Hassan Said Salim Mbarak & another v Awadh Mohamed & another [2018] KEELC 2788 (KLR)
The bottom line
#A Mombasa court let a nearly complete building continue but blocked neighbours from interfering, warning that delays in seeking injunctions can cost you that remedy.
What this practically means
#Executive summary
#Key legal issues
#Whether the Plaintiffs established the threshold for an interlocutory injunction against the Defendants
The Plaintiffs established a prima facie case with probability of success, showed irreparable damage not quantifiable in damages, and the balance of convenience favoured them; injunction granted
The court found the Plaintiffs had shown their right to undertake construction without interference, that interference damage would be enormous and unquantifiable given completion timelines, and that the balance of convenience tilted towards them. At the interlocutory stage the merits of the suit and counter-claim were not determined; conflicting evidence on encroachment and approvals was left for full hearing.
Whether the Defendants were entitled to an injunction stopping the Plaintiffs' construction
Refused because the application was brought late, after the construction had neared completion, and there was no prima facie showing of illegality by the Plaintiffs
The acts complained of had commenced earlier and reached near completion. Regulatory bodies had issued conflicting reports and there was no evidence of enforcement action for violation. The Defendants' remedy lay in their claim for damages through the counter-claim rather than a restraining order at that stage.
Legal principles established
#- Interlocutory injunctions are granted on the Giella v Cassman Brown principles: prima facie case with probability of success, irreparable injury not compensable in damages, and balance of convenience where the court is in doubt
- Where an interlocutory dispute turns on a conflict of affidavit evidence, the court will decline to determine it and leave the matter to full trial
- Injunction will not issue to restrain acts already substantially completed; the remedy is damages
Court orders
#- 1.The Notice of Motion dated 28th June 2017 is allowed in terms of prayer 3 thereof (interlocutory injunction restraining the Defendants from interfering with the construction on PLOT NO.85/XLVI/MI pending hearing and determination of the suit)
- 2.The Notice of Motion dated 11th July 2017 is dismissed
- 3.The Notice of Motion dated 2nd August 2017 is already spent
- 4.The Notice of Motion dated 7th August 2017 is already spent
- 5.Each party to bear their own costs
- Jurisdiction invoked
- Order 40 Rules 1, 2, 3 and 9 of the Civil Procedure Rules; Article 40 of the Constitution; Sections 1A, 1B, 3A and 80 of the Civil Procedure Act; Section 19 of the Environment and Land Court Act; inherent power of the Court
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Hassan Said Salim Mbarak & another v Awadh Mohamed & another [2018] KEELC 2788 (KLR)", Case Analysis (2018). PLOT NO.85/XLVI/MI suit (Notice of Motion dated 28th June 2017 with related motions dated 11th July 2017, 2nd August 2017 and 7th August 2017). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2018/2788/eng@2018-07-05
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.