AI-generated case brief
Case Brief · caselaw.co.ke
Court of AppealDismissedCivil Appeal (record not expressly numbered in judgment)· [2025] KECA 471 (KLR)

Moniks Agencies Limited v Kenya Airports Authority

Court of Appeal
7 March 2025
8,078 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~32 min to read original · ~4 min brief

The bottom line

#

The Court of Appeal dismissed a clearing agent's Kshs. 124 million claim against Kenya Airports Authority, holding that agreed contract rates bind both parties and cannot be unilaterally changed.

What this practically means

#

Executive summary

#
The appellant, a clearing agent, was awarded Tender No. KAA/ES/JKIA/837B by the Kenya Airports Authority in May 2014 to clear goods for the reconstruction of Terminal 4 at JKIA following the August 2013 fire, at a rate of 0.1% of CIF value. It was later engaged, without a formal written agreement, to clear goods for the construction of Terminal 2. The appellant sued in the High Court claiming commissions of 2.5% and 3% of CIF value, outstanding balances of over Kshs. 51 million, and payment for alleged additional work. The High Court upheld the claim in part, fixing payment at the contracted rates of 0.1% for clearing and 0.4% for bond cancellation and directing payment for extra work upon production of invoices. Both parties appealed. The Court of Appeal, on a first appeal akin to a retrial, framed four issues: the number and terms of the contracts, whether they were altered, whether extra work was done, and the reliefs available. It found two contracts — the written Terminal 4 contract and an unwritten Terminal 2 contract performed on the same terms, inferred from conduct. The only valid alteration was the tender-committee-approved 0.4% rate for bond cancellation under section 47 of the repealed Public Procurement and Disposal Act 2005, which bound both parties. The 60-day period was a tender validity period, not a performance deadline. The alleged extra work fell within the contractual scope, and all invoices raised at the contractual rates had been paid; invoices at 2.5% and 3% did not conform to the agreed rates. The Court dismissed the appeal, allowed the cross-appeal, dismissed the appellant's claim in its entirety, and awarded the respondent the costs of both the appeal and the High Court proceedings.

Key legal issues

#
01

Number and terms of the contracts between the parties

Holding

Two contracts existed: the written Terminal 4 contract at 0.1% of CIF value, and an unwritten Terminal 2 contract performed on the same terms, inferred from the parties' conduct.

Reasoning

The award letter of 8th May 2014 confirmed the Terminal 4 tender at 0.1% of CIF value. For Terminal 2 no written contract existed, but letters, emails, and concurrent oral testimony showed a direct award to the appellant, which performed without protesting the terms. Applying principles on implied contracts, the court held a party cannot refuse terms it silently performed under and later seek to impose new terms.

p. 10
02

Whether the contracts were fundamentally altered

Holding

The only valid alteration was the tender-committee-approved rate of 0.4% of CIF for bond cancellation under section 47 of the repealed Public Procurement and Disposal Act 2005; this did not fundamentally alter the contracts.

Reasoning

Bond cancellation was not part of the original clearing-services contract, as shown by the award letter, the separate 0.4% rate approved by the tender committee, and the respondent's correspondence. The amendment complied with section 47, binding both parties. The alleged 60-day performance period was merely the tender validity period, and the expanded scope claim was addressed under the extra-work issue.

p. 11
03

Whether the appellant performed additional work

Holding

No. The claimed tasks were within the scope of clearing services or bond cancellation and were not payable separately.

Reasoning

The alleged extra services — preparing and correcting documents, cancelling bonds, securing certificates of conformity, tracing consignments, amending shipping documents — fell within the contractual scope per DW1's unrebutted testimony. The appellant never complained of an expanded scope during performance, raised no invoices for extra work, and DW1's reference to an additional assignment concerned the separate Terminal 2 contract, not an admission of extra work.

04

Reliefs and the disposition of the invoices

Holding

All invoices raised at the contractual rates were paid; the appellant's invoices at 2.5% and 3% did not conform to the contractual rates and could not be enforced.

Reasoning

The appellant invoiced Kshs. 58,665,048 using non-contractual rates of 2.5% and 3%; the respondent paid Kshs. 7,038,266 based on invoices at the contracted rates, and that assertion was uncontroverted. A party cannot impose a perceived market rate over an agreed rate. The High Court's direction to pay upon production of invoices was therefore unnecessary, and both the appeal and the plaintiff's claim fail.

p. 14

Legal principles established

#
  • A contract may be inferred from the conduct of the parties even where no written document exists, and where no final document outlines the terms, the court may consider surrounding circumstances including prior contracts between the parties.
  • A procuring entity's contract amendment is effective only if approved in writing by the tender committee, and once so approved the amended rate binds both parties.
  • A party to a contract cannot unilaterally impose a perceived market rate where the parties had mutually agreed on a given rate.
  • On a first appeal the court's mandate is akin to a retrial: it reconsiders and evaluates the evidence and draws its own conclusions, but will not normally interfere with findings of fact unless based on no evidence, misapprehension of the evidence, or wrong principles.
  • The 60-day period in a tender award refers to the validity period of the quotation, not the period for performance of the contract.

Court orders

#
  1. 1.Dismissal of the appellant's appeal
  2. 2.Allowance of the respondent's cross-appeal, with the appellant's claim before the High Court dismissed in its entirety
  3. 3.Costs of the appeal and of the proceedings before the High Court awarded to the respondent
On appeal from
High Court of Kenya
Jurisdiction invoked
First appellate jurisdiction over the High Court (the Court describes it as 'a first appeal' whose mandate 'is akin to a retrial')

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Moniks Agencies Limited v Kenya Airports Authority", Case Analysis (2025). Civil Appeal (record not expressly numbered in judgment). Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2025/471/eng@2025-03-07

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.