ELCDismissedOyugis Environment and Land Court Appeal (memorandum of appeal dated 19th October 2018, filed 25th September 2018) - two notices of motion dated 30th April 2019 and 20th May 2019· [2019] KEELC 219 (KLR)

John Mbewa Olande v Kibiri Construction and Trading Company Limited [2019] KEELC 219 (KLR)

Environment and Land Court of Kenya
12 November 2019
2,670 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~11 min to read original · ~4 min brief

The bottom line

#

The Environment and Land Court refused to stop execution of a land decree because the appellant waited over six months before applying and offered no security.

What this practically means

#

Executive summary

#
This ruling of the Environment and Land Court at Migori (G.M.A Ong'ondo, J) determines two interlocutory applications by John Mbewa Olande, the appellant in an appeal against the judgment of the Senior Resident Magistrate (Hon. J.P. Nandi) in Oyugis CMCC No. 115 of 2015, in which Kibiri Construction and Trading Company Limited obtained eviction, permanent injunction and costs over land parcel West Karachuonyo/Koyugi/501. The first application, dated 30th April 2019, sought stay of execution of the trial decree pending appeal; it was brought under Order 40 of the Civil Procedure Rules although no temporary injunction was sought. The second, dated 20th May 2019, sought review of the court's orders of 6th May 2019 and an interlocutory injunction restraining Ikimwenya Auctioneers from attaching proclaimed property. The respondent opposed both, showing that a warrant of attachment had been executed and ten of the applicant's cows sold in partial satisfaction of costs. The court held that although the misquoting of a statutory provision was not by itself fatal (following Gatu v Muriuki), and that it enjoyed jurisdiction under section 13(7)(a) of the Environment and Land Court Act to grant preservation orders, the stay application failed the Order 42 Rule 6(2) prerequisites: it was mounted after an inordinate, unexplained delay of about 6½ months, substantial loss was not demonstrated, no security was offered, and execution had already occurred, overtaking the application. The review application failed to meet the Order 45 conditions. Both applications were disallowed with costs in the cause on 12th November 2019.

Key legal issues

#
01

Whether the applicant satisfied the prerequisites for stay of execution pending appeal under Order 42 Rule 6(2) of the Civil Procedure Rules

Holding

The prerequisites were not satisfied: the application was brought after an inordinate and unexplained delay of about 6½ months, substantial loss was not demonstrated, no security was offered, and the warrant of attachment had already been executed

Reasoning

The court outlined the three conditions under Order 42 Rule 6(2): no undue delay, substantial loss, and security. Judgment was delivered on 12th September 2018 but the 1st application was filed on 2nd May 2019, a delay of close to 6½ months with no reasons offered. The applicant also failed to demonstrate substantial loss or offer security, and execution had already proceeded by return of sale, overtaking the application.

p. 3
02

Whether the misquoting of Order 40 (temporary injunctions) instead of Order 42 Rule 6 in the 1st application was fatal

Holding

No - a wrong provision is not by itself a sound basis for dismissal, since the court has power under section 13(7)(a) of the Environment and Land Court Act to grant preservation and interlocutory orders including stays

Reasoning

The court noted that the applicant relied on Order 40, which governs temporary injunctions, yet sought a stay of execution. Relying on Gatu v Muriuki, it held that erroneously citing a wrong provision alone does not justify dismissal. The court then assessed the application on its merits under the correct principles for stay, applying Order 42 Rule 6(2) and its inherent preservation mandate.

p. 3
03

Whether the 2nd application for review under Order 45 was meritorious

Holding

It was not; the application failed to meet the prescribed conditions for review, and the respondent had not replied to it but opposed it in submissions

Reasoning

The court was conscious of the conditions for review under Order 45. The applicant's own affidavit admitted the court's observations and directions of 6th May 2019, which the review sought to vacate. The application was also, in the respondent's view, inordinate, an abuse of process and overtaken by events since attachment had been executed. The court found the respondent's contention sound and disallowed the application.

p. 4

Legal principles established

#
  • An application for stay of execution pending appeal must satisfy the three conditions in Order 42 Rule 6(2): brought without undue delay, demonstration of substantial loss, and provision of security for due performance of the decree
  • An application for stay of execution must be made without undue delay; unexplained and inordinate delay is fatal, since delay defeats equity
  • Citing a wrong statutory provision is not by itself a sound basis for dismissing an application where the court otherwise has power to grant the relief
  • An Environment and Land Court is fully mandated to grant preservation orders including injunctions under section 13(7)(a) of the Environment and Land Court Act, and a stay of execution may be characterised as an interlocutory or preservation order

Court orders

#
  1. 1.The 1st application dated 30th April 2019 is disallowed with costs in the cause
  2. 2.The 2nd application dated 20th May 2019 is disallowed with costs in the cause
On appeal from
Oyugis Principal Magistrate's Court
Oyugis CMCC No. 115 of 2015
Jurisdiction invoked
Section 13(7)(a) of the Environment and Land Court Act, 2015; appellate and supervisory jurisdiction over the subordinate court decree in Oyugis CMCC No. 115 of 2015

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "John Mbewa Olande v Kibiri Construction and Trading Company Limited [2019] KEELC 219 (KLR)", Case Analysis (2019). Oyugis Environment and Land Court Appeal (memorandum of appeal dated 19th October 2018, filed 25th September 2018) - two notices of motion dated 30th April 2019 and 20th May 2019. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/219/eng@2019-11-12

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.