Kenya Railways Corporation & 1 other v Milly Glass Works Limited
The bottom line
#Kenya's Court of Appeal threw out a huge rent refund and barred garnishee execution against Kenya Railways, confirming you cannot recover money you never pleaded.
What this practically means
#Executive summary
#Key legal issues
#Jurisdiction under section 83(1) of the Kenya Railways Corporation Act
The trial court had jurisdiction; section 83(1) covers compensation for damage (in tort) caused by the Corporation's exercise of statutory powers, not contractual rent-review disputes.
The Court examined section 83(1), which bars suits and mandates negotiation or statutory arbitration 'where any person suffers damage' from the Corporation's exercise of powers under sections 13, 15, 16 and 17. Adopting the reasoning in prior decisions, the Court held that 'damage' denotes physical harm in the realm of tort. A dispute over the legality of a contractual rent increment under clause 2(a) of a lease is not such damage, so the arbitration mechanism was not triggered and the ELC was properly seised of the matter.
Proof of the 1st January 1994 rent increment
The finding that rent was increased on 1st January 1994 was justified by the 1st appellant's failure to specifically traverse paragraph 9 of the plaint (deemed admission under Order 2 rule 11(3)) and its own evidence that the prior rent was Kshs. 146,000.
Order 2 rule 11(3) requires specific traversal of allegations of fact; a general denial is insufficient and the allegation is deemed admitted. Beyond the tacit admission, the appellants' witness acknowledged the prior rent of Kshs. 146,000 but led no evidence on the date of the increment. In the absence of clear evidence from the 1st appellant, the trial judge was entitled to bind the respondent to its pleading that the increment took effect on 1st January 1994.
Effect of the 1994 early rent revision on the lease's review dates
The 1994 revision did not vary clause 2(a); the next review dates remained the 30th and 60th anniversaries of the lease term, and the 2012 revision notice was valid.
The lease was silent on the effect of an early revision. Applying Halsbury's rent-review principles and the principle that contracts yield to business common sense, the Court held that an unconditional early revision not anchored on an express variation left clause 2(a) intact; the review date is computed from the term's commencement. The respondent's acquiescence in and payment of the 1994 rent, without challenge within the six-year limitation period under section 4(1) of the Limitation of Actions Act, barred any belated claim based on that revision.
Refund for unjust enrichment and failure to quantify
The refund order was set aside: no prayer or specific pleading for refund existed, the sums were not strictly proved, and the quantum could not be left to the parties.
The plaint sought only declaratory and injunctive relief; the respondent admitted by application that refund was not pleaded. Unquantified pecuniary loss is special damage which must be specifically pleaded and strictly proved. The trial court's order delegating computation to the parties also offended the rule that a judgment must be complete and the determination of quantum is a judicial function. The trial court therefore had no jurisdiction to award the unpleaded, unquantified refund.
Garnishee execution against the Corporation under section 88
Section 88 of the Act places the Corporation's assets, including its bank deposits, beyond reach of execution or garnishment; the trial court's orders permitting attachment were set aside.
Section 88(a) provides that no execution or attachment or process in the nature thereof shall issue against the Corporation, while the Managing Director must pay decretal sums from the Corporation's revenue. Following Hezron Ossorey Jura, Ernest Morara Mokua and Postal Corporation of Kenya v Ndarua, the Court held the Corporation's money in a bank account is its 'property' and cannot be garnished; the statutory remedy is against the Managing Director. The Court acknowledged the access-to-justice concerns but held the mischief's solution lies with the legislature.
Legal principles established
#- Section 83(1) of the Kenya Railways Corporation Act applies only to compensation for physical damage suffered in the exercise of the Corporation's statutory powers (torts), and does not oust the court's jurisdiction over contractual disputes such as rent review
- Section 88 of the Kenya Railways Corporation Act prohibits execution or attachment, including garnishee proceedings, against the Corporation's assets and bank deposits; the remedy lies against the Managing Director to pay from the Corporation's revenue
- A court cannot award relief that was neither prayed for nor specifically pleaded and strictly proved; unquantified sums akin to special damages must be specifically pleaded and strictly proved
- An early rent revision outside the terms of a lease does not, without evidence of a mutual variation, reschedule the contractual rent review dates; an unchallenged early revision may constitute waiver/acquiescence of any right to contest it, subject to the limitation period
- A court of law cannot re-write a contract between the parties; parties are bound by the terms of their contract unless coercion, fraud or undue influence are pleaded and proved
Court orders
#- 1.The 1st appellant's appeal from the judgment and decree of the ELC (M. Sila, J.) dated 4th November 2021 succeeds and the said judgment and decree are set aside
- 2.The appellants' appeal against the ruling and orders of the ELC (M. Sila, J.) dated 1st November 2022 succeeds and the said ruling and orders are set aside
- 3.The costs of the two consolidated appeals to be borne by the respondent
- On appeal from
- Environment and Land Court at Mombasa
- Mombasa ELC No. 135 of 2012
- Jurisdiction invoked
- First appellate jurisdiction under the Constitution and law of Kenya over appeals from the Environment and Land Court
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief