Republic v Peter Chege Ngonyi (Subject); County Director of Land Adjudication and Settlement-Narok; Lasit Ole Teeka(Interested Party) [2019] KEELC 2311 (KLR)
The bottom line
#The High Court in Narok dismissed a landowner's challenge filed over ten years late, confirming that judicial review applications must be filed within six months of the decision being challenged.
What this practically means
#Executive summary
#Key legal issues
#Whether the judicial review application was filed within the statutory time limit
The Application was fatally out of time, being filed over ten years after the decision, and no application for extension of time having been made
Order 53 Rule (2) mandatorily requires judicial review applications to be made within six months. The decision complained of was made on 22nd February 2009, yet the Motion was dated 12th March 2018, over ten years later. Having not sought leave or an extension, the Application could not stand.
Legal principles established
#- Applications for judicial review orders of certiorari must be made not later than six months from the date of the decision sought to be quashed
Court orders
#- 1.Application dismissed with costs
- Jurisdiction invoked
- Order 53 Rule (2) and (3) of the Civil Procedure Rules and Section 10 of the Fair Administrative Action Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Republic v Peter Chege Ngonyi (Subject); County Director of Land Adjudication and Settlement-Narok; Lasit Ole Teeka(Interested Party) [2019] KEELC 2311 (KLR)", Case Analysis (2019). Judicial Review Application (Notice of Motion dated 12th March, 2018). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/2311/eng@2019-07-25
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.