Fernando Vischi & another v Albert Mukare Mulewa & 6 others [2019] KEELC 1565 (KLR)
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Whether the 6th Defendant's Counterclaim should be struck out as unsustainable, abusive or time-barred
The application to strike out the Counterclaim failed; the dispute over title between the parties raises matters fit for trial
The court noted the long history of the suit and that the dispute concerns who between the Plaintiffs, 6th and 7th Defendants was the rightful owner of the suit properties. The 6th Defendant's title was cancelled and the 7th Defendant registered in May 2007; the circumstances of that cancellation could not be characterised as a sham at interlocutory stage. The court prioritised substantive justice and declined to strike out the Counterclaim, dismissing the application with costs to the 6th Defendant.
Whether the 6th Defendant was estopped from bringing a Counterclaim having withdrawn Malindi HCCC No. 78 of 2006
The court did not accept the estoppel argument as a basis for striking out the Counterclaim
The 7th Defendant argued that the 6th Defendant, having voluntarily withdrawn Malindi HCCC No. 78 of 2006 on 7th September 2007 and never paid costs, was estopped from claiming rights over the suit properties on which it had since made substantial investments. The 6th Defendant explained that the withdrawal was to avoid sub-judice proceedings after discovering the current suit. The court did not find merit in striking out on this basis.
Legal principles established
#- The primary duty of a court is to ensure substantive justice is served to all parties before it, and striking out pleadings should not be done where bona fide triable issues exist
Court orders
#- 1.The 7th Defendant's Notice of Motion dated 17th October 2018 is dismissed
- 2.Costs of the application to the 6th Defendant
- 3.The suit shall proceed as between the Plaintiffs and the 5th, 6th and 7th Defendants
- Jurisdiction invoked
- Original civil jurisdiction over land disputes transferred from the High Court (HCCC No. 12 of 2006, Mombasa) pursuant to transfer order of 24th October 2017
Key timeline
#Practical implications
#Frequently asked questions
#Later judgments citing this (2)
#Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.
- Dreamgeast Limited v Vischi & 7 others (Civil Appeal 157 of 2019) [2021] KECA 101 (KLR)[2021] KECA 101 (KLR)22 Oct 2021
- Dreamgeast Limited v Vischi & 7 others (Civil Appeal 157 of 2019) [2021] KECA 101 (KLR)[2021] KECA 101 (KLR)22 Oct 2021applied
Cite this brief
#Cite this brief
Caselaw, "Fernando Vischi & another v Albert Mukare Mulewa & 6 others [2019] KEELC 1565 (KLR)", Case Analysis (2019). HCCC No. 12 of 2006 (transferred to Malindi ELRC/ELC). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/1565/eng@2019-10-08
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.