 2019 (OS). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2020/2460/eng@2020-05-14

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.