Mugambi v Electricity Transmission Company Ltd (KETRACO) (Civil Appeal 205 of 2018) [2023] KECA 1048 (KLR)
The bottom line
#A landowner's appeal against a KETRACO power line easement was struck out because it was filed late, so the original court's decision stands.
What this practically means
#Executive summary
#Key legal issues
#Timeliness of institution of the appeal and the operation of the proviso to Rule 84(1)
The proviso to Rule 84(1) could not be invoked because the appellant's letter bespeaking proceedings was written about 100 days after judgment, outside the 30-day window, and was not served on the respondent; the record of appeal was therefore filed out of the statutory time
Rule 84(1) requires an appeal to be instituted within 60 days of the notice of appeal. The proviso excludes certified-preparation time only where the application for proceedings is made in accordance with Rule 84(2), i.e. in writing within 30 days and served on the respondent. The appellant wrote to the trial court roughly 100 days after judgment and did not copy the letter to the respondent, so the proviso was unavailable.
Consequence of failure to institute the appeal in time and absence of an extension-of-time application
Without an extension under Rule 4, the notice of appeal died after 60 days and, under Rule 85(1), the appeal is deemed withdrawn; the appellant is liable for costs under Rule 85(2)
Once out of time, the appellant's only recourse was an application under Rule 4 for extension of time, which was never made. Rule 85(1) then deems the notice of appeal withdrawn, and Rule 85(2) makes the defaulting party liable to pay costs. The court applied this scheme to deem the notice withdrawn and to award the respondent costs.
Legal principles established
#- To rely on the proviso to Rule 84(1) of the Court of Appeal Rules excluding time for preparation of proceedings, the appellant must apply for the copy in writing within 30 days of the decision and serve that application on the respondent
- Where an appellant fails to institute an appeal within the appointed time, the notice of appeal lapses and the appeal is deemed withdrawn under Rule 85(1); a party in default must move under Rule 4 for extension of time
Court orders
#- 1.The notice of appeal lodged following the judgment delivered on February 14, 2018 is deemed to have been withdrawn
- 2.The appellant shall pay to the respondent the costs of this appeal
- On appeal from
- Environment and Land Court at Meru
- Not stated in the judgment
- Jurisdiction invoked
- First appellate jurisdiction under the Court of Appeal Rules, 2022; appeal against the judgment of the Environment and Land Court
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Mugambi v Electricity Transmission Company Ltd (KETRACO) (Civil Appeal 205 of 2018) [2023] KECA 1048 (KLR)", Case Analysis (2023). Civil Appeal No 205 of 2018. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2023/1048/eng@2023-08-24
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.