Republic v National Environment Management Authority; Ex-parte Applicant: Comply Industries Limited & another [2020] KEELC 869 (KLR)
The bottom line
#Kenya's Environment and Land Court confirmed that NEMA can issue environmental compliance notices without a hearing, and aggrieved companies must appeal to the tribunal rather than rush to court.
What this practically means
#Executive summary
#Key legal issues
#Whether NEMA was obliged to give the applicants a hearing before issuing the notice
No hearing was required; the notice did not breach natural justice because it merely required the applicants to comply with their statutory EIA obligations under EMCA
NEMA is the principal instrument of government on environmental matters. The applicants admitted they were harvesting forests without an EIA licence. Section 58 of EMCA and Paragraph 2(5) of the Second Schedule mandatorily require an EIA study report for timber harvesting. The notice merely required performance of statutory obligations and correctly warned of the offence under Section 138 of EMCA, so it was procedurally proper.
Whether a suitable alternative remedy disentitled the applicants from judicial review
Yes; the applicants had a statutory right of appeal to the National Environment Tribunal under Section 129(1)(e) of EMCA, and no exceptional circumstances were demonstrated to bypass it
The notice was an environmental restoration order under Section 108 of EMCA. Aggrieved persons may appeal to NET, which under Section 129(3) can confirm, set aside or vary the order and maintain the status quo. NET decisions are further appealable to the High Court under Section 130. The statutory appeal provides adequate remedies including the setting aside sought by certiorari.
Legal principles established
#- Where a statutory appeal procedure exists, judicial review will only be granted in exceptional circumstances
- A person commencing or proceeding with a project specified in the Second Schedule to EMCA must submit an Environmental Impact Assessment study report and obtain an EIA licence before commencement, notwithstanding any other permit
Court orders
#- 1.Notice of Motion dated 10th November 2011 dismissed
- 2.Notice of Motion dated 27th October 2011 dismissed
- 3.Costs of both applications awarded to the respondent (NEMA)
- Jurisdiction invoked
- Judicial review jurisdiction over NEMA's decision, exercised under EMCA following transfer of the High Court judicial review applications to the Environment and Land Court
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Republic v National Environment Management Authority; Ex-parte Applicant: Comply Industries Limited & another [2020] KEELC 869 (KLR)", Case Analysis (2020). ELCC Nos. 401 of 2017 and 402 of 2017 (formerly HC Judicial Review Applications Nos. 121 of 2011 and 118 of 2011). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2020/869/eng@2020-10-29
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.