ELCStruck OutConstitutional Petition No. 16 of 2018· [2019] KEELC 1797 (KLR)

Hempstead Investments Limited v County Government of Mombasa & 2 others [2019] KEELC 1797 (KLR)

Environment and Land Court
31 July 2019
1,922 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~8 min to read original · ~4 min brief

The bottom line

#

A developer waited 422 days for a Mombasa building permit, but the court still struck out its case because it skipped the review process set by law.

What this practically means

#

Executive summary

#
Hempstead Investments Limited petitioned the Environment and Land Court at Mombasa seeking declarations that the County Government of Mombasa and its officers were bound by Chapter Six of the Constitution and Article 47 in processing its building application, an order of mandamus compelling issuance of a building permit for its proposed development on plot Mombasa/Block IX/159, and damages for delay. The Petitioner paid Kshs779,378 upon application in April 2017 and waited 422 days without approval or written reasons, alleging that the delay offended Articles 47, 43, 73 and 35. The 1st and 2nd Respondents opposed, asserting the Petitioner failed to provide structural calculations, a geotechnical survey report and to attend pre-submission meetings, and that the court lacked jurisdiction because the Petitioner had not exhausted the review and appeal mechanisms under Sections 13 and 15 of the Physical Planning Act, nor the remedies required under Sections 9(2) and 9(3) of the Fair Administrative Actions Act. The court acknowledged that 422 days is a long wait but found the Physical Planning Act provided a necessary alternative mechanism through the Liaison Committee and National Liaison Committee. Given the massive scale of the development and its potential environmental effects, the court held the Petition premature and ordered it struck out. All reliefs sought were declined. However, the court denied the Respondents costs, holding that they did not prudently carry out their duties.

Key legal issues

#
01

Exhaustion of alternative dispute mechanisms under the Physical Planning Act

Holding

The Petition was premature because the Petitioner did not seek review or appeal to the Liaison Committee as provided by Sections 13 and 15 of the Act

Reasoning

The court held that despite the 422-day delay being a long time, the Physical Planning Act establishes the National Liaison Committee to deal with review or appeals against decisions of the Director. The Petitioner was aware of these provisions yet did not explain why she did not apply for review. Where a necessary alternative mechanism exists, court intervention is premature, particularly given the massive scale and environmental impact of the proposed development.

p. 3
02

Delay in processing the building application

Holding

The 422-day delay was acknowledged as long, but the existence of the statutory review mechanism displaced the need for constitutional intervention

Reasoning

The Petitioner argued the delay was unexplained and violated Articles 73 and 47. The court accepted 422 days was a long waiting period but held that applicable law under the Physical Planning Act provides mechanisms for a dissatisfied party before coming to court. The Respondents attributed the delay to the Petitioner's own omissions, including failure to attend pre-submission meetings and provide structural calculations.

p. 3

Legal principles established

#
  • A litigant must first exhaust the review and appeal mechanisms provided under the Physical Planning Act before invoking the court's jurisdiction; failing which the petition is premature

Court orders

#
  1. 1.The Petition is struck out for being premature
  2. 2.All orders sought in the Petition are declined
  3. 3.The 1st and 2nd Respondents are not entitled to costs because they did not prudently carry out their duties

Authorities

#

Legislation

  • Constitution of Kenya, 2010Chapter Six, Article 73; Article 47; Article 43; Article 35; Article 2(1); Article 19(1)
  • Physical Planning Act (Cap 286)Sections 13(1), 15(1), 15(4), 31
  • Fair Administrative Actions Act No. 4 of 2015Sections 9(2) & 9(3)

Cases cited (5)

  • JSC –versus- Mbalu Mutava & Another
    (2015) eKLR
  • Kenya Human Rights Commission & Another –versus- NGO Co-ordination Board & Another
    (2018) eKLR
  • Erick Dunde & Another –versus- City Council of Nairobi & 3 Others
    (2016) eKLR
  • Ndiara Enterprises Ltd –versus- Nairobi City County Government
    (2018) eKLR
  • Mwangaza Humanitarian Assistance –versus- National Environment & Management Authority & 2 Others
    (2013) eKLR
Jurisdiction invoked
Original constitutional jurisdiction of the Environment and Land Court under the Constitution

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Hempstead Investments Limited v County Government of Mombasa & 2 others [2019] KEELC 1797 (KLR)", Case Analysis (2019). Constitutional Petition No. 16 of 2018. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/1797/eng@2019-07-31

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.