ELCPartially Allowed· [2020] KEELC 311 (KLR)

Hurlingham Park Limited v Kings Developers Limited & another [2020] KEELC 311 (KLR)

Environment and Land Court
10 December 2020
2,784 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~11 min to read original · ~4 min brief

The bottom line

#

A Nairobi court held a developer liable for damaging a neighbouring building during construction, awarding over Kshs.524,000 plus costs.

What this practically means

#

Executive summary

#
The plaintiff, manager of Hurlingham Park Estate on LR No. 1/311 along Argwings Kodhek Road, sued the defendants, developers of the adjacent LR No. 1/688, seeking a declaration that the defendants' development contravened its right to quiet and peaceful possession, a permanent injunction, special damages, and general and aggravated damages for negligence, nuisance and unlawful interference. The plaintiff's witnesses, including a property manager and an independent quantity surveyor who produced a cost estimates report, testified that falling debris and careless construction damaged the electric fence, water tanks, flower beds, cars, TV cables and roofing. The defendants, through a site supervisor, admitted limited damage (a replaced DSTV dish) and contended they had complied with a National Environment Management Authority Improvement Notice. The court found the construction was carried out negligently, relying on the undisputed NEMA Improvement Notice, photographs showing netting with gaping holes, complaint letters, and the defendants' admission of damage. The unchallenged expert cost estimate was accepted as proof of special damages, with Kshs.115,000 attributable to satellite dishes owned by tenants (who were not called) deducted. General damages for nuisance were assessed at Kshs.200,000 rather than the Kshs.800,000 sought. The permanent injunction was refused as construction was complete. Judgment was entered jointly and severally for the plaintiff with costs and interest.

Key legal issues

#
01

Whether the defendants' construction was negligently carried out causing damage to the plaintiff's property

Holding

Yes - the construction on LR No. 1/688 was undertaken negligently and caused damage to the plaintiff's property on LR No. 1/311, established on a balance of probabilities

Reasoning

The court relied on the NEMA Improvement Notice dated 30th July 2015 requiring the defendants to stop construction and install protective barriers, which the defendants did not dispute. Photographs showed netting with gaping holes allowing debris to fall. Letters of complaint and DW1's admission that a tenant's DSTV dish was damaged and replaced corroborated the damage. The court found the construction was undertaken negligently and/or carelessly.

p. 3
02

Whether the quantity surveyor's cost estimate was sufficient proof of special damages absent receipts

Holding

Yes - the unchallenged expert report by PW2 was sufficient proof of the cost of repairs; special damages were awarded on the report less the Kshs.115,000 for satellite dishes

Reasoning

The defendants did not tender a contrary expert report; an expert report can only be challenged by the evidence of another expert and not by submissions. The plaintiff explained the absence of receipts by the fact that repairs had not been undertaken except on the roof. The court accepted the report as proof of the renovations needed and the cost, but deducted amounts for the DSTV dishes owned by tenants who were not called as witnesses.

p. 4
03

Quantum of general damages for nuisance

Holding

Kshs.200,000 awarded as adequate compensation for the nuisance

Reasoning

The plaintiff proposed Kshs.800,000, citing Professor David M. Ndetei vs Orbit Chemical Industries Ltd where Emukule J referred to Rylands vs Fletcher and awarded Kshs.800,000. The court was guided by the principle that damages should restore the injured party to the position they would have been in had the wrong not occurred, but considered Kshs.200,000 adequate compensation in the circumstances.

p. 4
04

Whether the permanent injunction should issue

Holding

No - the prayer for permanent injunction was overtaken by events as construction was complete

Reasoning

It was admitted by both parties that the defendants' building had been completed. There was therefore nothing left to restrain, and the court declined to grant the injunction though it issued the declaration and damages.

p. 4

Legal principles established

#
  • Measure of damages is the sum of money that will put the injured party in the same position as if the wrong had not been sustained
  • Nuisance is an interference with a person's rights used or enjoyed in connection with land, including where consequences of acts on one's land escape to a neighbour's land

Court orders

#
  1. 1.A declaration that the manner in which the defendants have undertaken the development on LR No. 1/688 contravenes the plaintiff's right to quiet and peaceful possession and enjoyment of its property being LR No. 1/311
  2. 2.Special damages of Kshs.324,600/-
  3. 3.General damages for nuisance of Kshs.200,000
  4. 4.Costs of the suit and interest

Authorities

#

Cases cited (6)

  • Livingstone vs Rawyards Coal Co.
    [1880] 5 App Cases 25
  • Prof David M. Ndetei vs Orbit Chemical Industries Ltd
    [2014] eKLR
  • Mike Maina Kamau vs Attorney General
    [2017] eKLR
  • Tadis Travel & Tours Ltd & Another vs Astral Aviation Limited
    [2015] eKLR
  • Statpack Industries vs James Mbithi Munyao
    [2005] eKLR
  • Rylands vs Fletcher
    [1861-73] ALL ER REP 1
Jurisdiction invoked
Original civil jurisdiction over claims relating to land and nuisance caused by development on land

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (1)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#