ELCDismissedNot stated in judgment (application dated 10 January 2019 in the pending suit)· [2019] KEELC 2051 (KLR)

Dickson Ngige Ngugi v Consolidated Bank Ltd (Formerly Jimba Credit Corporation Limited) & another [2019] KEELC 2051 (KLR)

Environment and Land Court of Kenya
4 July 2019
1,125 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~5 min to read original · ~4 min brief

The bottom line

#

A Kenyan court refused to dismiss a stalled land suit, ruling that a simple letter requesting a mention date counts as progress within the last year.

What this practically means

#

Executive summary

#
This was a ruling on an application dated 10 January 2019 by the 1st defendant, Jimba Credit Corporation Limited, seeking dismissal of the plaintiff's suit for want of prosecution under Order 17 Rule 2 of the Civil Procedure Rules. The underlying suit, filed in December 2016, concerned land parcel LR No. 1117/1 (grant No. IR 31947), which the plaintiff alleged he charged in 1991 to secure a Kshs. 300,000 loan from the 1st defendant. He pleaded that the charge and subsequent transfers were void for want of Land Control Board consent, that the land was sold by public auction to the 2nd defendant in September 1985 and later to the 3rd defendant in 1996 without consent, and sought declarations of nullity, cancellation of the 3rd defendant's title, registration in his name and damages. Defences were filed in March and May 2017, after which the only step was a letter from the plaintiff's advocates dated 8 June 2017/2018 requesting a mention date. The plaintiff filed no response to the motion but counsel submitted from the bar that no mention dates were available. The court, Munyao Sila J, held that Order 17 Rule 2 permits dismissal where no step is taken for a year, but treating the letter requesting a mention date as a step, the mandatory one-year period had not lapsed and the application was premature. The court acknowledged the practice of filing dilatory letters but, in the circumstances, gave the plaintiff the benefit of doubt. The application was dismissed with no orders as to costs, and the plaintiff was given a chance to ventilate his case.

Key legal issues

#
01

Whether the application to dismiss for want of prosecution was premature

Holding

The application was premature because the plaintiff's letter of 8 June 2018 requesting a mention date was a step taken within a year of the application

Reasoning

Order 17 Rule 2 permits the court, or any party, to seek dismissal where no step has been taken for one year. The suit was filed in December 2016, defences were filed in March and May 2017, and a letter seeking a mention date was delivered on 8 June 2018. The court acknowledged the practice of filing letters to feign keenness, but in the circumstances gave the plaintiff the benefit of doubt and held the one-year period had not lapsed.

p. 2
02

Whether the court may discount a letter filed merely to appear diligent

Holding

Yes - where a party delivers a letter to court with no genuine intention of taking a date, the court may in its discretion discount it in computing time, but this was not established here

Reasoning

The court recognised that congested court diaries sometimes make it genuinely difficult to secure dates, and that parties sometimes deliver letters without any intention of fixing dates. It preserved judicial discretion to discount such technical letters, but on the facts before it, without evidence to the contrary, the plaintiff was given the benefit of doubt.

p. 2

Legal principles established

#
  • A party's letter to the court requesting a mention date may constitute a step in the suit under Order 17 Rule 2, and where such a step was taken less than a year earlier, an application by a party to dismiss the suit for want of prosecution is premature; though the court retains discretion to discount a letter filed merely as a technical device

Court orders

#
  1. 1.The application dated 10 January 2019 seeking dismissal of the suit for want of prosecution is dismissed
  2. 2.No orders as to costs

Authorities

#

Legislation

  • Civil Procedure RulesOrder 17 Rule 2
  • Land Control ActConsent of the Land Control Board (as pleaded by the plaintiff)
Jurisdiction invoked
Order 17 Rule 2 of the Civil Procedure Rules (inherent case-management power to dismiss suits for want of prosecution)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Dickson Ngige Ngugi v Consolidated Bank Ltd (Formerly Jimba Credit Corporation Limited) & another [2019] KEELC 2051 (KLR)", Case Analysis (2019). Not stated in judgment (application dated 10 January 2019 in the pending suit). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/2051/eng@2019-07-04

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.