Thomas Mumo Maingey v Sarah Nyiva Hillman & 3 others [2017] KEELC 2468 (KLR)
The bottom line
#The Machakos Environment and Land Court held that an unsurveyed road on private land is a private road, dismissed the Plaintiff's injunction, and barred him from using 39 Quarry Road.
What this practically means
#Executive summary
#Key legal issues
#Whether the Plaintiff established a prima facie case for an interlocutory injunction over 39 Quarry Road
The Plaintiff failed to establish a prima facie case with chances of success; survey records, the Director of Surveys, the County Surveyor and the National Land Commission all confirmed no public road passes through the suit plots.
The court examined the Deed Plan, sub-division plans and survey approvals. The proposed road appeared only as dotted lines (a proposal) in the executors' sub-division plan, and the Director of Surveys approved Deed Plans without the road. Authoritative letters from the Director of Surveys, the Machakos County Surveyor and the National Land Commission confirmed the plots are accessed from a common road along their North-Western boundary and that no surveyed public road traverses them.
Whether 39 Quarry Road is a public or private road
Any road traversing the larger parcel had not been surveyed and was therefore a private road, capable of surrender only with the consent of the registered proprietors.
Although the executors proposed the road in the sub-division plan, the approved survey plan F/R 337/63 did not accept the proposal and the Deed Plans issued excluded it. The court found no evidence of a public road traversing the land before acquisition in 1971, and the National Land Commission confirmed the road was neither surveyed nor documented as an easement.
Legal principles established
#- A party claiming a public right of way must show it was surveyed or otherwise legally established; an unsurveyed road on private land is a private road
- A private road can only be surrendered as public access with the consent of the affected registered proprietors
Court orders
#- 1.The Plaintiff's Application dated 9th April 2015 was dismissed
- 2.The Plaintiff and his servants be restrained from interfering or using the road known as '39 Quarry Road' pending the hearing and determination of the suit
- 3.The OCPD Athi River Police Station to enforce the order of the court
- 4.The Plaintiff to pay the costs of the Defendants' Application
- 5.The suit to be set down for pre-trial directions and hearing
- Jurisdiction invoked
- Original jurisdiction of the Environment and Land Court over land and rights of way (not expressly stated in the ruling)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Thomas Mumo Maingey v Sarah Nyiva Hillman & 3 others [2017] KEELC 2468 (KLR)", Case Analysis (2017). Not stated in the judgment as provided. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2017/2468/eng@2017-07-13
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.