The bottom line

#

The Environment and Land Court dismissed Simba Corporation's challenge to a massive rent increase because it sued Kenya Railways too early, skipping a mandatory 30-day notice step.

What this practically means

#

Executive summary

#
The plaintiff, Simba Corporation Limited, lessee of Mombasa/Block XLVIII/114 under an 81-year lease originally granted in 1966/1967, challenged the 1st defendant's unilateral revision of annual rent from Kshs.27,000 to Kshs.2,815,720 by notice dated 13th October 2010, seeking declarations that the increase was unlawful, an injunction restraining interference with its possession, and costs. The plaintiff commenced suit on 22nd May 2013, before expiry of the 30-day statutory notice period. The 1st defendant contended the suit was premature and incompetent for violating section 87(a) of the Kenya Railways Corporation Act, that its right to review rent was intact, and that the plaintiff was in breach including late payment. The court framed four issues. First, it held section 87(a) is mandatory and, following Peter Nzioka Mani & Another v Kenya Railways Corporation, struck out the plaint as premature and incompetent. Nevertheless it proceeded to determine the merits: the 1st defendant's failure to increase rent after the first 30 years did not extinguish or waive its right to review rent in 2010; the notice of increment was not illegal or unlawful as the Corporation had conducted a valuation through unchallenged professional valuers, while the plaintiff's valuer's sources were unattached; and the apparent increment included penalties for late payment. The plaintiff failed to prove its case on a balance of probabilities and was not entitled to the prayers sought. The suit was dismissed with costs to the 1st defendant.

Key legal issues

#
01

Prematurity and incompetence of the plaint for violating section 87(a) of the Kenya Railways Corporation Act

Holding

The plaint is premature and incompetent and is struck out

Reasoning

Section 87(a) is set in mandatory terms and requires one month's written notice of the claim before commencing proceedings against the Corporation. The plaintiff admitted commencing proceedings before expiry of the 30 days and offered no reasonable justification. Guided by the Peter Nzioka Mani authority, the court held the suit premature and incompetent.

p. 3
02

Whether the 1st defendant's failure to increase rent after the first 30 years extinguished its right to review rent in 2010

Holding

The right to review rent was not extinguished by the failure to exercise it earlier

Reasoning

Nothing prevented the 1st defendant from increasing rent even after expiry of the first thirty years. The plaintiff's own witness admitted the apparent increment was annual rent inclusive of penalties for late payment, and correspondence showed the plaintiff was aware the right to increase rent had never been waived or extinguished.

03

Whether the notice of rent increment dated 13th October 2010 was illegal or unlawful

Holding

The notice was not illegal or unlawful

Reasoning

The 1st defendant did a valuation before increasing the rent and had professional valuers capable of internal valuation; this evidence was not challenged. The plaintiff's valuer conceded her sources were not attached to her report. The plaintiff did not demonstrate the assessment was done wrongly.

Legal principles established

#
  • An action against the Kenya Railways Corporation shall not be commenced until at least one month after written notice containing particulars of the claim has been served upon the managing director
  • Non-compliance with the statutory notice requirement renders a suit premature and incompetent

Court orders

#
  1. 1.The plaint is struck out as premature and incompetent
  2. 2.The plaintiff's suit is dismissed with costs to the 1st defendant

Authorities

#

Legislation

  • Kenya Railways Corporation ActSection 87(a)

Cases cited (8)

  • Republic vs Kenya Railways & Another Exparte Involatte Wacike Siboe
    [2014] eKLR
  • Kenya Bus Services Limited & Another vs Minister for Transport & 2 Others
    [2012] eKLR
  • The Law Society of Kenya vs Kenya Revenue Authority & Another
    [2017] eKLR
  • National Bank of Kenya Ltd vs Pipe Plastic Smkolit (K) Ltd & Another
    [2001] eKLR
  • Serah Njeru Mwobi vs John Kimani Njoroge
    [2013] eKLR
  • Peter Nzioka Mani & Another vs Kenya Railways Corporation
    [2012] eKLR
  • Kenya Breweries Limited & Another vs Washington O. Okeyo
    [2002] eKLR
  • Aziz vs Bhalia Brothers Ltd
    [2001] 1EA
Jurisdiction invoked
Environment and Land Court, original jurisdiction over lease of land (ELC Civil Case No. 104 of 2013)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Simba Corporation Limited v Kenya Railways Corporation & another [2019] KEELC 34 (KLR)", Case Analysis (2019). ELC Civil Case No. 104 of 2013. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2019/34/eng@2019-11-07

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.