ELCPartially AllowedNotice of Motion dated 8th August 2016 in pending suit· [2017] KEELC 2100 (KLR)

FEB Holdlings Limited v Charles Magua alias Charles Henry Mangua [2017] KEELC 2100 (KLR)

Environment and Land Court
14 July 2017
2,506 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~10 min to read original · ~4 min brief

The bottom line

#

A Kenyan court halted rock blasting next to a hotel under construction because the neighbour could not show a blasting permit.

What this practically means

#

Executive summary

#
The plaintiff, registered proprietor of land parcel KIINE/RUKANGA/3513 on which a four-storey Suntec Hotel was under construction, brought a Notice of Motion dated 8th August 2016 seeking a temporary injunction restraining the defendant, proprietor of adjacent parcels KIINE/RUKANGA/2876 and 2877, from rock drilling, blasting, extraction or quarry mining operations that allegedly threatened the hotel's structural integrity, workers' safety and the environment, and an order directing the OCS Sagana Police Station to enforce the court's order. The plaintiff contended the blasting lacked NEMA, Mining Act and Explosives Act licences and produced photographs (annexture SM 3) showing a drilling machine and scattered rocks. The defendant denied blasting, asserting he was only levelling ground with bulldozers to build a house and create access, and argued the licensing complaint was a criminal matter for the Police. Applying Giella v Cassman Brown, the court found a prima facie case: the photographic evidence showed blasting, and the defendant failed to demonstrate the permit required by Section 11(1) of the Explosives Act (Cap 115). The court also found potential irreparable environmental and structural harm not compensable by damages, and that the balance of convenience favoured the plaintiff. It accordingly issued a temporary injunction pending trial. However, it declined the prayer for Police enforcement, following Kamau Mucuha v Ripples Ltd, holding the Police should not be involved in enforcing civil orders, compliance being secured under Order 40 rule 3(1) of the Civil Procedure Rules. Costs were in the cause, and parties were directed to comply with pre-trial directions for hearing within twelve months.

Key legal issues

#
01

Prima facie case for temporary injunction

Holding

The plaintiff established a prima facie case: photographic evidence (annexture SM 3) showed a drilling machine and scattered rocks on the defendant's properties, and the defendant gave no evidence of holding the permits required by Section 11(1) of the Explosives Act, making his activities prima facie unlawful.

Reasoning

The court accepted that the parcels are adjacent and that blasting activities were demonstrably occurring on the defendant's land based on the photographs. The defendant's own admission that the plaintiff's agents entered to take photos confirmed the photos were taken there. The defendant, expected to show a permit, instead argued the licensing issue was a criminal matter. Activities in apparent contravention of the law threatening the plaintiff's property justified the injunction.

p. 3
02

Irreparable injury / environmental hazard

Holding

The plaintiff satisfied the second Giella limb because the alleged blasting could cause the hotel under construction to collapse, endanger workers, and cause environmental hazards whose irreversible impacts damages may not adequately compensate.

Reasoning

The plaintiff alleged imminent danger to the hotel, workers' lives and adjacent properties from flying debris, plus environmental threat. The court reasoned that environmental hazardous acts often have irreversible impacts, so damages may be insufficient, and a court would not hesitate to grant a temporary injunction against a continuing environmental violation.

p. 4
03

Balance of convenience

Holding

If in doubt (which the court said it was not), the balance of convenience tilted in favour of granting the temporary injunction.

Reasoning

The court stated that even were it in doubt, the balance of convenience favoured the plaintiff, completing the third Giella limb and reinforcing entitlement to the injunction.

p. 4
04

Order directing Police to enforce the injunction

Holding

Refused. Courts should not direct the Police to enforce civil injunction orders; compliance mechanisms exist under the Civil Procedure Rules and the Police have their own statutory mandate.

Reasoning

Relying on Kamau Mucuha v Ripples Ltd, the court held Police should never be involved in enforcing civil injunctions. Order 40 rule 3(1) provides punishment for non-compliance, and Hadkinson establishes the obligation to obey court orders. The Police, under Section 24 of the National Police Service Act, already must intervene where the law is flouted without court prompting.

p. 4

Legal principles established

#
  • A transgression of the law likely to waste or damage another person's property is sufficient reason to warrant the grant of a temporary injunction pending suit.
  • A party alleging blasting activities should demonstrate possession of the requisite permit under Section 11(1) of the Explosives Act (Cap 115), which prohibits use of blasting materials without a valid miner's blasting certificate or permit.
  • Where there is a continuing violation of the environment, a court will issue a temporary injunction to mitigate environmental dangers because damages may be inadequate.
  • The Police should not be enlisted to enforce orders in civil proceedings; compliance is secured through the sanctions in the Civil Procedure Rules.

Court orders

#
  1. 1.Pending the hearing and determination of the suit, a temporary injunction restraining the defendant, his agents, servants, employees or any other person claiming under him from carrying out rock drilling, rock blasting, rock extraction or quarry mining operations on parcels KIINE/RUKANGA/2876 and 2877 or near parcel KIINE/RUKANGA/3513 or interfering with the plaintiff's quiet enjoyment of the suit land
  2. 2.Costs in the cause
  3. 3.Parties to comply with pre-trial directions so that the suit is heard and determined within twelve (12) months

Authorities

#

Legislation

  • Explosives Act (Cap 115)Section 11(1)
  • Explosives Act (Cap 115)Section 12
  • Mining Act (Cap 306)referenced in s.11(1) of Explosives Act
  • Environmental Management and Co-ordination Actnot specified (NEMA licences)
  • National Police Service ActSection 24
  • Civil Procedure RulesOrder 21 rule 28; Order 40 Rule 3(1)

Cases cited (6)

  • GIELLA VS CASSMAN BROWN & CO. LTD
    1973 E.A 358
  • MRAO VS FIRST AMERICAN BANK OF KENYA LTD & TWO OTHERS
    C.A CIVIL APPEAL No. 39 of 2002 (2003 e K.L.R)
  • NGURUMAN LTD VS JAN BONDE NIELSEN & OTHERS
    C.A CIVIL APPEAL No. 77 of 2012
  • FILMS ROVER INTERNATIONAL VS CANNON FILM SALE LTD
    1986 3 ALL E.R 772
  • KAMAU MUCUHA VS RIPPLES LTD
    1993 K.L.R 35
  • HADKINSON VS HADKINSON
    1952 ALL E.R 567
Jurisdiction invoked
Original civil jurisdiction over land disputes (Environment and Land Court) - provision not expressly stated

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "FEB Holdlings Limited v Charles Magua alias Charles Henry Mangua [2017] KEELC 2100 (KLR)", Case Analysis (2017). Notice of Motion dated 8th August 2016 in pending suit. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2017/2100/eng@2017-07-14

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.