ELCDismissedNot stated in the judgment (suit filed 27th July 2017; Notice of Motion dated 26th January 2018)· [2018] KEELC 172 (KLR)

Vision Peoples in Mission Limited & another v Ministry of Lands, Housing & Urban Development & 3 others [2018] KEELC 172 (KLR)

Environment and Land Court
13 December 2018
2,191 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~9 min to read original · ~4 min brief

The bottom line

#

A Nairobi court refused to stop the Korogocho slum upgrading project, holding that churches and landowners suing for money cannot also block public development.

What this practically means

#

Executive summary

#
The plaintiffs, owner of L.R No. 27070 (Grant No. 966133), Korogocho, Nairobi, and a church running a school, medical centre, vocational training centre and feeding programme on the property, sued the defendants for Kshs.4,711,900/= as the cost of demolitions and losses occasioned by the Korogocho road expansion and Slum Upgrading Programme (KSUP), including demolition of their gate, wall and church building and the loss of two plots belonging to the 2nd plaintiff. About five months after filing suit, they moved the court by Notice of Motion dated 26th January 2018 seeking to restrain any transaction, demarcation, demolition, subdivision, sale or related activity on the suit property pending the hearing of the suit. The defendants, through a replying affidavit of Kenneth Nyaseda, explained that KSUP was a public slum-upgrading project; that the plaintiffs' structures had encroached on a road reserve; that the 1st plaintiff had surrendered its title, which had anomalies, to facilitate survey and issuance of a fresh title; and that the plaintiffs had been allocated a parcel accommodating their structures. After hearing counsel, the court held that the plaintiffs had not established a prima facie case with a probability of success, since they had not shown how the defendants had interfered with their interest in property whose title they had already surrendered. The court further held that any loss was compensable in damages: the demolition loss was liquidated at Kshs.4,711,900/=, and the value of the reduced land could be assessed. The Notice of Motion was dismissed with costs to the defendants. The main suit seeking the Kshs.4,711,900/= compensation remains for trial.

Key legal issues

#
01

Whether the conditions for grant of an interlocutory injunction were met

Holding

The conditions were not met; the application was dismissed with costs

Reasoning

The court considered the plaintiffs' affidavit and the defendants' replying affidavit and counsel's submissions. The plaintiffs did not demonstrate how the defendants had interfered with their interest in the suit property, whose title they appeared to have already surrendered. The claim was quantified at Kshs.4,711,900/= for demolition losses, and the loss of land after surrender was assessable by valuation, so damages were an adequate remedy and no prima facie case or irreparable harm was shown.

p. 3

Legal principles established

#
  • An applicant for an interlocutory injunction must establish a prima facie case with a probability of success and irreparable harm not compensable in damages
  • A claim for a liquidated, assessable amount in damages is inconsistent with a claim of irreparable harm, and a party who did not plead injunctive relief cannot obtain it on interim application

Court orders

#
  1. 1.The Notice of Motion dated 26th January 2018 was dismissed
  2. 2.Costs of the application awarded to the defendants
Jurisdiction invoked
Original civil suit (plaint) before the Environment and Land Court; specific provision not stated in the judgment

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Vision Peoples in Mission Limited & another v Ministry of Lands, Housing & Urban Development & 3 others [2018] KEELC 172 (KLR)", Case Analysis (2018). Not stated in the judgment (suit filed 27th July 2017; Notice of Motion dated 26th January 2018). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2018/172/eng@2018-12-13