ELCDismissedNairobi BPRT Case No. 95 of 2015 (Appeal)· [2018] KEELC 2143 (KLR)

Shade Manufacturers & Hotel Limited v Serah Mweru Mutuu & 3 others [2018] KEELC 2143 (KLR)

Environment and Land Court
10 July 2018
891 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~4 min to read original · ~4 min brief

The bottom line

#

A Nairobi tenant lost its bid to pause an eviction order because it couldn't show it would suffer substantial loss or offer security.

What this practically means

#

Executive summary

#
This is a ruling of the Environment and Land Court at Nairobi (K. Bor, J) on a notice of motion dated 15/12/2017 in which the Appellant, a tenant running a hotel and restaurant on L.R. No. 192/19, Karen, Nairobi, sought a stay of execution of the judgment and order of the Business Premises Rent Tribunal delivered on 13/10/2017 by its Chairman, Mr. Mbichi Mboroki, in Nairobi BPRT Case No. 95 of 2015. The Tribunal had dismissed the Appellant's Reference, allowed the Respondents' Termination Notice requiring the Appellant to vacate and hand over vacant possession by 1/5/2018, and ordered removal of all its improvements. The Appellant argued under Order 42 Rule 6(1) and (2) of the Civil Procedure Rules that it would suffer substantial loss given its heavy investment since 1981, that the application was made timeously, and that its appeal was arguable and would be rendered nugatory if evicted. It relied on Butt v Rent Restriction Tribunal, Masisi Mwita v Damaris Wanjiku Njeri and Machira v East African Standard (No. 2). The Respondents, through Louis Waithera, maintained they terminated the tenancy to develop the property. The court held that the Appellant had not demonstrated substantial loss and had not furnished security for the performance of the Tribunal's order. The application was dismissed with costs to the Respondents.

Key legal issues

#
01

Whether the Appellant established substantial loss

Holding

Substantial loss was not established

Reasoning

The court weighed the Appellant's claim that it had invested heavily and made improvements on the property since 1981 against the decision of the Tribunal. It found that the Tribunal had allowed the termination notice and given the Appellant six months to remove its structures. On the material presented, including the Respondent's stated intention to develop the property, the court was not satisfied that the tenant-Appellant would suffer substantial loss if stay was refused.

p. 2
02

Whether security for the due performance of the Tribunal's order was furnished

Holding

No security was furnished, undermining the stay application

Reasoning

Under Order 42 Rule 6(2), an applicant for stay must offer security for the due performance of the decree. The judgment records that the Appellant had not furnished security for the performance of the Chairman's order. The absence of security, coupled with the failure to demonstrate substantial loss, meant the application failed on the established criteria.

p. 2

Legal principles established

#
  • A stay must be granted so that an appeal may not be rendered nugatory, absent any overwhelming hindrance
  • A successful party is ordinarily entitled to the fruits of his judgment, subject to the overriding objective of doing justice

Court orders

#
  1. 1.The application dated 15/12/2017 seeking stay of execution of the BPRT judgment and order of 13/10/2017 is dismissed
  2. 2.Costs of the application to the Respondents

Authorities

#

Legislation

  • Civil Procedure RulesOrder 42 Rule 6(1) & (2)

Cases cited (3)

  • Butt v Rent Restriction Tribunal
    Civil Application No. NAI 6 of 1979
  • Masisi Mwita v. Damaris Wanjiku Njeri
    [2016] eKLR
  • Machira T/A Machira & Co. Advocates v East African Standard (No. 2)
    [2002] KLR 63
On appeal from
Business Premises Rent Tribunal (BPRT)
Nairobi BPRT Case No. 95 of 2015
Jurisdiction invoked
Order 42 Rule 6(1) & (2) of the Civil Procedure Rules (appeal from the Business Premises Rent Tribunal)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Shade Manufacturers & Hotel Limited v Serah Mweru Mutuu & 3 others [2018] KEELC 2143 (KLR)", Case Analysis (2018). Nairobi BPRT Case No. 95 of 2015 (Appeal). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2018/2143/eng@2018-07-10

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.