Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedMalindi ELC Case (number not stated in judgment)· [2020] KEELC 1220 (KLR)

Abdalla Mohamed Abdisheikh v Kishan Construction Limited [2020] KEELC 1220 (KLR)

Environment and Land Court
2 October 2020
1,577 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~6 min to read original · ~4 min brief

The bottom line

#

A Kenyan court ruled a construction company trespassed on private land after failing to prove the owner gave verbal permission.

What this practically means

#

Executive summary

#
The Plaintiff, registered proprietor of Ngomeni Squatter Settlement Scheme/1859, sued Kishan Construction Limited for trespass, alleging that from October 2016 the Defendant cleared his land and constructed a 9-metre access road to reach an adjoining construction site on Plot No. 2099, dividing the suit property into two uneconomical portions. He sought a permanent injunction, general damages, Kshs 15,000/- survey costs, costs and interest. The Defendant denied trespass, asserting the Plaintiff had orally granted permission to make a temporary access road in the presence of two witnesses. At trial, the Plaintiff testified but conceded he had no report supporting his claim of Kshs 1.5 million loss. The Defendant's Director testified but did not indicate where or to whom the alleged consent was given, and neither of the two named witnesses was called. The court held that the burden lay on the Defendant to prove the verbal consent, which it failed to do; in any event, any permission ceased upon the Plaintiff's formal demand letter of 23rd January 2017, after which continued use constituted trespass. Relying on the Survey Report showing the road was on the eastern end of the property, and considering the short duration of the trespass and lack of evidence of agricultural use, the court assessed general damages at Kshs 300,000/-. Judgment was entered for the Plaintiff with a permanent injunction, general damages of Kshs 300,000/-, special damages of Kshs 15,000/- as survey costs, and costs of the suit.

Key legal issues

#
01

Whether the Defendant's use of the Plaintiff's land as an access road constituted trespass

Holding

Yes. The Defendant created a 9-metre access road on the Plaintiff's land without establishing the alleged verbal consent, and persisted after a formal demand to cease, amounting to trespass.

Reasoning

The court found it uncontested that the Plaintiff was the registered proprietor and that the Defendant created the road. The Defendant claimed verbal consent given in the presence of two witnesses but called neither witness, and its Director could not say where or to whom consent was given. In any event, any permission ended when the Plaintiff's advocates demanded cessation of use. Continued use thereafter was trespass.

p. 2
02

What damages were payable for the trespass

Holding

General damages of Kshs 300,000/- and special damages of Kshs 15,000/- as survey costs.

Reasoning

The Plaintiff claimed Kshs 1.5 million for loss of agricultural use but could not justify the figure. The Survey Report showed the road was on the eastern end of the property, not half-way through. Considering the short period of trespass and absence of evidence of actual agricultural use, the court found Kshs 300,000/- to be reasonable compensation, plus the proved survey costs.

p. 3

Legal principles established

#
  • A plaintiff who proves trespass is entitled to nominal damages even without actual loss, and to compensatory damages where actual damage is proved.
  • A party asserting that permission to use land was granted bears the burden of demonstrating it; a party relying on witnesses to the granting of consent must call them.
  • Even if permission to use land was initially given, it ceases upon the owner's protest and formal demand, after which continued use constitutes trespass.

Court orders

#
  1. 1.A permanent injunction restraining the Defendant by itself, its employees, servants and or agents from trespassing upon, encroaching or passing through or being on the suit property
  2. 2.General damages of Kshs 300,000/- for wrongful trespass and or encroachment
  3. 3.Special damages of Kshs 15,000/- as Survey Costs
  4. 4.The Plaintiff shall also have the costs of this suit
Jurisdiction invoked
Original jurisdiction of the Environment and Land Court over land disputes (Plaint filed in the ELC)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief