The bottom line

#

A Kenyan landlord recovered over Kshs 5 million from a former tenant for unpaid rent and unauthorized house alterations, with costs.

What this practically means

#

Executive summary

#
This was an undefended first-instance suit decided after formal proof. Kipkai Enterprise Limited, the plaintiff landlord, sued Maurine Louise Osembe, the defendant tenant, on a plaint dated 31st May 2016 seeking rental arrears of Kshs 4,020,000/-, an eviction order, restoration of the leased House No. 6 on LR No. 8272/46 to its original state, and costs. The plaintiff alleged the defendant defaulted on rent under a 3-year lease dated 1st December 2012 at Kshs 210,000/- monthly, and made extensive unauthorized alterations reducing the house from 3 to 2 bedrooms. The defendant filed neither appearance nor defence despite service, and judgment was taken under Order 10 rule 4 of the Civil Procedure Rules 2010, with formal proof conducted through testimony by Ms Njagi Nyaboke, a director of the plaintiff. The court considered the 25th January 2017 six-point mediation agreement under which Kshs 1 million was paid, Kshs 419,000/- written off, and the balance fixed at Kshs 3 million. Finding the claim proved on a balance of probability, the court awarded Kshs 2,210,000/- in rent arrears, Kshs 700,000/- for the unaccounted repair set-aside, Kshs 2,024,500/- restoration costs, plus Kshs 135,000/- electricity and Kshs 6,000/- water, entering judgment for Kshs 5,075,500/- with costs to the defendant. The eviction prayer was abandoned as overtaken by events.

Key legal issues

#
01

Quantum of rent arrears recoverable

Holding

Rent arrears of Kshs 2,210,000/- awarded: Kshs 2,000,000/- balance after the Kshs 1,000,000/- part payment and Kshs 419,000/- write-off, plus Kshs 210,000/- for January 2017.

Reasoning

Although the Plaintiff submitted an outstanding rent figure of Kshs 3 million, the record showed the Defendant paid Kshs 1 million (paid via Mr Anders Ostman) and the Plaintiff had written off Kshs 419,000/- in the 25th January 2017 mediation agreement. The court therefore awarded the adjusted balance of Kshs 2 million plus January 2017 rent of Kshs 210,000/-, totalling Kshs 2,210,000/-.

p. 3
02

Claim for Kshs 700,000/- repair set-aside

Holding

Awarded to the Plaintiff because the Defendant carried out repairs without authority and failed to produce receipts accounting for the monies.

Reasoning

The lease provided that Kshs 70,000/- monthly for 10 months (totaling Kshs 700,000/-) would be withheld from rent and applied to approved repairs, a condition precedent being the Plaintiff's written approval. The Defendant claimed to have done repairs but without authority and without accounting for the sums by way of receipts, so the Plaintiff was entitled to the amount.

p. 3
03

Restoration costs for unauthorized alterations

Holding

Kshs 2,024,500/- awarded as itemized in the bills of quantities from Kurstan Builders presented in court.

Reasoning

The Plaintiff testified that the Defendant extensively and unauthorizedly demolished and altered the house - reducing it from 3 to 2 bedrooms, demolishing the pantry, removing fittings and mahogany finishes - contrary to the lease. The claim was supported by photographs and an itemized quotation from Kurstan Builders, and the court found the Plaintiff entitled to the restoration cost.

p. 3
04

Utility bills (electricity and water)

Holding

Kshs 135,000/- for electricity and Kshs 6,000/- for water were pleaded and proved and form part of the total award.

Reasoning

In setting out the total amount pleaded and proved, the court listed electricity at Kshs 135,000/- and water bill at Kshs 6,000/- alongside rent arrears and restoration costs, and these amounts are subsumed in the aggregate judgment sum of Kshs 5,075,500/-.

p. 3

Legal principles established

#
  • A claim in a first-instance civil suit is determined on a balance of probability, even in formal proof proceedings after an unrepresented/unresponsive defendant.
  • A tenant who undertakes works/repairs without the landlord's written authority and fails to account for them in form of receipts remains liable for the agreed repair set-aside.

Court orders

#
  1. 1.Judgment entered for the Plaintiff in the sum of Kshs 5,075,500/-
  2. 2.The costs of the suit to be paid by the Defendant

Authorities

#

Legislation

  • Civil Procedure Rules 2010Order 10 rule 4
Jurisdiction invoked
Original civil jurisdiction; suit instituted by plaint under the Civil Procedure Act and Civil Procedure Rules 2010

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kipkai Enterprises Ltd v Maurine Louise Osembe [2017] KEELC 1624 (KLR)", Case Analysis (2017). Not stated in judgment (plaint dated 31st May 2016). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2017/1624/eng@2017-09-22

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.