Brit Ahlfert v Nawaz Mussa t/a Hash Construction [2016] KEELC 1124 (KLR)
The bottom line
#A Kenyan court ordered a construction contractor to refund money paid for unfinished work and pay damages for breach of contract.
What this practically means
#Executive summary
#Key legal issues
#Breach of construction contract and refund of unutilised payment
The defendant breached the contract by failing to complete the works; the unutilised 30% payment must be refunded less the value of work done in excess of the deposit
The court accepted the plaintiff's evidence and that of PW2, a quantity surveyor, that works done were valued at Kshs.10,665,202 against a contract sum of Kshs.21,348,362. Only the 50% deposit (USD 130,000) and a further USD 77,302 were paid, leaving about USD 68,698 unpaid, which could not have completed the works. Deducting USD 7,400 of overpayment gave a refund of USD 69,902.
General damages for breach of contract
General damages of Kshs.500,000 awarded for the defendant's breach
Having found the defendant did not fulfil his contractual obligations, the court condemned him to pay general damages and assessed Kshs.500,000 as sufficient in the circumstances.
Standard and burden of proof in a claim undefended at hearing
The plaintiff proved her case on a balance of probabilities even though the defendant had filed a defence and counterclaim
The defendant's advocates ceased acting and the defendant neither appeared nor called evidence. The plaintiff produced the contract and photographs, and PW2's assessment corroborated her claim that only about half the works had been done. The defence assertion of 80% completion was unsupported by evidence.
Legal principles established
#- A contractor who fails to complete works under a construction contract and is overpaid must refund the unutilised sums and is liable in general damages for breach of contract
Court orders
#- 1.Judgment for the Plaintiff against the Defendant for overpayment of USD 69,902
- 2.General damages of Kshs.500,000 for breach of contract
- 3.Costs of the suit to the plaintiff
- Jurisdiction invoked
- Original civil jurisdiction of the High Court (contract claim for USD 77,302 plus interest and costs)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Brit Ahlfert v Nawaz Mussa t/a Hash Construction [2016] KEELC 1124 (KLR)", Case Analysis (2016). HCCC No. 13 of 2013. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2016/1124/eng@2016-02-24
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.