ELCPartially AllowedNot stated in the judgment· [2016] KEELC 495 (KLR)

Mark Mathenge Gikonyo v Raphael Githinji [2016] KEELC 495 (KLR)

Environment and Land Court
13 September 2016
2,328 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~9 min to read original · ~4 min brief

The bottom line

#

A landowner who allowed a house to be built on his land lost his claim and must now pay the builder Kshs.2.1 million.

What this practically means

#

Executive summary

#
The plaintiff, registered owner of LR. No. Sinyerere/Sitatunga Block 1/Mukuyu/204 (about 15 acres), sued for a declaration of sole ownership, a permanent injunction, removal of a fence erected by the defendant, and demolition of a permanent brick house the defendant built on the suitland. The parties' relationship arose from yearly leases of the suitland by the defendant from 1996 to 2012. The defendant, by defence and counter-claim, sought Kshs.2,100,000/= being the valued cost of the house (plus a well and ablution block) he built for the blind plaintiff, or alternatively 4.1 acres of the suitland, contending that on 12/7/2012 they agreed in writing that he would build for the plaintiff in exchange for land equivalent to the value of the improvements. The plaintiff denied any such agreement, claiming he first learnt of the house in September 2012. The court found the plaintiff's denial untruthful: he thumbprinted the written agreement, was present at the November 2012 valuation with his son John Mutua, was photographed in front of the completed house, and lived nearby throughout construction. The court held the plaintiff sanctioned the construction and reneged only after the valuation. It dismissed the plaintiff's suit with costs, found the counter-claim proved on a balance of probability, and entered judgment for the defendant for Kshs.2,100,000/= with interest at court rates from the date of filing the counter-claim, the plaintiff to pay costs of the counter-claim.

Key legal issues

#
01

Whether the house on the suitland was built with the plaintiff's permission and knowledge

Holding

The court found the plaintiff was aware of, and sanctioned, the construction of the house; his denial and the evidence of his son were untruthful

Reasoning

The defendant produced a written agreement dated 12/7/2012 which the plaintiff thumbprinted, drafted in the presence of a village elder. The plaintiff was present at the valuation in November 2012 with photographs taken in front of the completed house. His account of first learning of the house in September 2012 yet appearing willingly at the valuation was internally inconsistent, and his son's evidence contradicted his own. The court concluded the plaintiff knew of and permitted the construction.

p. 3
02

Whether there was an agreement that the defendant be given land equivalent to the value of the house

Holding

The court found such an agreement existed on 12/7/2012, though the plaintiff reneged on it after the valuation

Reasoning

The agreement, reduced to writing in a note book and produced as an exhibit, provided that the defendant would build a house, well and toilet for the plaintiff in return for land equivalent to the value of the house. The plaintiff did not deny thumbprinting it, and evidence from DW3 and DW4 confirmed he was known as Michael Ndegwa, the named party to the agreement. The court found the plaintiff reneged after the valuation of Kshs.2,100,000/=.

p. 3
03

Whether the defendant was entitled to Kshs.2,100,000/= under his counter-claim

Holding

Judgment was entered for the defendant in terms of prayer (a) of the counter-claim for Kshs.2,100,000/= with interest and costs

Reasoning

The house was valued by a professional valuer (DW5 Francis Kariuki) in the presence of the plaintiff and his son John Mutua; the valuer testified and explained his methodology, and the valuation report was produced as defence exhibit 3. The claim was duly pleaded as a special claim and the court found it proved on a balance of probability.

p. 4

Legal principles established

#
  • A party who stands by and watches construction proceed to completion before claiming his rights were violated cannot obtain demolition or injunctive relief; equity will not aid such conduct
  • A plaintiff who reneges on an agreement to convey land equivalent to the value of improvements must instead pay the monetary value of those improvements
  • A counterclaim based on a valuation pleaded as a special claim, proved by the professional valuer who made it, is proved on a balance of probability

Court orders

#
  1. 1.Dismissal of the plaintiff's suit with costs to the defendant
  2. 2.Judgment for the defendant in terms of prayer (a) of the counter-claim (Kshs.2,100,000/= being the value of the house)
  3. 3.Plaintiff to pay costs of the counter-claim
  4. 4.Interest on Kshs.2,100,000/= at court rates from the date the counter-claim was filed
Jurisdiction invoked
Original civil jurisdiction over a land dispute (suit and counter-claim); no specific constitutional/statutory provision cited in the judgment

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Mark Mathenge Gikonyo v Raphael Githinji [2016] KEELC 495 (KLR)", Case Analysis (2016). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2016/495/eng@2016-09-13

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.