The bottom line

#

A Mombasa court settled a land fight by freezing things as they are and sending the county surveyor to check the true boundary beacons.

What this practically means

#

Executive summary

#
The plaintiff/applicant moved the Court under Order 40 and Order 1 of the Civil Procedure Rules and Section 3A of the Civil Procedure Act seeking a temporary injunction to restrain the defendants and/or its employees from dealing with, constructing on, selling, wasting, damaging, intruding upon, trespassing on or interfering with plots Nos. Mombasa Block XIV/147, XIV/162, 177, 192 and 206 pending hearing and determination of the suit. Ex parte interim orders were obtained on 30th May 2013 and extended by consent on 26th August 2013 when parties agreed to dispose of the application by written submissions. Neither party filed submissions as agreed, and the application lingered. Delivering a brief ruling at Mombasa on 24th July 2015, Omollo J observed that the application had been in court unnecessarily long, that the prayers in the plaint made the suit essentially a boundary dispute, that the interim orders had no time limit, and that no party indicated any activity on the ground. Rather than rule on the merits, the Court compromised the application by directing that the status quo obtaining under the interim orders be maintained. The Court also, suo motu, directed the county surveyor – Mombasa, in the presence of the parties and their witnesses, to visit the disputed plots to establish their beacons and record whether the defendant had encroached on them, with the cost of the survey to be shared equally and the report to be filed within 60 days, followed by a mention for further orders.

Key legal issues

#
01

Whether the injunction application should be determined on the merits

Holding

The Court declined to go into the merits, treating the application as compromised and maintaining the status quo under the existing interim orders

Reasoning

The application had been in court unnecessarily long; the parties had failed to file submissions as agreed on 26th August 2013 and the matter was protracted. The Court noted the plaint's prayers made it essentially a boundary dispute, that the interim orders of 30th May 2013 had no time limit, and that no party indicated any ground activity. Rather than rule on the merits, it maintained the status quo and directed a survey by the county surveyor to establish the beacons and any encroachment within 60 days.

p. 2

Legal principles established

#

    Court orders

    #
    1. 1.The application be determined as compromised in terms that the status quo obtaining as a result of the interim orders issued be maintained
    2. 2.The county surveyor – Mombasa, in the presence of the parties and their witnesses if need be, to visit the disputed plots Nos. Mombasa Block XIV/147, 162, 177, 192 and 206 with a view to establishing their beacons and record whether the defendant has encroached on them or not
    3. 3.The cost of the survey, if any, to be shared by both parties equally
    4. 4.The surveyor to visit and file his report within 60 days of service of the order
    5. 5.The matter to be mentioned after sixty days to confirm if the report is filed and for further orders

    Authorities

    #

    Legislation

    • Civil Procedure ActSection 3A
    • Civil Procedure RulesOrder 40
    • Civil Procedure RulesOrder 1
    Jurisdiction invoked
    Sections 3A of the Civil Procedure Act and Order 40 and Order 51 of the Civil Procedure Rules

    Key timeline

    #

    Practical implications

    #

    Frequently asked questions

    #

    Cite this brief

    #

    Cite this brief

    Caselaw, "Swaleh Hussen Sherman Swaleh v Kenya Rural Roads Authority Mombasa [2015] KEELC 231 (KLR)", Case Analysis (2015). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2015/231/eng@2015-07-24

    Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.