Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCDismissedNot stated in the judgment as provided (suit number omitted; only the application dated 10th April 2019 is identified)· [2019] KEELC 1119 (KLR)

Esther Cheptanui Chebii & 3 others v Sbi International Holdings (Ag) K & another [2019] KEELC 1119 (KLR)

Environment and Land Court
29 October 2019
5,354 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~21 min to read original · ~4 min brief

The bottom line

#

A Kenyan court refused to stop a road campsite next to homes because the residents had no strong evidence the project breached environmental law.

What this practically means

#

Executive summary

#
This was a ruling of the Environment and Land Court at Nyahururu (M.C. Oundo, Judge) on the Plaintiffs' application dated 10th April 2019, brought under Order 40 Rules 1, 2 and 3 of the Civil Procedure Rules and Sections 1A, 1B and 3A of the Civil Procedure Act, seeking an interlocutory injunction to restrain the Respondents from operating from 269 Project Campsite, established for the maintenance of the Marigat Muchongai-Karandi, Ol Ng'arua Muhotetu-JNCT C77 and Muhotetu-Sipili roads. The Plaintiffs, members of one family (including a 9-month-old minor and the Estate of John Kiplangat) living about 4 metres from the campsite on title Laikipia/Lariak/50, complained of harmful fumes from a tar mixer and bitumen boiler, deafening noise, dust, a sparking high-voltage transformer, and walls marked 'caution radiation area'; they relied on medical reports, a public health officer's report recommending relocation, and their constitutional and EMCA rights to a clean and healthy environment, and urged the precautionary principle. The Respondents relied on NEMA and county approvals, an EIA by Peman Consultants Ltd, environmental audits showing air quality and noise within acceptable limits, and argued there was no empirical evidence of harm. The court applied the Giella v Cassman Brown principles as restated in Mrao and Nguruman, found the project duly cleared with public participation, held that no prima facie case was established, and, the Giella enquiry being sequential, dismissed the application with costs to the Respondents and vacated the interim orders, directing compliance with Order 11 within 21 days for the hearing of the main suit.

Key legal issues

#
01

Whether the Applicant established a prima facie case with a probability of success under the Giella v Cassman Brown principles

Holding

No prima facie case was established; the project had NEMA clearance, a duly conducted Environmental Impact Assessment by a lead expert, and public participation, and the Plaintiffs produced no empirical evidence of breach or harm

Reasoning

The court applied the Giella test and the Nguruman formulation of a prima facie case. Considering the Respondent's annexures and submissions, and without holding a mini trial, it found sufficient evidence that the project was cleared by the relevant authority including NEMA, that an EIA was done by a lead agency expert whose report found the project environmentally friendly, and that public participation occurred even though the Plaintiffs were not consulted. No provision of law was alleged to have been breached and the claims of harmful fumes, noise and radiation were unsupported by empirical data.

p. 7
02

Whether the interlocutory injunction could nonetheless issue on the balance of convenience or the precautionary principle

Holding

The second and third Giella conditions were not reached because the enquiry is sequential and the first condition failed

Reasoning

The court adopted the Joseph Wambua Mulusya v David Kitu formulation that the Giella conditions are sequential, so the second condition (irreparable injury) can only be addressed if the first (prima facie case) is satisfied. Having found no prima facie case, the balance of convenience and the precautionary principle invoked by the Plaintiffs fell away, and the application had to be dismissed with interim orders vacated.

p. 7

Legal principles established

#
  • The enquiry into whether to grant an interlocutory injunction is sequential; the second Giella condition (irreparable harm) is only addressed if the first (prima facie case) is satisfied
  • In considering a prima facie case the court does not hold a mini trial; it need only see that the applicant has a right apparently infringed or threatened with violation, on a balance of probabilities
  • A person alleging contravention of the entitlement to a clean and healthy environment under EMCA may seek redress, and statutory approvals, permits and licences obtained under the law weigh in favour of the project proponent where no breach is demonstrated

Court orders

#
  1. 1.The application dated 10th April 2019 is dismissed with costs to the Respondents
  2. 2.The interim orders vacated - the Defendant/Respondent is no longer restrained from operating the machines at 269 Project Campsite
  3. 3.Parties to comply with the provisions of Order 11 of the Civil Procedure Rules within the next 21 days for the hearing of the main suit

Authorities

#

Legislation

  • Civil Procedure RulesOrder 40 Rules 1, 2 and 3
  • Civil Procedure ActSections 1A, 1B and 3A
  • Civil Procedure RulesOrder 11
  • Constitution of KenyaArticles 42 and 70
  • Environmental Management and Co-ordination Act (EMCA), Cap 387Sections 3, 58, 59 and 60
  • Radiation Protection Act, Cap 243 Laws of KenyaNot specified (licence for nuclear density gauge unit)

Cases cited (12)

  • Giella vs Cassman Brown
    [1973] EA 358
  • E.A. Industries v. Trufoods
    [1972] E.A. 420
  • MRAO versus FIRST AMERICAN BANK OF KENYA LIMITED & 2 OTHERS
    (2003) KLR 125
  • Nguruman Ltd vs Jan Bonde Nielsen & Others
    C.A civil Appeal No. 77 of 2012
  • Joseph Wambua Mulusya –vs-David Kitu & Another
    (2014) eKLR
  • Ken Kasing’a vs Daniel Kiplagat Kirui & 5 Others
    [2015] eKLR
  • Erick Ochieng vs Frederick Aila Onyango
    (2018) eKLR
  • Deepak Harakch & Another vs Anmol Ltd & 4 Others
    (2018) eKLR
  • Diani Road Developers Ltd & 10 Others vs Jerusha Kerubo Nyamweya & 4 Others
    (2015) eKLR
  • Aggrey Ogutu vs Daniel Kamau Mwangi, County Government of Kajiado & Another
    [2016] eKLR
  • Bart Kibati & 2 Others vs Harrow Investment Ltd and Another
    (2014) eKLR
  • Nixon Azaria vs Rose Weke & 2 Others
    (2014) eKLR
Jurisdiction invoked
Sections 1A, 1B and 3A of the Civil Procedure Act and Order 40 Rules 1, 2 and 3 of the Civil Procedure Rules (interlocutory injunctive relief), with the substantive claim founded on Article 42 and Article 70 of the Constitution and Section 3 of the Environmental Management and Co-ordination Act

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Esther Cheptanui Chebii & 3 others v Sbi International Holdings (Ag) K & another [2019] KEELC 1119 (KLR)", Case Analysis (2019). Not stated in the judgment as provided (suit number omitted; only the application dated 10th April 2019 is identified). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/1119/eng@2019-10-29