Court of AppealDismissedCivil Appeal No. 5 of 2018· [2020] KECA 296 (KLR)

Synresins Limited v Pravin Vora t/a Vora Construction [2020] KECA 296 (KLR)

Court of Appeal
9 October 2020
3,490 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~14 min to read original · ~4 min brief

The bottom line

#

Kenya's Court of Appeal upheld a Kshs. 5 million damages award against a property developer whose sloppy record-keeping and improper contract termination backfired completely.

What this practically means

#

Executive summary

#
This was a first appeal against the judgment of Sergon, J. delivered on 19th February 2016 in H.C.C.C No. 1095 of 2003, in which the High Court dismissed Synresins Limited's claim for a refund of an alleged overpayment of Kshs. 5,328,566.75, found the appellant in breach of a construction contract for office blocks and warehouses, and awarded the respondent Pravin Vora t/a Vora Construction Kshs. 5,000,000 in damages for breach, while rejecting the respondent's counterclaim for Kshs. 7,301,683.50 for work done. The appellant raised nine grounds, principally that the Judge disregarded the contract, wrongly awarded damages at large, and erred in finding no privity between the appellant and Vora Construction Co. Limited; the respondent cross-appealed for the balance of the value of work done. The Court of Appeal, re-evaluating the evidence as a first appellate court, held that the penalty clause for delayed handover presupposed that delay per se did not terminate the contract, that the appellant was responsible for obtaining Nairobi City Council approvals whose absence stopped the works, and that it was the appellant who improperly brought the contract to an end. The Court upheld the Kshs. 5,000,000 damages award, holding that the contract provided no measure for general breach, leaving damages to judicial assessment. Both the claim of overpayment and the counterclaim failed on proof: the appellant's payment figures were contradictory and unexplained, while the respondent's valuation lacked support from any quantity surveyor, independent valuer or architect's certificate. The appeal and cross-appeal were both dismissed, with each party bearing their own costs.

Key legal issues

#
01

Which party was in breach of the construction contract

Holding

The appellant, not the respondent, was in breach; the appellant failed to obtain City Council approvals, delayed and irregularly made payments, and brought the contract to an end without following its terms.

Reasoning

The Council stopped excavation because building plans, for which the client was responsible, were unapproved. The respondent remained on site, as shown by correspondence, and the appellant brought another contractor on site and evicted the respondent without properly following the contract. Delay alone, given the penalty clause, did not justify termination.

p. 4
02

Whether the Kshs. 5,000,000 damages award was excessive

Holding

The award stood; clause 1(ii) covered only early or late handover, not general breach, so damages were assessable at large and the appellant failed to show excessiveness.

Reasoning

The contract's penalty/bonus provision addressed only early or delayed handover, not breach generally. With no contractual measure, the trial judge had discretion to assess damages, considered appropriate authorities, and the appellate court found no basis to interfere.

p. 4
03

Whether the respondent proved the counterclaim of Kshs. 7,301,683.50 for work done

Holding

The counterclaim failed for lack of proof; only a self-made schedule was produced, unsupported by independent professional valuation.

Reasoning

The respondent produced only its own evaluation of the work done, without a Quantity Surveyor's report, independent valuation or architect's certificate, and no payment certificates were produced. The learned Judge was right to reject the counterclaim, and the cross-appeal was dismissed.

p. 4
04

Whether the appellant proved its claim of overpayment of Kshs. 5,328,566.75

Holding

The claim failed; the appellant's own figures were contradictory and unsupported by evidence.

Reasoning

The Robi & Partners letter lacked testimonial support and did not reflect overpayment; the accounts attached to a payment letter were unexplained and their maker unidentified; the appellant's witness gave inconsistent payment figures differing from the plaint. No evidence explained the contradictions.

p. 4

Legal principles established

#
  • On a first appeal, the Court of Appeal's role is to re-evaluate, re-assess and re-analyze the evidence and make its own conclusions, while remaining conscious that it did not see or assess the witnesses' demeanour.
  • A penalty clause for delayed handover does not entitle a party to terminate for delay; it presupposes that delay attracts the penalty rather than termination.
  • Where a contract lacks a clause governing damages for breach, the trial judge has discretion to assess and award damages at large.

Court orders

#
  1. 1.The appeal is dismissed
  2. 2.The cross-appeal is dismissed
  3. 3.Each party to bear their own costs

Authorities

#

Cases cited (4)

  • Caltex Oil Kenya Ltd. vs Evanson Njiiri Wanjihia
    [2017] eKLR
  • Sun Sand Dunes Ltd vs Raiya Construction Ltd
    [2018] eKLR
  • David Mose Gekara vs Hezron Nyachae
    [2012] eKLR
  • Kenya Ports Authority vs. Kuston (Kenya) Limited
    [2009] 2 EA 212
On appeal from
High Court of Kenya at Nairobi
H.C.C.C No. 1095 of 2003
Jurisdiction invoked
First appeal to the Court of Appeal under the Constitution of Kenya, 2010 and the Court of Appeal Act

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Synresins Limited v Pravin Vora t/a Vora Construction [2020] KECA 296 (KLR)", Case Analysis (2020). Civil Appeal No. 5 of 2018. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2020/296/eng@2020-10-09