Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedPetition dated 10th July 2014, filed 11th July 2014

Prinsal Enterprises Limited v Kenya Electricity Transmission Co. Limited [2018] KEELC 3045 (KLR)

Environment and Land Court
12 April 2018
1,881 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~8 min to read original · ~4 min brief

The bottom line

#

A Kenyan court ruled that power line wayleaves compensate only the affected strip of land, awarding Kshs 13.5 million instead of the claimed Kshs 66 million.

What this practically means

#

Executive summary

#
The petitioner, registered owner of Juja/Komo Block 2/1670 (about 11 acres / 4.55 ha), petitioned the court alleging that the respondent, having laid 132 KV electricity transmission power lines across the land from 2010, violated its constitutional right to property and unlawfully invaded the land. It sought declarations of violation and invasion, general damages, and costs, claiming compensation for the entire parcel at Kshs 6 million per acre (Kshs 66 million) plus rental income at Kshs 300,000 per acre per month, relying on its own valuation. The respondent, through the affidavit of Johnson Muthoka, acknowledged laying the lines over 23.21% of the parcel but explained it could not identify the owner because the parcel had been wrongly captured as LR 10080/1; it offered Kshs 3,196,555/- (later computed as Kshs 3,197,250/-), being 35% of the value of the affected area at an open market value of Kshs 3.5 million per acre, consistent with the standard practice that wayleave compensation is limited to loss of use and does not transfer the land. Ownership was undisputed. The court held that the entry was not trespass given the respondent's inability to identify the parcel and owner, and framed the sole issue as adequate compensation. Adopting the respondent's valuation and the 35% rate over the affected acreage, the court awarded Kshs 13,475,000/- payable within 45 days, refusing whole-parcel compensation and rental income. No costs order was made in the disposition.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the respondent's entry onto the suit property and laying of electricity transmission power lines constituted a violation of the petitioner's right to property and an unlawful invasion/trespass
  2. 2.What compensation is adequate in respect of the portion of the suit property taken up by the electricity power lines

Key legal issues

#
01

Whether the laying of electricity transmission lines on private land amounts to compulsory acquisition requiring compensation for the whole parcel

Holding

No - the laying of power lines is a wayleave acquisition conferring a limited right of use over the affected portion only, compensable at a percentage of the value of that portion, not the entire land

Reasoning

The court noted ownership was undisputed and that only 23.21% of the 4.55 ha parcel was affected. The respondent's survey showed the interest acquired was limited to prohibiting trees over 3.5m and building structures within the wayleave. The court adopted a 35% compensation rate applied to the respondent's open market value of Kshs 3.5 million per acre across 11 acres, rejecting the petitioner's whole-parcel valuation of Kshs 66 million.

p. 2
02

Whether the respondent's entry onto the suit property constituted trespass and violation of the constitutional right to property

Holding

It was not trespass, as the respondent was unable to identify the proper parcel and its owner due to faulty land reference details and acted with a view to compensate

Reasoning

The respondent surveyed and valued the land in 2010 but could not trace the owner because the parcel was captured as LR 10080/1, a faulty reference. Other neighbouring parcels were compensated. Only in 2014 did the respondent identify the petitioner and make an offer of Kshs 3,196,555/-. The court accepted this explanation and held the entry was not a trespass, though compensation remained due for the use of the land.

p. 2

Legal principles established

#
  • Compensation for wayleave acquisition is limited to loss of use of the affected portion of land rather than outright purchase of the entire parcel
  • Entry onto land to lay electricity lines with an intention to compensate, occasioned by inability to identify the registered owner, does not constitute trespass

Court orders

#
  1. 1.Judgment entered in favour of the petitioner in the sum of Kshs. 13,475,000/- to be paid by the respondent within 45 days from the date of delivery of the judgment

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

majority

Wrote the judgment

majority
Jurisdiction invoked
Petition alleging contravention of the fundamental right to property (constitutional petition)

Relief refused

#

Declaration that the petitioner's fundamental right to property was violated, transgressed on and trampled upon by the respondent

The court found the entry was not trespass as the respondent could not identify the proper parcel owner at the time and was willing to compensate

p. 2

Declaration that the respondent illegally and unlawfully invaded the petitioner's land

The respondent's actions were explained by faulty parcel identification and it did not claim ownership nor dispute traversing the land

p. 2

Claim for compensation for the entire parcel of land (Kshs 66 million at Kshs 6 million per acre)

Only 23.21% of the parcel was actually used for the power lines; the court adopted the respondent's valuation of Kshs 3.5 million per acre

p. 3

Claim for rental income at the rate of Kshs 300,000 per acre per month

The court declined to award anything towards rental income

p. 3

Costs

Not expressly stated in the judgment; the petitioner had sought costs of the petition in the prayer but the disposition makes no costs order.

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

Accordingly, judgment is entered in this suit in favour of the petitioner in the sum of Kshs. 13,475,000/- to be paid by the respondent within 45 days from the date of delivery of this judgment.
p. 3Final orders - compensation award and payment period
I will go with the value accorded by the respondent in to calculate their compensation value to be given to the petitioner by the respondent as 35% of 11 acres multiplied by the open market value at Kshs. 3.5 million to arrive at Kshs. 13,475,000/-.
p. 3Method of assessing wayleave compensation
In the circumstances I would find that this is not a case of trespass.
p. 2Rejection of the trespass and rights-violation claim
He noted that it is a generally accepted and standard practice that compensation for way leave acquisition is normally limited to loss of use of one's land without changing any transfer of the land as opposed to outright purchase
p. 2Standard practice in wayleave compensation

Issues in the judgment

#
minor

The judgment contains garbled/typographical passages, e.g. on the reason the petitioner could not be contacted and on the rental income award: "I will not want anything towards rental income." (apparently intended as 'I will not grant anything towards rental income').

minor

The replying affidavit figures differ slightly between the offer letter (Kshs. 3,196,555/-) and the supplementary affidavit computation (Kshs. 3,197,250/-), and the respondent's 35% offer is described in one place as a 'higher rate of 35%'.

minor

The disposition makes no express order on costs despite the petitioner's prayer for costs of the petition.

minor

Signature and delivery dates differ: signed and dated 12th April 2018 by Justice Mary M. Gitumbi but delivered 19th April 2018 by Justice Samson Okongo.

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Prinsal Enterprises Limited v Kenya Electricity Transmission Co. Limited [2018] KEELC 3045 (KLR)", Case Analysis (2018). Petition dated 10th July 2014, filed 11th July 2014. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2018/3045/eng@2018-04-19

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.