Stephen Kibet Malakwen v Benson Gateca Mbugua [2014] KEELC 67 (KLR)
The bottom line
#A Kenyan court ordered a land seller to complete a sale five years late, confirming that written demand letters can legally make timing urgent.
What this practically means
#Executive summary
#Key legal issues
#Whether time was of essence in the sale agreement of 3/2/2009
Although the agreement did not make time of the essence, the plaintiff's demand letters of 6/3/2013 and 11/6/2013, which the defendant received but ignored, constituted valid notices making time of essence; the 5-year delay was unreasonable.
The court applied the Sagoo v Dourado test. The parties did not expressly stipulate time as of essence, but the defendant, who was obliged to subdivide and transfer, took no steps in furtherance of the contract over five years despite two demand letters. A delay of five years was held unreasonable in the circumstances, and the notices validly made time of the essence.
Whether specific performance should be ordered
Specific performance was granted because the plaintiff proved the sale agreement and full payment on a balance of probabilities, took possession and built a maisonette, and nothing disentitled him from the relief.
The defendant conceded the sale and full payment and did not oppose the claim. The defendant failed to prove he had paid land rent and rates, blaming the surveyor without evidence. The plaintiff had taken possession and constructed a residential house. The court found the defence a sham and proved the case on a balance of probabilities.
Legal principles established
#- In contracts of all types, time will not be considered of the essence unless the parties expressly stipulate it, the nature of the subject matter or surrounding circumstances show it, or a party subjected to unreasonable delay gives notice making time of essence.
- A party who has been subjected to unreasonable delay may make time of essence by notice to the party in default.
Court orders
#- 1.An order of specific performance of the agreement for sale dated 3/2/2009 is issued
- 2.The Deputy Registrar is empowered to sign all documents necessary to give effect to the agreement of 3/2/2009 if the defendant will not willingly comply
- 3.The plaintiff shall have costs of the suit
- Jurisdiction invoked
- Environment and Land Court original jurisdiction over contracts for sale of land (ELC), Land Case No. 75 of 2013
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Stephen Kibet Malakwen v Benson Gateca Mbugua [2014] KEELC 67 (KLR)", Case Analysis (2014). Land Case No. 75 of 2013. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2014/67/eng@2014-12-01
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.