ELCPartially Allowed· [2016] KEELC 503 (KLR)

Patrick Kamotho Githinji & 4 others (suing for and on behalf of aggrieved residents of Muthurwa Estate within Nairobi County) v Resjos Enterprises Ltd & 4 others [2016] KEELC 503 (KLR)

Environment and Land Court of Kenya
1 July 2016
3,524 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~14 min to read original · ~4 min brief

The bottom line

#

A Nairobi court halted the Muthurwa road project because it started before getting the required NEMA environmental licence, confirming no project is too big to stop.

What this practically means

#

Executive summary

#
This is a ruling on the petitioners' Notice of Motion dated 4th March 2016 seeking a conservatory injunction to restrain the respondents from continuing construction, excavation or related works on the Muthurwa Jogoo Road access project, pending the hearing of their constitutional petition brought under Articles 10, 22, 23, 42 and 70 of the Constitution for enforcement of the right to a clean and healthy environment. The petitioners, residents of Muthurwa Estate, alleged that the respondents commenced the road rehabilitation without an Environmental Impact Assessment licence from NEMA, cut down trees over 85 years old, created a dangerous road diversion through the estate on which a school pupil was fatally hit, and exposed residents to noise and air pollution causing respiratory ailments. The 2nd, 4th and 5th respondents, through Engineer Andrew Amayi Sirkoi, opposed the application, asserting that an Environmental and Social Impact Assessment study had been done, public awareness meetings and questionnaires used, safety measures put in place, and that halting the 50%-complete project would incur public costs. Applying the Rule 23 test of prima facie case, likely prejudice and public interest, the court found the project was being undertaken in breach of EMCA, since works commenced before any NEMA licence issued, and the study report submitted to NEMA after the suit was of no significance until approved. Applying the precautionary principle (in dubio pro natura), the court held the petitioners had a prima facie case and rejected the respondents' public-interest argument, holding that a clean environment is a right for all humanity. The application was allowed on conditional terms.

Key legal issues

#
01

Whether the respondents' commencement of the road project before obtaining an EIA licence breached EMCA and the petitioners' right to a clean and healthy environment

Holding

Yes. The project was required to undergo EIA and obtain an EIA licence before commencement; the respondents commenced works before licensing, and the study report was submitted to NEMA only after the suit was filed, with no licence exhibited.

Reasoning

Section 58 and the Second Schedule of EMCA and the 2013 Regulations required the road project to undergo environmental impact assessment and not commence until licensed by NEMA. The respondents were aware of this requirement but commenced implementation before obtaining the licence. The study report dated 31st March 2016 was submitted to NEMA only after the petition was filed, and much of the public participation occurred during ongoing works. No licence was exhibited. In the absence of NEMA approval, the court could not assess the adequacy of the proposed mitigation measures.

p. 5
02

Whether public participation and the environmental assessment satisfied constitutional requirements

Holding

No. Much of the claimed public participation was conducted after the filing of the suit and while the project was ongoing.

Reasoning

The respondents relied on meetings, questionnaires and an Environmental and Social Impact Assessment Project Study Report to demonstrate public participation and assessment. However, the court noted that much of the participation process in preparing the report took place after the petition was filed on 8th March 2016 and while project execution was ongoing. The report itself, submitted to NEMA on 31st March 2016, remained unapproved, so the adequacy of the mitigation interventions could not be judicially verified.

p. 5
03

Whether public interest in the road project outweighed the petitioners' environmental rights

Holding

No. The right to a clean and healthy environment benefits all humanity and cannot be downgraded to a private right; no public interest justified limiting it in the circumstances.

Reasoning

The respondents argued that the project, 50% complete and costing over Kshs 107 million, was for public good and that halting it would cause delays, extra costs and taxpayer burden. The court rejected the framing of environmental protection as a private interest, holding that the duty to protect the environment is universal. It therefore declined to allow public-interest considerations to justify the respondents' unlawful conduct and lack of licensing.

p. 5
04

Whether the alleged ailments and risks warranted interim relief absent scientific proof of causation

Holding

Yes, by applying the precautionary principle; scientific proof of causation was not required where environmental harm was in doubt.

Reasoning

The court accepted that there was no scientific proof that the residents' ailments directly resulted from the project, but held that the acknowledged impacts in the study report - noise and air pollution, vegetation destruction and accident risks - in the absence of NEMA-approved mitigation measures, justified applying the precautionary principle, resolving doubt in favour of protecting nature. This supported finding a prima facie case.

p. 5

Legal principles established

#
  • An applicant for a conservatory or interim order under Rule 23 must demonstrate a prima facie case, likely prejudice or injury from violation or threatened violation of constitutional rights, and that it would be in the public interest to grant the order
  • A road project of the scale contemplated under Section 58 and the Second Schedule of EMCA and the Environmental (Impact Assessment and Audit) Regulations, 2013 requires an environmental impact assessment and must not commence before an EIA licence is issued by NEMA
  • An environmental impact assessment study report is of no legal significance until approved by NEMA; it is NEMA's duty to verify mitigation measures and ensure post-licensing audit compliance
  • Where there is doubt as to environmental harm, the precautionary principle (in dubio pro natura) applies, resolving doubt in favour of protection and conservation of the environment
  • A right to a clean and healthy environment is a right for the benefit of all humanity and cannot be characterised as a mere private right against which public interest may be weighed

Court orders

#
  1. 1.A conservatory order in the nature of an injunction restraining the 1st, 2nd, 4th and 5th respondents from continuing with any further construction or rehabilitation of access road to Muthurwa Market and bus terminus until they obtain and furnish the court with an Environmental Impact Assessment Licence issued by NEMA in respect of the project and a written report on the measures taken to address the petitioners' concerns regarding public safety and noise and air pollution caused by excessive dust and vehicular traffic through the road diversion within the petitioners' residences
  2. 2.Either party shall be at liberty to apply
  3. 3.The cost of the application shall be in the cause

Authorities

#

Legislation

  • Constitution of KenyaArticles 10, 22, 23, 42, 70(1)
  • Constitution of Kenya (Protection of Rights and Fundamental Freedoms) Practice and Procedure Rules, 2013Rule 23
  • Environmental Management and Co-ordination Act, 1999Section 58 and Second Schedule
  • Environmental (Impact Assessment and Audit) Regulations, 2013Not specified

Cases cited (2)

  • George Odero vs. Lake Victoria Environment Management Programme & others
    [2015] eKLR
  • Gatirau Peter Munya –vs- Dickson Mwenda Kithinji and 2 others
    Petition No. 2 of 2014 [2014] eKLR
Jurisdiction invoked
Articles 10, 22, 23, 42 and 70 of the Constitution; Rule 23 of the Constitution of Kenya (Protection of Rights and Fundamental Freedoms) Practice and Procedure Rules, 2013

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (3)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#