Kenya Power & Lighting Company v Njumbi Road Residents Association [2017] KEELC 1762 (KLR)
The bottom line
#The Environment and Land Court refused to let Kenya Power keep its Lavington substation operational pending appeal, prioritising environmental safety over maintenance requests.
What this practically means
#Executive summary
#Key legal issues
#Whether maintenance of the substation pending appeal could be permitted
The application was dismissed because maintenance would entail operating the equipment, effectively allowing the appeal before admission and hearing
The court held that maintenance denotes the care and work put into equipment to keep it operational - repairing, replacing, servicing, inspecting and testing - which inevitably results in operating the equipment. NET had applied the precautionary principle, finding the substation posed risks to nearby residents. The appellant did not demonstrate how potential negative impacts on human health and the environment would be addressed. The court noted the appellant could move the equipment elsewhere for safekeeping and maintenance.
Balancing public interest in electricity supply against the right to a clean and healthy environment
The court is enjoined to balance the appellant's distribution function against the constitutional right to a clean and healthy environment; NET's precautionary finding of risk weighed against interim relief
The court acknowledged its duty to weigh the public interest in the appellant distributing electricity nationwide against the constitutional right of every person to a clean and healthy environment. NET had found the substation posed a risk to nearby residents and potential fire outbreaks and had applied the precautionary principle, including noting statutory avenues such as compulsory acquisition under the Land Act for safe relocation.
Legal principles established
#- An interlocutory order that would require operating the equipment subject to a cancelled licence pending appeal amounts to allowing the appeal before it has been admitted and heard
- A party seeking interim relief in an environmental appeal must show how it will deal with potential negative impacts on human health and the environment
Court orders
#- 1.The application dated 12/2/2016 is dismissed
- 2.Parties are directed to set down the matter for directions on the appeal
- On appeal from
- National Environmental Tribunal (NET)
- Jurisdiction invoked
- Appeal from NET under Section 130 of the Environmental Management and Coordination Act to the High Court, transferred to the Environment and Land Court
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kenya Power & Lighting Company v Njumbi Road Residents Association [2017] KEELC 1762 (KLR)", Case Analysis (2017). Appeal filed 2/4/2013 (Civil Appeals Division, High Court, transferred to ELD 19/11/2015). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2017/1762/eng@2017-09-27
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.