ELCAllowedNot stated in judgment (Notice of Motion dated 14th February, 2017)· [2017] KEELC 1550 (KLR)

Isaac Chebon & 4 others v County Government of Baringo [2017] KEELC 1550 (KLR)

Environment and Land Court
25 September 2017
1,659 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~7 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court stopped Baringo County from building a cattle dip because its environmental assessment was never approved by NEMA.

What this practically means

#

Executive summary

#
The Plaintiffs, owners of neighbouring plots within a human settlement, moved the court by Notice of Motion dated 14th February 2017 seeking a temporary injunction restraining the County Government of Baringo from constructing a cattle dip on plot No. BARINGO/KEWAMOI 'B'/856 until an Environmental Impact Assessment was given. They argued the dip, five metres from their church and near a water spring used as a shrine and catchment, would endanger health and pollute the environment, and that no EIA had been approved. The Defendant opposed, asserting the suit land was a public utility reserved for a cattle dip, that the EIA report had been approved by NEMA, that an expert report could not be discredited by affidavit, and that the plaintiffs should have filed judicial review or a constitutional petition. The court first rejected the forum objection, holding that only gross defects going to the root of the suit warrant upholding a preliminary objection on form, guided by Article 159 on procedural technicalities. On the merits, applying the settled principles in Giella v Cassman Brown, the court found the NEMA letter of 21st March 2017 merely acknowledged the private EIA report by Lead Securities Ltd and directed that no development proceed pending review; no approval letter existed. The plaintiffs thus established a prima facie case with a probability of success, and in an environmental pollution context damages would not be adequate compensation. The application succeeded, with a temporary injunction granted and costs awarded to the plaintiff.

Key legal issues

#
01

Choice of forum - whether the suit should have been brought by judicial review or constitutional petition

Holding

The objection was rejected; the court may determine the matter in the form brought unless the defect is gross and goes to the root of the suit.

Reasoning

The court treated the forum objection as a halfhearted preliminary objection. It held that a preliminary objection for lack of form can only succeed if the defect is gross and prevents a just decision, and Article 159 obliges the court to disregard procedural technicalities, so the plaintiff's choice of a civil suit for injunction was proper.

p. 3
02

Prima facie case

Holding

Established - NEMA had only acknowledged receipt of the EIA report and directed that no development proceed until it communicated its assessment; no approval letter existed.

Reasoning

The defendant itself annexed NEMA's letter of 21/3/17, which acknowledged the report by Lead Securities Ltd and stated it would be reviewed under the EIA and Audit Regulations 2003, directing that no development commence in the interim. No go-ahead letter existed, so the EIA had not been approved and the plaintiffs' environmental and health concerns gave a probability of success.

p. 3
03

Irreparable injury / adequacy of damages

Holding

Damages would not adequately compensate for harm from environmental pollution affecting health.

Reasoning

Given the prima facie case and the environmental pollution context, the court reasoned that monetary compensation for health effects of pollution would be inadequate, since medical costs cannot guarantee cure. This disposed of the second Giella criterion in favour of injunctive relief.

p. 3

Legal principles established

#
  • An Environmental Impact Assessment report is merely a proposal until reviewed and approved by NEMA; development may not commence until NEMA communicates its approval.
  • A preliminary objection based on form will only be upheld where the defect is gross and goes to the root of the suit; the court must not sacrifice substantive justice to procedural technicalities under Article 159.
  • In environmental pollution cases, damages are generally not an adequate remedy.

Court orders

#
  1. 1.Temporary injunction restraining the defendant, its employees, servants and/or agents from constructing a cattle dip on plot No. BARINGO/KEWAMOI 'B'/856 until an Environmental Impact Assessment is given
  2. 2.Costs of the application awarded to the plaintiff

Authorities

#

Legislation

  • Constitution of KenyaArticle 159
  • Environmental Impact Assessment and Audit Regulations2003

Cases cited (6)

  • Giella -v- Cassman Brown & Co. Ltd
    [1973] E.A 358
  • Ibrahim –v- Sheik Bros Investments Ltd
    [1973] EA 118
  • Mrao Ltd –v- First American Bank Ltd & 2 others
    [2002] LLR 3801
  • Bonde –v- Steyn
    [2013] 2 EA 8
  • The Despina Pontikos
    [1975] EA 38
  • Locabail Intern Finance –v- Agro Export & others
    [1986] 1 All ER 901
Jurisdiction invoked
Original jurisdiction of the Environment and Land Court; Article 159 of the Constitution invoked on procedural technicalities

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Isaac Chebon & 4 others v County Government of Baringo [2017] KEELC 1550 (KLR)", Case Analysis (2017). Not stated in judgment (Notice of Motion dated 14th February, 2017). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2017/1550/eng@2017-09-25

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.