Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
Court of AppealPartially AllowedCivil Appeal No. E083 of 2022 (consolidated with Civil Appeal No. E035 of 2023)· [2024] KECA 1482 (KLR)

Kenya Railways Corporation & 1 other v Milly Glass Works Limited

Court of Appeal of Kenya
25 October 2024
15,955 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~64 min to read original · ~4 min brief

The bottom line

#

Kenya's Court of Appeal threw out a huge rent refund and barred garnishee execution against Kenya Railways, confirming you cannot recover money you never pleaded.

What this practically means

#

Executive summary

#
This is one judgment of a three-judge bench of the Court of Appeal at Mombasa (Murgor, Laibuta and Odunga, JJ.A) determining two consolidated appeals by Kenya Railways Corporation and its auctioneer against decisions of the Environment and Land Court (M. Sila, J.) in a dispute over rent review of an 81-year lease of Mombasa/Block XLVIII/134. The trial court had upheld its own jurisdiction, invalidated the Corporation's 2011 notice raising rent from Kshs. 146,000 to Kshs. 10,200,000, ordered a refund of all rent paid above Kshs. 146,000 per year, and later permitted garnishee execution against the Corporation's bank account. The Court of Appeal allowed both appeals and set aside both decisions. It held that section 83(1) of the Kenya Railways Corporation Act, which channels 'damage' claims to negotiation and arbitration, applies only to tortious physical damage and did not oust the ELC's jurisdiction over this contractual dispute. However, the early 1994 rent revision did not vary clause 2(a) of the lease; the respondent acquiesced in it and any claim was statute-barred under section 4(1) of the Limitation of Actions Act, so the September 2011 review with effect from January 2012 was a valid exercise of the Corporation's contractual right. The refund order also fell because the claim was neither pleaded, prayed for, nor strictly proved, and quantum cannot be delegated to the parties. Finally, section 88(a) of the Act bars all execution, attachment and garnishee proceedings against the Corporation, including against its bank deposits; the decree-holder's remedy is the Managing Director's statutory duty to pay from the Corporation's revenue. The respondent was ordered to bear the costs of both appeals. These holdings now bind the ELC and subordinate courts.

Key legal issues

#
01

Jurisdiction under section 83(1) of the Kenya Railways Corporation Act

Holding

The trial court had jurisdiction; section 83(1) covers compensation for damage (in tort) caused by the Corporation's exercise of statutory powers, not contractual rent-review disputes.

Reasoning

The Court examined section 83(1), which bars suits and mandates negotiation or statutory arbitration 'where any person suffers damage' from the Corporation's exercise of powers under sections 13, 15, 16 and 17. Adopting the reasoning in prior decisions, the Court held that 'damage' denotes physical harm in the realm of tort. A dispute over the legality of a contractual rent increment under clause 2(a) of a lease is not such damage, so the arbitration mechanism was not triggered and the ELC was properly seised of the matter.

p. 11
02

Proof of the 1st January 1994 rent increment

Holding

The finding that rent was increased on 1st January 1994 was justified by the 1st appellant's failure to specifically traverse paragraph 9 of the plaint (deemed admission under Order 2 rule 11(3)) and its own evidence that the prior rent was Kshs. 146,000.

Reasoning

Order 2 rule 11(3) requires specific traversal of allegations of fact; a general denial is insufficient and the allegation is deemed admitted. Beyond the tacit admission, the appellants' witness acknowledged the prior rent of Kshs. 146,000 but led no evidence on the date of the increment. In the absence of clear evidence from the 1st appellant, the trial judge was entitled to bind the respondent to its pleading that the increment took effect on 1st January 1994.

p. 13
03

Effect of the 1994 early rent revision on the lease's review dates

Holding

The 1994 revision did not vary clause 2(a); the next review dates remained the 30th and 60th anniversaries of the lease term, and the 2012 revision notice was valid.

Reasoning

The lease was silent on the effect of an early revision. Applying Halsbury's rent-review principles and the principle that contracts yield to business common sense, the Court held that an unconditional early revision not anchored on an express variation left clause 2(a) intact; the review date is computed from the term's commencement. The respondent's acquiescence in and payment of the 1994 rent, without challenge within the six-year limitation period under section 4(1) of the Limitation of Actions Act, barred any belated claim based on that revision.

p. 18
04

Refund for unjust enrichment and failure to quantify

Holding

The refund order was set aside: no prayer or specific pleading for refund existed, the sums were not strictly proved, and the quantum could not be left to the parties.

Reasoning

The plaint sought only declaratory and injunctive relief; the respondent admitted by application that refund was not pleaded. Unquantified pecuniary loss is special damage which must be specifically pleaded and strictly proved. The trial court's order delegating computation to the parties also offended the rule that a judgment must be complete and the determination of quantum is a judicial function. The trial court therefore had no jurisdiction to award the unpleaded, unquantified refund.

p. 26
05

Garnishee execution against the Corporation under section 88

Holding

Section 88 of the Act places the Corporation's assets, including its bank deposits, beyond reach of execution or garnishment; the trial court's orders permitting attachment were set aside.

Reasoning

Section 88(a) provides that no execution or attachment or process in the nature thereof shall issue against the Corporation, while the Managing Director must pay decretal sums from the Corporation's revenue. Following Hezron Ossorey Jura, Ernest Morara Mokua and Postal Corporation of Kenya v Ndarua, the Court held the Corporation's money in a bank account is its 'property' and cannot be garnished; the statutory remedy is against the Managing Director. The Court acknowledged the access-to-justice concerns but held the mischief's solution lies with the legislature.

p. 25

Legal principles established

#
  • Section 83(1) of the Kenya Railways Corporation Act applies only to compensation for physical damage suffered in the exercise of the Corporation's statutory powers (torts), and does not oust the court's jurisdiction over contractual disputes such as rent review
  • Section 88 of the Kenya Railways Corporation Act prohibits execution or attachment, including garnishee proceedings, against the Corporation's assets and bank deposits; the remedy lies against the Managing Director to pay from the Corporation's revenue
  • A court cannot award relief that was neither prayed for nor specifically pleaded and strictly proved; unquantified sums akin to special damages must be specifically pleaded and strictly proved
  • An early rent revision outside the terms of a lease does not, without evidence of a mutual variation, reschedule the contractual rent review dates; an unchallenged early revision may constitute waiver/acquiescence of any right to contest it, subject to the limitation period
  • A court of law cannot re-write a contract between the parties; parties are bound by the terms of their contract unless coercion, fraud or undue influence are pleaded and proved

Court orders

#
  1. 1.The 1st appellant's appeal from the judgment and decree of the ELC (M. Sila, J.) dated 4th November 2021 succeeds and the said judgment and decree are set aside
  2. 2.The appellants' appeal against the ruling and orders of the ELC (M. Sila, J.) dated 1st November 2022 succeeds and the said ruling and orders are set aside
  3. 3.The costs of the two consolidated appeals to be borne by the respondent
On appeal from
Environment and Land Court at Mombasa
Mombasa ELC No. 135 of 2012
Jurisdiction invoked
First appellate jurisdiction under the Constitution and law of Kenya over appeals from the Environment and Land Court

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kenya Railways Corporation & 1 other v Milly Glass Works Limited", Case Analysis (2024). Civil Appeal No. E083 of 2022 (consolidated with Civil Appeal No. E035 of 2023). Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2024/1482/eng@2024-10-25

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.