Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedNot stated in judgment· [2016] KEELC 133 (KLR)

Stephen Muriithi Mathenge v S.S.Mehta & Sons Ltd [2016] KEELC 133 (KLR)

Environment & Land Court
8 November 2016
3,685 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~15 min to read original · ~4 min brief

The bottom line

#

A Kenyan court ordered a road contractor to restore land and pay Kshs. 610,530 after it excavated murram far deeper than the contract allowed.

What this practically means

#

Executive summary

#
The plaintiff owned two adjacent parcels in Dundori, Nakuru, and by an agreement dated 8 March 2011 allowed the defendant, a road construction company, to excavate murram over 0.68 acres at Kshs. 300,000/= per acre, to a maximum depth of 2m below the existing river bed, with the pit to be left open as an earth dam. The plaintiff sued, alleging the defendant excavated 8m deep, destroyed trees and fencing, and diverted a river through his land. He sought Kshs. 119,885/= for fencing and survey fees, a mandatory injunction to re-route the river, replant trees and slope the pit, Kshs. 610,530/= for the excess murram, and costs. The defendant denied breach, claiming it excavated less than the agreed area, that the plaintiff supervised and then frustrated the works, and that no fencing or sloping obligation existed. The court relied on the plaintiff's uncontradicted topographical survey showing excavation to 8m below the river bed, holding the river bed a fixed base level unaffected by the slope of the land, and found breach. It found no evidence of destruction of trees or fences beyond the excavation area and no contractual or EIA obligation to fence, replant or back-slope, the agreement having contemplated the pit being left open as a 2m-deep earth dam for the plaintiff. It inferred the river was re-routed by the defendant's activities and ordered restoration. Final orders: back-fill to 2m below the original river bed, re-route the river, both under NEMA supervision within 90 days; award of Kshs. 22,000/= surveyor's fees and Kshs. 610,530/= for excess murram payable within 30 days; no orders on fencing or replanting; costs to the plaintiff.

Key legal issues

#
01

Whether excavation exceeded the agreed depth of 2m below the river bed

Holding

The defendant breached the agreement by excavating to 8m below the river bed

Reasoning

The plaintiff's topographical survey by PW-2 showed excavation to 8m below the original river course. The defendant called no expert report to contradict it and conceded it had none. The court held the river bed is a fixed base level, so the sloping of the land created no ambiguity; excavation went beyond the agreed 2m.

p. 4
02

Whether the defendant was obliged to fence, replant or back-slope the site

Holding

No such obligations arose from the agreement or the EIA

Reasoning

The agreement provided that upon termination the defendant would not back-fill but leave the area open with 2m depth as an earth dam for the owner's use. There was no term on fencing, replanting or back-sloping, and the EIA contained no environmental management plan for site B. Since the site was to be handed to the plaintiff, no further obligation could be imposed.

p. 4
03

Whether the defendant destroyed trees and fences

Holding

The allegation was unsupported by evidence

Reasoning

Beyond the plaintiff's word of mouth, no particulars or proof of damage beyond the excavation area were given; the survey report made no mention of damage to vegetation or fences, and no environmental management plan existed to establish such an obligation.

p. 4
04

Whether the defendant re-routed the river

Holding

The court found the river was re-routed by the defendant's quarrying activities and ordered restoration

Reasoning

The surveyor's report showed the river had been re-routed. Though the EIA report did not mention such an impact, the defendant was the party undertaking activities on the land, so the court inferred the diversion resulted from its quarrying, creating a danger to the public requiring restoration under NEMA supervision.

p. 5
05

Entitlement to compensation for excess murram excavated

Holding

Kshs. 610,530/= awarded as restitution for unjust enrichment

Reasoning

Having found the defendant excavated to 8m rather than the agreed 2m, the court held it unjustly enriched itself. The quantum of Kshs. 610,530/= was accepted as consistent with the agreed rate of Kshs. 203,510/= for a 2m depth.

p. 5

Legal principles established

#
  • Where the permissible depth is fixed by reference to the river bed, that river bed is a fixed base level and excavation beyond it is measured against that level regardless of the slope of the land
  • A party who disputes an expert report instructed by the other side should obtain its own expert opinion; failing which the uncontradicted report stands
  • A party undertaking activities on land from which a diversion results bears responsibility for restoring what was diverted

Court orders

#
  1. 1.The defendant is ordered to back-fill the site up to a depth of 2m below the original river bed level
  2. 2.The defendant is ordered to re-route the river back to its original position before the excavation started
  3. 3.Execution of the back-filling and re-routing orders to be supervised by NEMA and done within 90 days
  4. 4.No orders against the defendant to re-do a fence or re-plant vegetation on the site
  5. 5.Award of Kshs. 22,000/= as surveyor's fees and Kshs. 610,530/= as the cost of the excess murram excavated, payable within 30 days
  6. 6.The plaintiff shall have the costs of the suit
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over a dispute relating to land (excavation of murram on titled parcels); no specific constitutional provision cited

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Stephen Muriithi Mathenge v S.S.Mehta & Sons Ltd [2016] KEELC 133 (KLR)", Case Analysis (2016). Not stated in judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2016/133/eng@2016-11-08

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.