Farmers Trust Limited v Registered Trustees of Agricultural Society of Kenya (Environment & Land Case 250 of 2019) (Environment and Land) [2020] KEELC 1402 (KLR)
The bottom line
#A Kenyan court protected disputed showground land for 18 months while arbitration runs, but only the specific areas a developer was contractually meant to develop.
What this practically means
#Executive summary
#Key legal issues
#Whether the suit should be struck out because the interim measures application would wholly dispose of it
The suit was not struck out; it becomes spent once the interim measures application is determined
Rule 2 of the Arbitration Rules 1997 requires an application under Section 7 to be made by summons in a suit, so a suit must exist. Rule 11 incorporates the Civil Procedure Rules. Since the interim measures application mirrors the plaint's prayers, once it is determined the suit is spent, but that does not justify striking it out.
The test for granting interim measures of protection pending arbitration
The court applied the Safaricom test: existence of an arbitration agreement, threat to the subject matter, appropriate measure after assessing merits, and duration; it must not undermine the arbitration
The court found an arbitration agreement existed and the ICC arbitration had commenced. The proper measure had to preserve the subject matter without undermining the arbitration. The parties' dispute over the validity of termination was for the arbitral tribunal.
Whether the subject matter of the arbitration was under threat
Yes - specific performance of the Concession Agreement would be impossible if the showgrounds were alienated or developed for third parties, so a time-limited injunction was warranted
Specific performance would entail the Plaintiff providing services at the showgrounds for the agreed term. The court reasoned that such performance would be impossible if the land were transferred or dealt with in a manner rendering performance impossible. However, completed developments could not be restrained.
Duration and scope of the interim measure
An injunction for 18 months, limited to the portions the Plaintiff was to develop and excluding the Reserved Sites and the developed Jamhuri Park Expo Hall portion
Eighteen months was considered ample time for the Plaintiff to expedite the ICC arbitration. The court tempered the order to avoid paralysing the Defendant entirely, restricting it to the land specified in the First Schedule subject to the Plaintiff's consent under the Concession Agreement.
Legal principles established
#- Interim orders of protection under Section 7 of the Arbitration Act are holding orders pending the outcome of arbitral proceedings, granted on consideration of the existence of an arbitration agreement, whether the subject matter is under threat, the appropriate measure after assessing the merits, and the duration of the measure
- An application under Section 7 of the Arbitration Act must be made by summons in a suit; a suit supporting such an application cannot be struck out merely because the application will dispose of it
- Where a defined portion of the subject matter of an arbitration is under threat of alienation or development that would render specific performance impossible, the court may grant a time-limited injunction as an interim measure of protection without delving into the merits of the arbitration
Court orders
#- 1.The Defendant's application dated 27/9/2019 to strike out the suit is declined/dismissed, with each party bearing its own costs for that application
- 2.An interim measure of protection in the form of an injunction directed at the Defendant, its agents and servants, enjoining it not to lease, license, transfer, develop, part with possession, vest rights on any third party or otherwise change the character of the land specified in the First Schedule to the Concession Agreement without the express written consent of the Plaintiff in accordance with the Concession Agreement, for a period of 18 months pending the hearing of ICC Arbitration Case No. 23993/TO of 2018
- 3.The injunction does not extend to the Reserved Sites or the portion of the Nairobi showground within Jamhuri Park on which the Expo Hall and auxiliary facilities have been developed
- 4.Each party to bear its own costs for the application and of the suit
- Jurisdiction invoked
- Sections 7 and 22 of the Arbitration Act and Rule 2 of the Arbitration Rules 1997 (application for interim measures of protection pending ICC arbitration); disputes over land within the ELC's jurisdiction
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Farmers Trust Limited v Registered Trustees of Agricultural Society of Kenya (Environment & Land Case 250 of 2019) (Environment and Land) [2020] KEELC 1402 (KLR)", Case Analysis (2020). Not stated in judgment (application dated 31/7/2019; Defendant's application dated 27/9/2019). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2020/1402/eng@2020-08-19
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.